Schedule creation device, schedule creation method, and program
AssigneeMitsubishi Heavy Industries, Ltd.
InventorTatsuki Takazaki
Life of this patent
Estimating the term…
Abstract
Provided is a schedule creation device for creating a conveyance schedule according to which a conveyance device conveys a product to work positions designated for each manufacturing process. Said schedule creation device sets a first score to the work positions and to a conveyance path of the conveyance device; sets a second score for products; and uses the first score and the second score to determine the product to be conveyed by the conveyance device from among products present at a plurality of work positions.
Claims11
A schedule creation device for creating a transport schedule of an automated transport device on which a product is transported to a work position determined for each production process by the automated transport device, based on a production schedule which is determined in advance and defines an execution time of a production work for each production process in a production line configured to perform the production work at the work position determined for each production process to manufacture the product, such that the production work is started at the execution time defined in the production schedule, the schedule creation device comprising:
- a schedule creation unit configured to set a first score to the work position and a transport path of the automated transport device, set a second score to the product, and decide the product to be transported by the automated transport device from among the products present at a plurality of the work positions based on the first score and the second score, and
- an output unit configured to output an instruction to the automated transport device to cause the automated transport device to move along the transport path to transport the product decided by the schedule creation unit from a first work position within the plurality of the work positions to a second work position within the plurality of the work positions,
- wherein the production schedule is provided to the schedule creation device from outside,
- wherein the schedule creation unit is configured to set the first score based on whether or not passage of the automated transport device to the work position and the transport path is possible and set, based on a preset priority of each work position, the second score of the product present at the work position,
- wherein the first score is set to a value corresponding to a hardness of passage of the automated transport device, the second score is set to a value corresponding to a level of a priority of production work of the product with the second score set, and the schedule creation unit is configured to select the product having the second score set to a greater value than the first score set to the transport path of the product, to which the second score is set, as a transport candidate,
- wherein the schedule creation unit is configured to decide to retract the product, to which a maximum second score is set, in a case where there is no product to which the second score greater than the first score set to the transport path of the product is set, and
- wherein, in a case where there is a plurality of the automated transport devices, the schedule creation unit is configured to set the first score of the transport path, through which the automated transport device having already decided the product to transport passes, to a value such that passage of another automated transport device is impossible.
A schedule creation method comprising,
- creating, using a schedule creation device, a transport schedule of an automated transport device on which a product is transported to a work position determined for each production process by the automated transport device, based on a production schedule which is determined in advance and defines an execution time of a production work for each production process in a production line configured to perform the production work at the work position determined for each production process to manufacture the product, such that the production work is started at the execution time defined in the production schedule,
- setting a first score to the work position and a transport path of the automated transport device, sets a second score to the product, and decides the product to be transported by the automated transport device from among the products at a plurality of the work positions based on the first score and the second score;
- and
- causing the automated transport device to move along the transport path to transport the product decided by the schedule creation unit from one work position within the plurality of the work positions to a second work position within the plurality of the work positions,
- wherein the production schedule is provided to the schedule creation device from outside,
- wherein the schedule creation unit is configured to set the first score based on whether or not passage of the automated transport device to the work position and the transport path is possible and set, based on a preset priority of each work position, the second score of the product present at the work position,
- wherein the first score is set to a value corresponding to a hardness of passage of the automated transport device, the second score is set to a value corresponding to a level of a priority of production work of the product with the second score set, and the schedule creation unit is configured to select the product having the second score set to a greater value than the first score set to the transport path of the product, to which the second score is set, as a transport candidate,
- wherein the schedule creation unit is configured to decide to retract the product, to which a maximum second score is set, in a case where there is no product to which the second score greater than the first score set to the transport path of the product is set, and
- wherein, in a case where there is a plurality of the automated transport devices, the schedule creation unit is configured to set the first score of the transport path, through which the automated transport device having already decided the product to transport passes, to a value such that passage of another automated transport device is impossible.
A program causing a computer of a schedule creation device to:
- create a transport schedule of an automated transport device on which a product is transported to a work position determined for each production process by the automated transport device, based on a production schedule which is determined in advance and defines an execution time of a production work for each production process in a production line configured to perform the production work at the work position determined for each production process to manufacture the product, such that the production work is started at the execution time defined in the production schedule,
- set a first score to the work position and a transport path of the automated transport device;
- set a second score to the product;
- decide the product to be transported by the automated transport device from among the products present at a plurality of the work positions based on the first score and the second score;
- and
- cause the automated transport device to move along the transport path to transport the product decided by the schedule creation unit from one work position within the plurality of the work positions to a second work position within the plurality of the work positions,
- wherein the production schedule is provided to the schedule creation device from outside,
- wherein the schedule creation unit is configured to set the first score based on whether or not passage of the automated transport device to the work position and the transport path is possible and set, based on a preset priority of each work position, the second score of the product present at the work position,
- wherein the first score is set to a value corresponding to a hardness of passage of the automated transport device, the second score is set to a value corresponding to a level of a priority of production work of the product with the second score set, and the schedule creation unit is configured to select the product having the second score set to a greater value than the first score set to the transport path of the product, to which the second score is set, as a transport candidate,
- wherein the schedule creation unit is configured to decide to retract the product, to which a maximum second score is set, in a case where there is no product to which the second score greater than the first score set to the transport path of the product is set, and
- wherein, in a case where there is a plurality of the automated transport devices, the schedule creation unit is configured to set the first score of the transport path, through which the automated transport device having already decided the product to transport passes, to a value such that passage of another automated transport device is impossible.
Dependencies are inferred from the claim text.