Split stream pumping system for oil production using electric submersible pumps
AssigneeTexaco Inc.
InventorKevin Rush Bolin
Life of this patent
Estimating the term…
Abstract
A system for reducing lifting costs in a producing oil well is disclosed. The system employs a casing string set through a production zone having upper producing perforations and lower injection perforations. Dual electric submersible pumps are run in on a tubing string to the production zone and a production packer is set between the producing and injection perforations. Produced fluid is allowed to separate in the casing--production tubing annulus and the first electric submersible pump pumps the separated oil to the surface via the production tubing. The reported water is pumped to the injection perforations below the packer by the second electric submersible pump.
Claims10
A method for improving the economics of production from a producing oil well by reducing lifting costs comprising the steps of:
- placing a casing string downhole through a production zone in a well borehole;
- placing a production tubing string extending downwardly through said casing and forming an annulus therebetween;
- placing upper production perforations and lower injection perforations in said casing string in upper and lower portions of said production zone;
- placing a single production packer in said casing string between said production perforations and said injection perforations;
- producing mixed oil and water fluids into said casing-tubing annulus through said production perforations and allowing said produced fluids to collect in said annulus above said production packer and to separate into an oil layer and a water layer under the influence of gravity;
- pumping with a first electric submersible pump, fluid from said oil layer to the surface of the earth via said production tubing;
- and
- pumping with a second electric submersible pump water from said water layer into said injection perforations below said packer for injection back into said production zone.
A system for improving the economics of production from a producing oil well by reducing lifting costs, comprising:
- a casing string extending downhole in a well borehole penetrating a production zone therein;
- upper production perforations and lower injection perforations in said casing string placed respectively in upper and lower portions of said production zone;
- a production packer placed in said casing string between said upper and lower perforations;
- a production tubing string run into the wellbore through said casing string and carrying thereon;
- an electric motor and power cable therefor and a first electric submersible pump powered thereby and having its fluid intake located in the annulus between said casing and said tubing string above said production perforations and said packer and its discharge into said tubing string to the earth's surface, and a second electric submersible pump powered by said motor and having its fluid intake located in the annulus between said casing and said tubing string below said production perforations and above said packer and its discharge tube routed below said packer, whereby produced fluids are separated into oil and water layers in the casing-tubing annulus and primarily oil is pumped to the surface and primarily water is pumped below said packer and back into the production zone via said injection perforations.
Dependencies are inferred from the claim text.