Method for estimating the vapor phase corrosion load
AssigneeKemira Oyj
InventorsMarko KOLARI, Iiris JOENSUU
Life of this patent
Estimating the term…
Abstract
Method for estimating vapor phase corrosion load in a paper or board manufacturing system, method for controlling vapor phase corrosion load in a paper or board manufacturing system and an arrangement usable is those method. Said methods allow easy on-line follow up of the corrosion load and also adjusting biocide dosage.
Claims17
A method for estimating vapor phase corrosion load in a paper or board manufacturing system, comprising:
- i. determining in a defined location of an aqueous process flow a threshold rH value;
- ii. determining rH values of said aqueous process flow in said defined location over a defined time period in defined time points;
- iii. calculating Δ rH in each time point as a difference between a determined rH value and the threshold rH value determined in step i, wherein the calculated value Δ rH is at least zero;
- and
- iv. calculating Σ Δ rH as a cumulative sum of Δ rH values obtained in step iii,
- or alternatively
- v. calculating cumulative sum of each determined rH value obtained in step ii, wherein the determined rH value is at least same or higher than the threshold rH value;
- and
- vi. calculating Σ Δ rH as a difference between the cumulative sum obtained in step v and the threshold value obtained in step i multiplied with the defined number of time points;
- and using the Σ Δ rH obtained in step iv or vi to estimate the corrosion load,
- wherein increase in Σ Δ rH indicates an increase in corrosion load and decrease in Σ Δ rH indicates a decrease in corrosion load.
A method for controlling vapor phase corrosion load in a paper or board manufacturing system comprising:
- i. determining in a defined location of an aqueous process flow a threshold rH value;
- ii. determining rH values of said aqueous process flow in said defined location over a defined time period in defined time points;
- iii. calculating Δ rH in each time point as a difference between a determined rH value and the threshold rH value obtained in step i, wherein the calculated value Δ rH is at least zero;
- and
- iv. calculating Σ Δ rH as a cumulative sum of Δ rH values obtained in step iii,
- or alternatively
- v. calculating cumulative sum of each determined rH value obtained in step ii, wherein the determined rH value is at least same or higher than the threshold rH value;
- and
- vi. calculating Σ Δ rH as a difference between the cumulative sum obtained in step v and the threshold value obtained in step i multiplied with the defined number of time points;
- wherein a cumulative Δ rH value for the predetermined time period is used to estimate the corrosion load;
- and
- vii. using the estimate to determine how to adjust the dosing of an oxidizing biocide in a paper or board making process;
- and
- viii. adjusting the amount of the oxidizing biocide based on the estimate obtained regarding vapor phase corrosion.
An arrangement for use in connection with paper or board manufacturing system, comprising:
- i. at least one computing device;
- ii. a method application executable in the at least one computing device, the method application comprising:
- logic that obtains information regarding estimated load of vapor phase corrosion over a time period;
- and
- logic that uses the information to determine how to adjust the dosing of an oxidizing biocide in a paper or board making process.
Dependencies are inferred from the claim text.