Back to results
US 2006/0095219 A1Published application
Electricity metering with a current transformer
AssigneeVeris Industries, LLC
InventorDavid Bruno
Life of this patent
Estimating the term…
Abstract
The data storage and processing resources required for an electric meter are reduced by basing the selection and application of phase error correction on a root mean square load current flowing through the meter.
Claims13
A method of a load current in a conductor, the method comprising the steps of:
- (a) determining a phase error correction factor corresponding to a root mean square of a load current from a first plurality of sampled currents;
- (b) determining a root mean square of a load current from a second plurality of sampled currents;
- and
- (c) computing a phase adjusted root mean square load current from said root mean square load current for said second plurality of sample currents and said phase error correction factor.
1 more element
A method of measuring load current in a conductor, the method comprising the steps of:
- (a) determining a first root mean square load current from a first plurality of sample currents;
- (b) determining a second root mean square load current from another plurality of sample currents;
- (c) determining a phase correction factor corresponding to said first root mean square load current;
- and
- (d) determining a phase corrected root mean square load current from said second root mean square load current and said phase correction factor.
2 more elements
A method of measuring current in an electrical distribution system, said method comprising the steps of:
- (a) periodically sampling a secondary current in a winding of a current transformer,
- (b) calculating an assumed load current from said sample secondary current;
- (c) repeating steps (a) and (b) for a first plurality of samples of said secondary current;
- (d) calculating a first root mean square of said assumed load currents from said first plurality of samples;
- (e) repeating steps (a) and (b) for a second plurality of samples of said secondary current;
- (f) calculating a later root mean square of said assumed load currents from said second plurality of samples of secondary current;
- (g) determining a phase correction factor corresponding to said first root mean square assumed load current, and
- (h) calculating an adjusted load current from said later root mean square assumed load current and said phase correction factor.
5 more elements
A meter for measuring a load current in a conductor, the meter comprising:
- (a) a current transformer including a primary winding and a secondary winding, said load current inducing a secondary current in said secondary winding;
- and
- (b) a data processing system that:
- (i) periodically samples said secondary current;
- (ii) calculates a first root mean square of assumed load currents from a first plurality of samples of said secondary current;
- (iii) determines a phase correction factor corresponding to said first root mean square assumed load current;
- and
- (iv) calculates a second root mean square of assumed load currents from a temporally later second plurality of samples of said secondary current;
- and
- (v) calculates a phase adjusted load current from said second root mean square assumed load current and said phase adjustment factor.
7 more elements
A meter for calculating power, the meter comprising:
- (a) a current transformer including a primary winding and a secondary winding, said load current inducing a secondary current in said secondary winding;
- (b) a data processing system that:
- (i) periodically samples said secondary current;
- (ii) calculates a correction factor representative of the phase shift been the secondary current and the load current;
- (v) calculates a phase adjusted load current from said secondary current and said correction factor;
- (c) said data processing system periodically samples a corresponding voltage associated with said load current at a temporal offset from said sampling of said secondary current, and determines said power based upon said phase adjusted load current and said voltage.
3 more elements
Dependencies are inferred from the claim text.