Method for building an underground continuous wall
AssigneeKabushiki Kaisha Kobe Seiko Sho
InventorsKenji Koike, Yoshiaki Inagaki, Minoru Aoi, Fumio Kinoshita, Shigeki Ashida, Yuji Nakajima, Tatsuo Komoto, Hiroaki Kondo
Life of this patent
Estimating the term…
Abstract
An underground continuous wall building method and apparatus in which a chain cutter 2 provided with excavation blades is obliquely mounted on a running carriage 1. Slanting continuous trenches G1, G2 are excavated by moving the running carriage 1 in a transverse direction while rotating the cutter 2 with the cutter 2 obliquely placed in the ground, and a water cutoff material is poured into the excavated continuous trenches G1, G2 and solidified therein to build slanting continuous walls R1, R2 in the ground.
Claims9
A method for building an underground continuous wall, comprising the steps of:
- placing a chain cutter carried by a running carriage obliquely in ground by sliding the chain cutter in an oblique direction by a hydraulic cylinder;
- moving the running carriage along a specified course over the ground, said running carriage carrying the chain cutter fixedly held in the oblique direction in the ground, said chain cutter being driven to form a first continuous slanting trench and a second continuous oppositely slanting trench;
- excavating the first and the second continuous slanting trenches so as to form an inverted V cross section separated at an apex thereof;
- pouring a wall material into the first and second continuous trenches in order to build two continuous walls with an inverted V cross section;
- and
- placing a slightly arcuate roof bridging the apex of the two continuous walls with the inverted V cross section above an underground construction.
A method for building an underground continuous wall, comprising the steps of:
- placing a chain cutter carried by a running carriage obliquely in ground by sliding the chain cutter in an oblique direction by a hydraulic cylinder;
- moving the running carriage along a specified course over the ground, said running carriage carrying the chain cutter fixedly held in the oblique direction in the ground, said chain cutter being driven to form a first continuous slanting trench and a second continuous crossing trench;
- building a plurality of vertical walls in the ground;
- excavating the first continuous slanting trench and the second continuous crossing trench between the vertical walls built in the ground;
- and
- pouring a wall material into the first and second continuous trenches in order to build a X-shaped wall for reinforcement between the vertical walls.
A method for building an underground continuous wall, comprising the steps of:
- placing a chain cutter carried by a running carriage obliquely in ground by sliding the chain cutter in an oblique direction by a hydraulic cylinder;
- moving the running carriage along a specified course over the ground, said running carriage carrying the chain cutter fixedly held in the oblique direction in the ground, said chain cutter being driven to form a continuous slanting trench;
- building two vertical walls at a specified spacing in the ground;
- undercutting at an angle and then excavating the continuous slanting trench so as to extend underneath the two vertical walls;
- and
- pouring a wall material into the continuous trench in order to build a slanting continuous cutoff bottom wall for preventing entry of water from below into a region between the two vertical walls.
A method for building an underground continuous wall, comprising the steps of:
- placing a chain cutter carried by a running carriage obliquely in ground by sliding the chain cutter in an oblique direction by a hydraulic cylinder;
- moving the running carriage along a specified course over the ground, said running carriage carrying the chain cutter fixedly held in the oblique direction in the ground, said chain cutter being driven to form a continuous slanting trench;
- excavating the continuous slanting trench in a zigzag manner;
- and
- pouring a wall material into the continuous trench in order to build a slanting zigzag continuous cutoff wall.
A method for building an underground continuous wall, comprising the steps of:
- placing a chain cutter carried by a running carriage obliquely in ground by sliding the chain cutter in an oblique direction by a hydraulic cylinder;
- moving the running carriage along a specified course over the ground, said running carriage carrying the chain cutter fixedly held in the oblique direction in the ground, said chain cutter being driven to form a continuous slanting trench;
- pouring a wall material into the continuous slanting trench to build a continuous wall under the ground;
- excavating the continuous slanting trench along a bank;
- and
- pouring a wall material into the continuous trench in order to build a slanting continuous wall along the bank.
A method for building an underground continuous wall, comprising the steps of:
- placing a chain cutter carried by a running carriage obliquely in ground by sliding the chain cutter in an oblique direction by a hydraulic cylinder;
- moving the running carriage along a specified course over the ground, said running carriage carrying the chain cutter fixedly held in the oblique direction in the ground, said chain cutter being driven to form a continuous slanting trench;
- building two vertical walls in the ground;
- excavating a conical continuous trench by moving the running carriage in a circle between the two vertical walls;
- and
- pouring a wall material into the continuous trench in order to build a conical continuous cutoff wall between the two vertical walls.