# US 6,205,431 B1 · System and method for forecasting intermittent demand

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 6,205,431 B1
- Document ID: US6205431B1
- Status: Granted
- Kind: B1
- Application number: 09/182,249
- Filed: 1998-10-29
- Granted: 2001-03-20
- Earliest claimed: 1998-10-29
- Assignees: Smart Software, Inc.
- Inventors: Thomas Reed Willemain; Charles Nelson Smart
- Web page: https://patentgrep.com/patent/US6205431B1

## CPC

- G06Q 10/04: Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem" (market predictions or forecasting for commercial activities G06Q30/0202)
- G06Q 10/063: Operations research, analysis or management
- G06Q 10/06315: {Needs-based resource requirements planning or analysis}
- G06Q 10/06375: {Prediction of business process outcome or impact based on a proposed change}
- G06Q 10/0639: Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q 10/087: Inventory or stock management, e.g. order filling, procurement or balancing against orders
- G06Q 10/08726: {for replenishment processing, procedures, or recommendations using forecasting or optimisation}
- G06Q 30/0201: Market modelling; Market analysis; Collecting market data
- G06Q 30/0202: Market predictions or forecasting for commercial activities
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

A system and method for forecasting intermittent demand. The forecasting technique utilizes sample reuse techniques to build a distribution of predicted cumulative lead time demand values that can be analyzed using statistical methods, be used as input for an inventory control system, be used as input for a sales planning system, etc.

## Claims

### Claim 1

A computerized method for forecasting intermittent demand for a lead time, comprising the steps of:
providing a data set of intermittent data comprising a predetermined number of historical demand values;
calculating lead time demand values for the lead time, wherein the calculating step comprises the step of sampling values from the historical demand values;
summing the lead time demand values to provide a lead time demand sum; and
repeating the calculating and summing steps a predetermined number of times to provide a distribution of lead time demand sums that forecast intermittent demand for inventory requirements.

### Claim 2 (depends on 1)

The method of claim 1, wherein at least ten percent of the historical demand values are zero.

### Claim 3 (depends on 1)

The method of claim 1, wherein the calculating step further includes the step of determining if a next lead time demand value is either zero or non-zero.

### Claim 4 (depends on 3)

The method of claim 3, wherein the step of determining if the next lead time demand value is zero is accomplished with a Markov model.

### Claim 5 (depends on 3)

The method of claim 3, wherein if the next lead time demand value is non-zero, the next lead time demand value is randomly chosen from among the non-zero historical demand values.

### Claim 6 (depends on 5)

The method of claim 5, wherein a jittered lead time demand value is calculated as a random selection of an integer that is in a neighborhood of the lead time demand value.

### Claim 7 (depends on 6)

The method of claim 6, wherein the jittered lead time demand value (S) is calculated as follows:
S=1+INT{LTV+Z sqrt(LTV)},
where INT calculates an integer value, Z is a normally distributed random value having a mean of 0 and variance of 1, and LTV is the lead time value.

### Claim 8 (depends on 7)

The method of claim 7, wherein if S≦0, then S is forced to LTV.

### Claim 9 (depends on 1)

The method of claim 1, further comprising the step of inputting the distribution into an inventory control system.

### Claim 10

A program product, having a computer usable medium having computer readable code embodied therein that, when executed, comprises:
means for examining intermittent data comprised of a predetermined number of historical demand values made up of zero and non-zero values;
means for calculating lead time demand values for the lead time, wherein the calculating means samples values from the historical demand values;
means for summing the lead time demand values to provide a lead time demand sum;
looping means for generating a plurality of lead time demand sums;
storing means for storing the plurality of lead time demand sums; and
means for providing the plurality of lead time demand sums that forecast inventory requirements.

### Claim 11 (depends on 10)

The program product of claim 10, wherein the calculating means sequentially calculates the lead time values, and comprises:
means for determining if each lead time value to be calculated is zero or non-zero;
means for randomly assigning one of the non-zero historical demand values to each non-zero lead time value; and
means for jittering each non-zero lead time value.

### Claim 12 (depends on 11)

The program product of claim 11, wherein the means for determining if each lead time value to be calculated is zero or non-zero utilizes a Markov model.

### Claim 13 (depends on 11)

The program product of claim 11, wherein the jittering means chooses a randomly selected integer that neighbors each non-zero lead time value.

### Claim 14 (depends on 10)

The program product of claim 10, further comprising an inventory control means that receives as input the plurality of lead time demand sums.

### Claim 15 (depends on 10)

The program product of claim 10, wherein the looping means loops N times, wherein N is a user defined value.

### Claim 16

A computer system, comprising:
a processing unit;
a computer system memory accessible to the processing unit;
a data set comprising intermittent data stored within the computer system memory, wherein the intermittent data is comprised of a plurality of time series values;
a mechanism for examining the intermittent data; and
a mechanism for generating a plurality of series of lead time demand values, wherein each series of lead time demand values is based upon at least one sampling selection from among the time series values.

### Claim 17 (depends on 16)

The computer system of claim 16, wherein the program further comprises:
a mechanism for summing the lead time demand values within each series of lead time demand values to provide a plurality of lead time demand sums; and
a mechanism for statistically analyzing the plurality of lead time demand sums.

### Claim 18 (depends on 16)

The computer system of claim 16, wherein the generating mechanism determines if a next lead time demand value to be calculated is zero or non-zero.

### Claim 19 (depends on 18)

The computer system of claim 18, wherein the generating mechanism randomly assigns a non-zero one of the plurality of time series values to the next lead time demand value if the next lead time demand value is calculated as non-zero.

### Claim 20 (depends on 16)

The computer system of claim 16, wherein the generating mechanism comprises a jittering mechanism for altering lead time demand values to neighboring integer values.

### Claim 21 (depends on 16)

The computer system of claim 16, wherein the at least one sampling selection randomly selects a single non-zero value.

### Claim 22 (depends on 16)

The computer system of claim 16, wherein the at least one sampling selection selects a consecutive series of values.

### Claim 23

A computerized method for generating a lead time demand (LTD) distribution for a lead time, comprising the steps of:
providing a data set of intermittent data comprising a predetermined number of historical demand values;
calculating subseries sums for the lead time based on the data set of intermittent data;
providing a cumulative distribution function (CDF);
calculating the LTD distribution based on the CDF and subseries sums; and
providing the LTD distribution to manage product requirements.

### Claim 24 (depends on 23)

The method of claim 23, wherein the CDF is a non-parametric function.

### Claim 25 (depends on 23)

The method of claim 23, wherein the CDF is a parametric function.

### Claim 26 (depends on 25)

The method of claim 25, wherein the CDF utilizes a lognormal probability density function.

### Claim 27 (depends on 25)

The method of claim 25, wherein the CDF utilizes a normal probability density function.

### Claim 28 (depends on 23)

The method of claim 23, further comprising the step of inputting the LTD distribution into an inventory control system.

### Claim 29

A program product embodied on a computer usable medium, for generating a lead time demand (LTD) distribution, wherein said program product, when executed, comprises:
means for examining a data set of intermittent data comprising a predetermined number of historical demand values;
means for calculating subseries sums based on the data set of intermittent data;
means for calculating the LTD distribution based on a cumulative distribution function (CDF) and the subseries sums; and
means for providing the LTD distribution to manage product requirements.

### Claim 30 (depends on 29)

The program product of claim 29 further comprising an analysis means for reporting statistical summaries of the LTD distribution.

### Claim 31 (depends on 29)

The program product of claim 29, further comprising an inventory control means for managing inventory based on the LTD distribution.

### Claim 32 (depends on 29)

The program product of claim 29, wherein the CDF is nonparametric and is given as:
F{circumflex over ( )}(0)=(½+#{=0})/(1+# total)
F{circumflex over ( )}(X)=F{circumflex over ( )}(0)+(1−F{circumflex over ( )}(0))·((½+#{≦X and >0})/(1+#{>0})), X>0,
and wherein X is a variable referring to the LTD.

### Claim 33 (depends on 29)

The program product of claim 29, wherein the CDF is parametric and is given as:
F{circumflex over ( )}(0)=(½+#{=0})/(1+# total)
F{circumflex over ( )}(X)=F{circumflex over ( )}(0)+(1−F{circumflex over ( )}(0))*G{circumflex over ( )}(X), X>0,
and wherein X is a variable referring to the LTD.

### Claim 34 (depends on 33)

The program product of claim 33, wherein G{circumflex over ( )}(X) is estimated by integrating g(X) from −∞ to X, where
g(X)={1/(Sqrt(2*Pi)*Sigma)}*exp(−0.5*((X−Mu)/Sigma){circumflex over ( )}2),
and wherein X is a variable referring to the LTD, Sigma is a standard deviation and Mu is a mean.

### Claim 35 (depends on 33)

The program product of claim 33, wherein G{circumflex over ( )}(X) is estimated by integrating g(X) from −∞ to X, where
g(X)={1/(Sqrt(2*Pi)*Sigma*X)}*exp(−0.5*((Ln(X)−Mu)/Sigma){circumflex over ( )}2),
and wherein X is a variable referring to the LTD, Sigma is a standard deviation and Mu is a mean.

### Claim 36

An inventory management program product embodied on a computer usable medium, that, when executed, comprises:
a forecast mechanism, the forecast mechanism including:,
means for examining intermittent data comprised of a predetermined number of historical demand values made up of zero and non-zero values;
means for calculating lead time demand values for a lead time, wherein the calculating means samples values from the historical demand values;
means for summing the lead time demand values to provide a lead time demand sum;
looping means for generating a plurality of lead time demand sums; and
storing means for storing the plurality of lead time demand sums on a computer system memory; and
an inventory control mechanism, including:
means for reading the plurality of lead time demand sums; and
means for outputting inventory reorder information that specifies when a product order should be placed.

### Claim 37 (depends on 36)

The program product of claim 36, wherein the calculating means sequentially calculates the lead time values, and comprises:
means for determining if each lead time value to be calculated is zero or non-zero;
means for randomly assigning one of the non-zero historical demand values to each non-zero lead time value; and
means for jittering each non-zero lead value.

### Claim 38 (depends on 36)

The program product of claim 36, wherein the inventory control mechanism further comprises means for outputting performance measures.

### Claim 39 (depends on 36)

The program product of claim 36, wherein the inventory reorder information comprise a reorder point and an order quantity.

### Claim 40 (depends on 36)

The program product of claim 36, wherein the inventory reorder information comprises a review interval and an order-up-to value.

### Claim 41 (depends on 38)

The program product of claim 38, wherein the performance measures include inventory/order costs and service level percentages.

### Claim 42

An inventory management program product embodied on a computer usable medium, that, when executed, comprises:
a forecast mechanism, the forecast mechanism including:
means for examining a data set of intermittent data comprising a predetermined number of historical demand values;
means for calculating subseries sums based on the data set of intermittent data;
means for calculating a lead time demand (LTD) distribution based on a cumulative distribution function (CDF) and the subseries sums;
an inventory control mechanism, including:
means for reading the plurality of lead time demand sums; and
means for outputting inventory reorder information that specifies when an order should be placed.

### Claim 43 (depends on 42)

The program product of claim 42, wherein the inventory control mechanism further comprises means for outputting performance measures.

### Claim 44 (depends on 42)

The program product of claim 42, wherein the inventory reorder information comprises a reorder point and an order quantity.

### Claim 45 (depends on 42)

The program product of claim 42, wherein the inventory reorder information comprises a review interval and an order-up-to value.

### Claim 46 (depends on 43)

The program product of claim 43, wherein the performance measures include inventory/order costs and service level percentages.