# US 7,377,322 B2 · Method and apparatus for cementing production tubing in a multilateral borehole

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 7,377,322 B2
- Document ID: US7377322B2
- Status: Granted
- Kind: B2
- Application number: 11/359,059
- Filed: 2006-02-22
- Published: 2006-09-21
- Granted: 2008-05-27
- Earliest claimed: 2005-03-15
- Assignees: Peak Completion Technologies, Inc.
- Inventors: Raymond A. Hofman
- Web page: https://patentgrep.com/patent/US7377322B2

## CPC

- E21B 21/103: {Down-hole by-pass valve arrangements, i.e. between the inside of the drill string and the annulus (valves specifically for maintaining circulation of drilling fluid while connecting or disconnecting tubular joints E21B21/019)}
- E21B 33/13: Methods or devices for cementing, for plugging holes, crevices or the like
- E21B 43/12: Methods or apparatus for controlling the flow of the obtained fluid to or in wells (E21B43/25 takes precedence; valve arrangements E21B34/00)
- E21B 43/14: Obtaining from a multiple-zone well
- E21B 43/261: {Separate steps of (1) cementing, plugging or consolidating and (2) fracturing or attacking the formation}
- E21B 34/14: operated by movement of tools, e.g. sleeve valves operated by pistons or wire line tools {(E21B34/066 takes precedence)}
- E21B 43/26: by forming crevices or fractures
- E21B: EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS

## Abstract

A hydraulically actuated anchor and a mechanically actuated packer are used in combination to secure a production tubing system in a lateral prior to injection of a cement to line the lateral borehole in which the production tubing is positioned. The packer is expanded to prevent fluid cement material from flowing past the packer into a junction area of the lateral with other laterals and aid the removal of superfluous cement material after hardening of the injected cement material around the production tubing system.

## Claims

### Claim 1

A method for cementing production tubing in a predefined lateral of a multilateral borehole, comprising:
running production tubing into said predefined lateral, said production tubing having a distal end, an anchor and a packer spaced from the distal end, and a work string removably attached to the packer, said running of the production tubing being continued until said packer and said anchor are advanced beyond a junction of lateral boreholes;
setting said anchor and securing said production tubing in a fixed relationship with said predefined lateral;
injecting a fluid cement material through said production tubing, out of at least one opening therein and around an annular space around the production tubing defined between a external surface of the production tubing and an internal surface of said predefined lateral, said injecting being continued for a period of time sufficient to substantially fill said annular space around the production tubing from said distal end approximately to said packer with said fluid cement material; and
subsequently setting said packer and forming a fluid seal between said production tubing and said internal surface of said predefined lateral.

### Claim 2 (depends on 1)

The method for cementing production tubing, set forth in claim 1 wherein subsequent to setting said packer said method includes removing fluid cement material deposits from the production tubing.

### Claim 3 (depends on 2)

The method for cementing production tubing, as set forth in claim 2, wherein said removing fluid cement material from the production tubing includes flushing said tubing with a liquid material.

### Claim 4 (depends on 2)

The method for cementing production tubing as set forth in claim 2, wherein said removing fluid cement material from the production tubing includes passing a swab through said production tubing.

### Claim 5 (depends on 2)

The method for cementing production tubing as set forth in claim 2, wherein subsequent to removing fluid cement material from the production tubing, said method includes disconnecting said work string from the distal end of said packer.

### Claim 6 (depends on 5)

The method for cementing production tubing as set forth in claim 5 wherein subsequent to disconnecting said working tubing from the distal end of the packer, said method includes flushing said borehole and removing any residual fluid cement material from said borehole and said junction.

### Claim 7 (depends on 6)

The method for cementing production tubing set forth in claim 6 wherein a junction is defined between each of said multiple lateral boreholes and a central wellbore and said flushing said borehole and removing any residual fluid cement material from said borehole and said junction includes removing any residual fluid cement material from each of said junctions.

### Claim 8 (depends on 1)

The method for cementing production tubing set forth in claim 1 wherein said setting said anchor includes hydraulically expanding at least one radially outwardly moveable member of said anchor.

### Claim 9 (depends on 1)

The method for cementing production tubing set forth in claim 1 wherein said setting said packer includes mechanically expanding at least one radially outwardly moveable member of said packer.

### Claim 10 (depends on 1)

The method for cementing production tubing as set forth claim 1 wherein said injecting a fluid cement material includes injecting an amount of said fluid cement material sufficient to substantially fill said annular space around the production tubing from said distal end to said packer.