Method and system for managing critical parameters of assembly of pressure boundary bolted flanged joints (1) having a gasket (9) between sealing surfaces (11,12) of flanges (2,3). Bolt load, applied load, turn of nut or bolt head, joint misalignment and flange gap closure can be monitored and controlled concurrently during assembly to indicate if joint assembly is unacceptable and/or whether assembly/component requires rectification. A field control unit (23) has a portable electronic processor (21) and a data acquisition and control unit (22), including a load cell test sensor (24) enabling pre-assembly of the joint or bolts (4,5) for on-site testing of applied bolt load by using the load cell test sensor (24) to verify bolt load achieved. Automatically guiding joint assembly can improve safety and efficiency of joint assembly and also joint reliability.
A method for the control and monitoring of the assembly of a bolted flanged joint, the bolted flanged joint including a first flange having a first sealing surface, a second flange having a second sealing surface, a gasket between the first flange and the second flange, and at least four bolts to retain together the flanges and the gasket of the bolted flanged joint when assembled, the method including the steps of:
A system for control and monitoring of the assembly of a bolted flanged joint, the bolted flanged joint including a first flange, a second flange, a gasket between the first flange and the second flange, and at least four bolts to retain together the flanges and the gasket of the bolted flanged joint when assembled, the system including:
(canceled)