Integrated heavy lift and logistics vessel
AssigneeKeppel Offshore & Marine Technology Centre Pte Ltd
InventorsJames Davis, Peter George Noble, TakOn Cheung, Aziz Amirali Merchant, Sreekala Kumar, Abul Bashar Md Masum Reza
Life of this patent
Estimating the term…
Abstract
This invention relates to an integrated heavy lift and logistics vessel for receiving another vessel. Further the integrated heavy lift and logistics vessel is able to provide logistical support to the other vessel in remote locations. More particularly, this invention relates to an integrated heavy lift and logistics vessel that is designed to carry out heavy lifting and logistic supply functions in a stable manner. The integrated heavy lift and logistics vessel is also equipped with safe refuge quarters, helipad(s), various forms of storage, and areas for storage.
Claims8
An integrated heavy lift and logistics vessel for docking a vessel comprising:
- a deck having a first section for receiving a vessel, and a second section bordered by a first wing-wall provided on a port side of the deck, a second wing-wall provided on a starboard side of the deck, and a deck box provided at a bow of the deck, the deck box abutting the first wing-wall and the second wing-wall wherein the first wing-wall comprises a first tube extending from a hull of the integrated heavy lift and logistics vessel to the deck, the first tube having a first opening at the hull and a second opening at a surface of the first wing-wall facing the deck, wherein in response to the ballasting system lowering the deck below the water level, water flows through the first tube via the first opening and the second opening to flood the second section of the deck and further wherein the first tube is tilted at an angle in relation to a surface of the deck such that the first opening of the tube is positioned lower than the second opening of the first tube;
- a ballasting system configured to lower the deck below a water level and below a hull of a docking vessel, and to raise the deck above the water level, wherein the second section of the deck is configured to flood when the deck is lowered below the water level;
- and
- an accommodation unit provided on a top surface of the deck box.
Dependencies are inferred from the claim text.