System operator side computer, power generation operator side computer, power system, control method, and program
AssigneeMitsubishi Heavy Industries, Ltd.
InventorNaoyuki Nagafuchi
Life of this patent
Estimating the term…
Abstract
A system operator side computer includes: a supply amount acquirer configured to acquire a maximum suppliable power amount from a power generation operator at a predetermined time later; a demand specifier configured to specify a power demand at the predetermined time later; and a shortage amount calculator configured to calculate a power shortage amount based on the power demand and the maximum suppliable power amount.
Claims11
An operator side power supply manager device, comprising:
- a memory storing computer-readable instructions;
- and
- a processor, coupled to the memory, the processor configured to execute the computer-readable instructions to:
- apply a first power amount to a load using a weather dependent power supply device;
- apply a second power amount to a load using a weather independent power supply device;
- receive weather information over a network;
- predict the first amount of power applied to the load by the weather dependent power supply device at a predetermined time based on the received weather information;
- determine a total power amount comprising a sum of the predicted first amount of power applied to the load by the weather dependent power supply device at the predetermined time based on the received weather information and a second amount of power applied to the load at the predetermined time by the weather independent power supply device;
- determine whether the total power amount applied to the load at the predetermined time is insufficient to meet a power demand of the load at the predetermined time;
- when the total power amount is determined to be insufficient at the predetermined time, determine an increase to the second amount of power to apply to the load at the predetermined time by the weather independent power supply device to meet the power demand of the load;
- and
- apply the increase to the load at the predetermined time.
A power system comprising:
- an operator side power supply manager device;
- and
- a power generation manager device,
- wherein the operator side power supply manager device includes
- a first memory storing first computer-readable instructions;
- and
- a first processor, coupled to the first memory, the first processor configured to execute the first computer-readable instructions to:
- apply a first power amount to a load using a weather dependent power supply device;
- apply a second power amount to a load using a weather independent power supply device;
- receive weather information over a network;
- predict the first amount of power applied to the load by the weather dependent power supply device at a predetermined time based on the received weather information;
- determine a total power amount comprising a sum of the predicted first amount of power applied to the load by the weather dependent power supply device at the predetermined time based on the received weather information and a second amount of power applied to the load at the predetermined time by the weather independent power supply device;
- determine whether the total power amount applied to the load at the predetermined time is insufficient to meet a power demand of the load at the predetermined time;
- when the total power amount is determined to be insufficient at the predetermined time, determine an increase to the second amount of power to apply to the load at the predetermined time by the weather independent power supply device to meet the power demand of the load;
- and
- apply the increase to the load at the predetermined time;
- and
- wherein the power generation manager device includes
- a second memory storing second computer-readable instructions;
- and
- a second processor, coupled to the second memory, the second processor configured to execute the second computer-readable instructions to:
- receive a request from the operator side power supply manager device for a maximum suppliable power amount of the weather independent power supply device at the predetermined time;
- calculate the maximum suppliable power amount of the weather independent power supply device at the predetermined time;
- and
- transmit the maximum suppliable power amount of the weather independent power supply device to the operator side power supply manager device.
A control method of an operator side power supply manager device, comprising:
- applying a first power amount to a load using a weather dependent power supply device;
- applying a second power amount to a load using a weather independent power supply device;
- receiving weather information over a network;
- predicting the first amount of power applied to the load by the weather dependent power supply device at a predetermined time based on the received weather information;
- determining a total power amount comprising a sum of the predicted first amount of power applied to the load by the weather dependent power supply device at the predetermined time based on the received weather information and a second amount of power applied to the load at the predetermined time by the weather independent power supply device;
- determining whether the total power amount applied to the load at the predetermined time is insufficient to meet a power demand of the load at the predetermined time;
- when the total power amount is determined to be insufficient at the predetermined time, determining an increase to the second amount of power to apply to the load at the predetermined time by the weather independent power supply device to meet the power demand of the load;
- and
- applying the increase to the load at the predetermined time.
A non-transitory computer-readable media having computer-readable instructions stored thereon, which when executed by a processor causes the processor to perform operator side power supply management operations comprising:
- applying a first power amount to a load using a weather dependent power supply device;
- applying a second power amount to a load using a weather independent power supply device;
- receiving weather information over a network;
- predicting the first amount of power applied to the load by the weather dependent power supply device at a predetermined time based on the received weather information;
- determining a total power amount comprising a sum of the predicted first amount of power applied to the load by the weather dependent power supply device at the predetermined time based on the received weather information and a second amount of power applied to the load at the predetermined time by the weather independent power supply device;
- determining whether the total power amount applied to the load at the predetermined time is insufficient to meet a power demand of the load at the predetermined time;
- when the total power amount is determined to be insufficient at the predetermined time, determining an increase to the second amount of power to apply to the load at the predetermined time by the weather independent power supply device to meet the power demand of the load;
- and
- applying the increase to the load at the predetermined time.
Dependencies are inferred from the claim text.