Risk-constrained Optimization of Virtual Power Plants in Pool and Future Markets
AssigneeMitsubishi Electric Research Laboratories, Inc.
InventorHongbo Sun
Life of this patent
Estimating the term…
Loading patent…
AssigneeMitsubishi Electric Research Laboratories, Inc.
InventorHongbo Sun
Estimating the term…
Embodiments for distributing energy for an energy system having an energy generation source, an energy storage system and a load. The method including identifying a risk level for the energy system, the risk level having objectives prioritized relative to one another. Calculating an objective function based on values including energy market values, electricity rates, and power producing, storing and consumption. Identifying an Optimized solution for charging or discharging the energy storage system based on the objective function. Controlling the distribution of energy to the energy storage system for charging according to the Optimized solution based on the objective function and discharging according to the Optimized solution. The objective function is Optimized using feasibility constraints, again Optimized using technical constraints and additional constraints. The Optimized solution maximizes an expected total pool market revenue and an expected total future market revenue, while minimizing an expected total energy cost for the energy system.
A method for distributing energy for an energy system having an energy generation source, an energy storage system and a demand load, comprising:
A system for distributing energy for an energy system including a renewable generating source, an energy storage system and a conversion system, wherein the energy storage system stores energy from the renewable generating source and a grid, and supplies energy to the demand load and the grid, and wherein the conversion system directs a flow of energy between the energy storage system, the renewable generating source and the grid, the system comprising:
A system for distributing energy for a virtual power plant (VPP), the VPP including a renewable generating source and an energy storage device, and a conversion system, wherein the energy storage device is to store energy from the renewable generating source and a grid, and supply energy to a local demand load and the grid, and wherein the conversion system is to direct a flow of energy between the energy storage device, the renewable generating source and the grid, the system comprising: