System for transferring fluids and methods for installing, modifying and operating system
AssigneeAdvanced Production and Loading AS
InventorsArild Bech, Carl K. Arnet, Jan Vidar Aarsnes
Life of this patent
Estimating the term…
Abstract
System for transferring fluids between a floating installation (10) and a tanker (30), wherein the floating installation is permanently moored (31, 32) to the seabed (1), and comprising a buoy (20) being moored (21A, 21B) to the seabed and connected to the installation through a first mooring line (12A) and a first fluid transfer line (12B). Buoy (20) is adapted to be connected to the tanker (30) through a second mooring line (32A) and a second fluid transfer line (32B), and the buoy (20) is immersed in the sea in its normal operative position and is provided with a swivel for the second mooring line (32A) and the second fluid transfer line (32B).
Claims11
A system for transferring fluids between a floating installation and a tanker, wherein the floating installation is permanently moored to the seabed, said system comprising:
- a buoy moored to the seabed and connected to the installation through a first mooring line and a first fluid transfer line,
- wherein the buoy is adapted to be connected to the tanker through a second mooring line and a second fluid transfer line, wherein the buoy is drawn to an immersed operative position by the first mooring line and is provided with a swivel for the second mooring line and the second fluid transfer line so that fluids are transferable to the tanker through the second fluid transfer line while the buoy is in the immersed operative position.
A method of installing a system for transferring fluids between a floating installation and a tanker, the method comprising the steps of:
- permanently mooring the floating installation to the seabed;
- mooring a buoy to the seabed;
- connecting the buoy to the installation through a first mooring line and a first fluid transfer line;
- providing a second mooring line and a second fluid transfer line at the buoy for connecting the buoy to a tanker,
- wherein a terminating adjustment of the moorings in said system is provided for by tensioning said first mooring line at the floating installation end thereof, thereby lowering the buoy to an immersed position.
A method of modifying a system for transferring fluids between a floating installation and a tanker, the system comprising a buoy moored to the seabed and connected to the installation through a first mooring line and a first fluid transfer line, wherein the buoy is adapted to be connected to the tanker through a second mooring line and a second fluid transfer line, wherein the buoy is immersed in the sea in an operative position and is provided with a swivel for the second mooring line and the second fluid transfer line, the method of modifying the system comprising the step of:
- raising said buoy from its immersed position to a surface position by detensioning or extending said first mooring line.
A method of modifying a system for transferring fluids between a floating installation permanently moored in a body of water, and a tanker, comprising:
- mooring a buoy to the seabed, the buoy being adapted to be connected to the tanker through a first mooring line and a first fluid transfer line;
- connecting the buoy to the installation through a second mooring line and a second fluid transfer line while the buoy is in an inoperative floating position on a surface of the body of water;
- and
- drawing the buoy down from the inoperative floating position to a submerged operative position a predetermined depth below the surface of the body of water by drawing in the second mooring line and pulling the buoy down to the operative submerged position.
Dependencies are inferred from the claim text.