Method for back end planning and scheduling
AssigneeApplied Materials, Inc.
InventorDavid Everton Norman
Life of this patent
Estimating the term…
Abstract
Embodiments presented herein provide techniques for planning and scheduling in a factory. The technique begins by generating a bottleneck loading plan from a plurality of inputs. A simulation is run using the bottleneck loading plan. The factory is simulated using decisions made based on the bottleneck loading plan and a lot-to-machine schedule is generated with the simulation bottleneck loading plan.
Claims14
A method for back end planning and scheduling a factory, the method comprising:
- generating a bottleneck loading plan for one or more families of equipment from a plurality of inputs;
- generating a simulation of the factory using the bottleneck loading plan;
- creating a model for the factory by running the simulation of the factory and using decisions based on the bottleneck loading plan and a block based workflow;
- and
- generating a lot-to-machine schedule with the model to control one of,
- one or more processes related to fabrication of semiconductor substrates;
- and
- one or more processes related to cutting, assembly, and testing of a semiconductor die on semiconductor substrates;
- publishing the lot-to-machine schedule to the factory;
- implementing what each equipment should work on next based on the generated lot-to-machine schedule;
- monitoring real-time factory data of the implemented schedule;
- comparing the real time factory data of the implemented schedule to the generated lot-to-machine schedule to determine a deviation;
- and
- providing a notification if the deviation exceeds a threshold.
A non-transitory computer-readable medium containing computer program code that, when executed by a processor, performs an operation for back end planning and scheduling a factory, the operation comprising:
- generating a bottleneck loading plan from a plurality of inputs;
- running a simulation using the bottleneck loading plan;
- simulating the factory using decisions made based on the bottleneck loading plan;
- and generating a lot-to-machine schedule with the model to control one of,
- one or more processes related to fabrication of semiconductor substrates;
- and
- one or more processes related to cutting, assembly, and testing of a semiconductor die on semiconductor substrates;
- publishing the lot-to-machine schedule to the factory;
- implementing what each equipment should work on next based on the generated lot-to-machine schedule;
- monitoring real-time factory data of the implemented schedule;
- comparing the real time factory data of the implemented schedule to the generated lot-to-machine schedule to determine a deviation;
- and
- providing a notification if the deviation exceeds a threshold.
A planning and scheduling system for a factory, wherein the factory comprises a plurality of work orders and one or more tools for processing the work orders, the scheduling system comprising:
- at least one processor;
- and
- a memory containing a program that, when executed by the at least one processor, performs an operation for planning and scheduling the factory, the operation comprising:
- generating a bottleneck loading plan from a plurality of inputs;
- running a simulation using the bottleneck loading plan;
- simulating the factory using decisions made based on the bottleneck loading plan;
- creating a model for the factory by running the simulation of the factory and using decisions based on the bottleneck loading plan and a block based workflow;
- and
- generating a lot-to-machine schedule with the model to control one of,
- one or more processes related to fabrication of semiconductor substrates;
- and
- one or more processes related to cutting, assembly, and testing of a semiconductor die on semiconductor substrates;
- publishing the lot-to-machine schedule to the factory;
- implementing what each equipment should work on next based on the generated lot-to-machine schedule;
- monitoring real-time factory data of the implemented schedule;
- comparing the real time factory data of the implemented schedule to the generated lot-to-machine schedule to determine a deviation;
- and
- providing a notification if the deviation exceeds a threshold.