Apparatus and process for separating a material in fluidized bed form and the detection of clogging
AssigneeAluminum Pechiney
InventorRene C. Rambaud
Life of this patent
Estimating the term…
Abstract
Apparatus and method for handling pulverulant material in fluidized bed form. The material is fed into the upper part of a two-part container, whose lower part consists of two independent volumes separated from the upper part by a porous wall comprising two horizontal parts at different levels. A pressure gap is created between the two separate volumes, and the evolution of this gap enables clogging to be detected. When the pressure differential exceeds a predetermined value, the porous wall is cleaned.
Claims5
Apparatus for handling pulverulent material in a fluidized bed mixed with non-fluidizable products and equipped with a clogging detection system comprising:
- (a) pulverulant material storage means (13);
- (b) fluidization means constituted by a two-part container (14) comprising an upper part having a first end connected to said storage means by a supply column (15) and a second end connected to a balancing column (16), and comprising a lower fluidization gas supply part separated from said upper part by first and second porous walls (19, 21);
- and
- (c) means for discharging pulverulent material located in said upper part of said container, at the end opposite to said supply column;
- (d) said first porous wall (19) being located below said supply column and in an area adjacent thereto, and said second porous wall (21) being located below said balancing column and in an area adjacent thereto, said first porous wall (19) being located at a horizontal level below that of said second porous wall (21);
- (e) said lower part of said container being subdivided into first and second independent volumes (18, 20) respectively located below each of said porous wall, said first independent volume (18) and said first porous wall (19) being separated from said second independent volume (20) and said second porous wall (21) by a vertical non-porous wall (11);
- (f) each of said independent volumes being supplied with fluidization gas by a common pipe (22) subdivided into two branches (23, 24);
- and
- (g) in order to detect pressure increases in said first volume (18) caused by clogging above said first porous wall (19), said apparatus comprises means for measuring and recording, as a function of time, a difference in pressure between said first and second independent volumes.
Process for detection of clogging in apparatus for handling pulverulent material in a fluidized bed mixed with non-fluidizable products, said process comprising the steps of:
- (a) feeding pulverulent material from storage means (13) through a supply column (15) into an upper part of a two-part container (14), said upper part having a first end connected to a supply column (15) and a second end connected to a balancing column (16), a lower part of said container consisting of first and second independent volumes (18, 20) respectively separated from said upper part by first and second porous walls (19,21 ) a horizontal level of said first porous wall (19) being lower (18) located below said supply column being lower than a horizontal level of said second porous wall (21) located below said balancing column (2), said first independent volume (18) and said first porous wall (19) being separated from said second independent volume (20) and said second porous wall (21) by a vertical non-porous wall (11);
- (b) supplying fluidization gas by a common pipe (22) subdivided into two branches (23, 24) into said first and second independent volumes (18, 20) in order to create a fluidized bed in said upper part of said container;
- (c) discharging said pulverulent material in said upper part of said container at the end opposite to said supply column;
- (d) continuously checking for an increase in pressure differential between said first and second independent volumes (18, 20) of said lower part constituting the fluidization means;
- and
- (e) cleaning said first porous wall (19) separating the lower fluidization gas supply from said upper part when said pressure differential exceeds a predetermined value.
Dependencies are inferred from the claim text.