Producing gas and liquid from below a permanent packer in a hydrocarbon well
AssigneeConocoPhillips Company
InventorDennis R. Wilson
Life of this patent
Estimating the term…
Abstract
The invention relates to an arrangement for positively pumping liquids to the surface of a hydrocarbon well where the hydrocarbon well has bee previously completed with a permanent packer and tailpipe. A rod pump having a plunger connected to a hollow rod string can positively pump the liquids collecting at the bottom of the well while the natural gas is produced up the annulus between the production tubing and the hollow rod string. In this invention, the tail pipe is perforated above the rod pump and below the packer to all the natural gas into the production tubing.
Claims6
A system for producing liquids from a gas well having a permanent packer and a tailpipe installed in the natural gas well where the system comprises:
- a) a pump comprising a barrel and a plunger, wherein the barrel is seated in and connected to the tailpipe, wherein the barrel is seated and connected near the lower end of the tailpipe, wherein the plunger is arranged for up and down pumping movement within the barrel;
- b) holes in the tailpipe above the connection of the barrel to the tailpipe, wherein the holes allow gas to proceed up the tailpipe and to the surface;
- and
- c) a string of hollow valve rod connected to the plunger and in fluid communication therewith, wherein the liquids drawn into the plunger during movement of the plunger up and down within the barrel exit the top of the plunger through the hollow valve rod, wherein the hollow valve rod includes a series of one-way valves to prevent particles that might settle in the liquid from descending below the one way valves, wherein the series of one-way valves are spaced apart so that liquids pumped up the hollow valve rod passes at least one one-way valve during each pump cycle.
A process for producing liquids from a cased natural gas well where the natural gas well has perforations in casing to produce gas and liquids, a permanent packer and a tailpipe installed therein wherein the process comprises:
- a) installing holes in the tailpipe generally at or above the level of the perforations in the casing, wherein the holes allow gas to proceed up the tailpipe and to the surface;
- b) installing a pump at the end of a string of hollow valve rod where the pump includes a barrel and a hollow plunger and where the hollow plunger is connected to and in fluid communication with the hollow valve rod and further includes a traveling valve to admit liquids into the hollow interior of the plunger and wherein the barrel connects to the tailpipe below the holes installed in the tailpipe in step a) and includes a standing valve to admit liquids into the barrel;
- and
- c) raising and lowering the plunger to draw liquids through the standing valve to fill the space in the barrel below the plunger and through the traveling valve to fill the plunger and direct the liquids to exit the top of the plunger into the hollow valve rod, wherein the hollow valve rod includes a series of one-way valves to prevent particles that might settle in the liquid from descending below the one way valves, wherein the series of one-way valves are spaced apart so that liquids pumped up the hollow valve rod passes at least one one-way valve during each pump cycle .
Dependencies are inferred from the claim text.