# US 9,882,453 B2 · Method for providing a frequency response for a combined cycle power plant

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 9,882,453 B2
- Document ID: US9882453B2
- Status: Granted
- Kind: B2
- Application number: 14/182,390
- Filed: 2014-02-18
- Published: 2014-08-28
- Granted: 2018-01-30
- Earliest claimed: 2013-02-22
- Assignees: General Electric Technology GmbH
- Applicants: ALSTOM Technology Ltd
- Inventors: Jan Schlesier; Hamid Olia; Martin Schoenenberger
- Web page: https://patentgrep.com/patent/US9882453B2

## CPC

- H02K 7/1823: {structurally associated with turbines or similar engines}
- F01K 23/101: {Regulating means specially adapted therefor (F01K23/105, F01K23/108 take precedence)}
- H02K 7/183: {wherein the turbine is a wind turbine (adaptation of a wind turbine to an electric generator F03D9/25)}
- Y02E 20/16: Combined cycle power plant [CCPP], or combined cycle gas turbine [CCGT]
- H02K: DYNAMO-ELECTRIC MACHINES (dynamo-electric relays H01H53/00; conversion of DC or AC input power into surge output power {H03K3/53})
- F01K: STEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES (gas-turbine or jet-propulsion plants F02; nuclear power plants, engine arrangements therein G21D)
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION

## Abstract

The disclosure refers to a method for providing a frequency response for a combined cycle power plant connected to an electric grid. The combined cycle power plant includes a gas turbine engine and a steam turbine engine. The steam turbine engine includes a boiler, a steam turbine, a pump, a condenser, a bypass for the steam turbine, a steam admission control valve. The steam turbine engine operates with the bypass closed or at least partly open to supply steam from the boiler to the condenser bypassing the steam turbine, and/or with the steam admission control valve at least partly open. The method comprises regulating the output load of the combined cycle power plant by regulating the steam admission control valve and/or by regulating the steam flow through the bypass in response to a frequency change of the electric grid. The output of the gas turbine can also be adjusted, such that steam generated by the boiler is sufficient to achieve the target load for the steam turbine.

## Claims

### Claim 1

A method for providing a frequency response for a combined cycle power plant connected to an electric grid, wherein the combined cycle power plant comprises a gas turbine engine and a steam turbine engine, the steam turbine engine comprises a boiler providing steam to a steam turbine, a pump, a condenser connected to an output of the steam turbine, a bypass for the steam turbine between the boiler and the condenser, a steam admission control valve, the steam turbine engine operates by manipulating the bypass between the boiler and the condenser and by manipulating the steam admission control valve, the method comprising:
regulating the output load of the steam turbine engine in response to a frequency change of the electric grid by increasing steam flow through the bypass between the boiler and the condenser when the frequency of the electric grid increases, wherein the regulation of the output load of the steam turbine engine includes at least a transient load variation phase (A) where the regulation of the output load of the steam turbine engine is faster than the regulation of the output load of the gas turbine engine.

### Claim 2 (depends on 1)

The method of claim 1, further comprising adjusting the gas turbine engine output load.

### Claim 3 (depends on 2)

The method of claim 2, further comprising:
supplying the boiler with exhaust gas discharged from the gas turbine engine, and
adjusting the gas turbine engine output load such that the amount of steam generated by the boiler is sufficient to achieve the target load of the steam turbine.

### Claim 4 (depends on 1)

The method of claim 1, wherein the regulation of the output load of the steam turbine engine further includes at least
a stabilization phase (B); and
a normalization phase (C).

### Claim 5 (depends on 2)

The method of claim 2 wherein the end of a normalization phase (C) the output load of the gas turbine engine and the output load of the steam turbine engine is the same as the output load of the gas turbine engine and the output load of the steam turbine engine before regulation.

### Claim 6 (depends on 2)

The method of claim 2, wherein the adjustment of the output load of the gas turbine engine includes at least
a transient load variation phase (D);
a stabilization phase (E); and
a normalization phase (F).

### Claim 7 (depends on 1)

The method of claim 1, wherein the transient load variation phase (A) for the regulation of the output load of the steam turbine engine is shorter than a transient load variation phase (D) for the adjustment of the output load of the gas turbine engine.

### Claim 8 (depends on 4)

The method of claim 4 wherein the normalization phase (C) for the regulation of the output load of the steam turbine engine is shorter than a normalization phase (F) for the adjustment of the output load of the gas turbine engine.

### Claim 9 (depends on 2)

The method of claim 2, further comprising adjusting the gas turbine engine output load simultaneously or with a time lag with respect to the steam turbine engine output load regulation.

### Claim 10 (depends on 1)

The method of claim 1, wherein the power output of the combined cycle power plant prior to the frequency disturbance is zero and a frequency increase above the nominal value causes the steam turbine to reduce load and yield to an import of active power by the combined cycle power plant.

### Claim 11 (depends on 10)

The method of claim 10, wherein a frequency increase above the nominal value further causes the gas turbine to reduce load and yield to an import of active power by the combined cycle power plant.

### Claim 12

The method of clam 1, wherein further regulation of the output load of the steam turbine engine in the response to a frequency change of the electric grid is carried out by decreasing steam flow through the bypass when the frequency of the electric grid decreases.