# US 6,350,327 B2 · Process for manufacturing pipes

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 6,350,327 B2
- Document ID: US6350327B2
- Status: Granted
- Kind: B2
- Application number: 09/384,183
- Filed: 1999-08-27
- Published: 2001-07-19
- Granted: 2002-02-26
- Earliest claimed: 1998-08-27
- Assignees: Forth Tool & Valve Limited
- Inventors: David Neill
- Web page: https://patentgrep.com/patent/US6350327B2

## CPC

- B23K 9/048: {on cylindrical surfaces}
- Y10T 428/12292: Workpiece with longitudinal passageway or stopweld material [e.g., for tubular stock, etc.]
- Y10T 428/12493: Composite; i.e., plural, adjacent, spatially distinct metal components [e.g., layers, joint, etc.]
- B23K: SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- Y10T: TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION

## Abstract

A process for producing clad pipe comprises forming a hollow body (S10) of base material, bonding a cladding material metallurgically to the base material (S12) to form a composite body and subsequently extruding the composite body to form a pipe. This process allows the metallurgical bond to be validated using non-destructive methods prior to extrusion. Any areas that are unbonded will be detected, thereby reducing wastage. Moreover, because the metallurgical bond is achieved prior to extrusion, the cladding thickness is controlled during the extrusion process, avoiding migration of the clad material into the base material by disproportionate amounts.

## Claims

### Claim 1

A process for producing clad pipe, comprising forming a tubular billet of base material, bonding a cladding meterial metallurgiucally to the base material to form a composite body by depositing a weld overlay of the cladding material on the base material and subsequently extruding the composite body to form a pipe.

### Claim 2 (depends on 1)

The process as claimed in claim 1, wherein the cladding material is machined prior to extrusion taking place.

### Claim 3 (depends on 1)

The process as claimed in claim 1, wherein the integrity of the metallurgical bond between the cladding material and the base material is inspected or validated prior to extrusion.

### Claim 4 (depends on 1)

The process as claimed in claim 1, wherein the cladding material is deposited on the internal surface of the tubular billet.

### Claim 5 (depends on 1)

The process as claimed in claim 1, further including cold working the clad pipe after extrusion.

### Claim 6 (depends on 1)

The process as claimed in claim 1, further including heat treating the clad pipe after extrusion.

### Claim 7 (depends on 1)

A pipe produced by the process as claimed in claim 1.