A footing/foundation form with an integral drain having two substantially parallel spaced apart, serpentuitous walls. Each wall includes a plurality of hollow tubes elevated "to grade" above an excavation bottom by a stake and clip mechanism with gravel filled between the elevated tubes and the excavation bottom such that the elevated tube and gravel both engage concrete poured between the walls. The tubes are common 10-foot PVC tubes with a plurality of holes positioned away from the footing/foundation thereby providing the form with an integral drain. The stakes are preferably pieces of reinforcing bar and the clips, while quite effective, are also inexpensively manufactured.
Claims25
In a concrete form for retaining concrete poured about one side of the form and having at least one tube and a support that supports the tube in spaced-apart relation to an excavation bottom, an improvement comprising
- gravel between at least a portion of said tube and the excavation bottom such that the tube and the gravel are positioned to engage liquid concrete poured about one side of the form.
A concrete form to retain concrete poured about one side of the form, said form comprising:
- at least one hollow tube having a first exterior concrete engaging side and at least one aperture providing the form with integral drainage;
- a support that supports the tube in spaced-apart relation to an excavation bottom;
- gravel between at least a portion of said tube and the excavation bottom such that the tube and the gravel are positioned to engage said concrete, the ravel being located beneath substantially all of the tube and filling substantially all of an area between the tube and the excavation bottom;
- wherein the support includes a stake having at least one slender end to facilitate driving the stake partially into the excavation bottom and a clip in frictional, resilient engagement with the stake and the tube to thereby secure the tube relative to the stake and support the tube in spaced-apart relation to the excavation bottom.
In a concrete footing/foundation form including an interior wall and an exterior wall each having at least one tube, an improvement comprising a support that elevates said at least one tube above an excavation bottom and gravel filled between the tube and the excavation bottom such that liquid concrete poured between the interior wall and the exterior wall engages the elevated tube as well as the gravel filled thereunder.
In a concrete footing/foundation form including an interior and an exterior wall each having at least one tube, an improvement comprising means for elevating said at least one tube above an excavation bottom and gravel filled between the tube and the excavation bottom such that concrete poured between the walls engages the elevated tube as well as the gravel filled thereunder, said at least one tube is hollow with a concrete engaging side and a plurality of apertures providing the form with an integral drainage, and a cross over pipe providing fluid communication between the interior and exterior walls and at least one hook coupled with the cross over pipe such that a reinforcing bar coupled with said at least one hook is elevated above the excavation bottom.
A method of constructing a concrete form for retaining liquid concrete poured about one side thereof, the method including the steps of:
- excavating a concrete receiving area;
- elevating a tube above a bottom of the excavation;
- and
- filling gravel between at least a portion of said excavating bottom and said elevated tube such that the tube and the gravel are both in position to engage said poured liquid concrete.
A method of constructing a concrete form for retaining concrete poured about one side thereof, the method including the steps of:
- excavating a concrete receiving area;
- elevating a tube above a bottom of the excavation;
- an
- filling gravel between at least a portion of said excavation bottom and said elevated tube such that the tube and the gravel are both in position to engage said poured concrete, the gravel being filled between substantially all of the elevated tube and the excavation bottom;
- wherein the step of elevating the tube includes the steps of elevating the tube to grade and supporting the tube thereat.
A concrete form to retain concrete poured about one side of the form, said form comprising:
- at least one tube;
- a support that supports the tube in spaced-apart relation to an excavation bottom, the support including a stake having at least one slender end to facilitate driving the stake partially into the excavation bottom and a clip in frictional, resilient engagement with the stake and the tube to thereby secure the tube relative to the stake and support the tube in spaced-apart relation to the excavation bottom;
- and
- gravel between at least a portion of said tube and the excavation bottom such that the tube and the gravel are positioned to engage said concrete.
In a concrete footing/foundation form including an interior and exterior wall each having at least one tube, an improvement comprising:
- a support elevating said at least one tube above an excavation bottom and gravel filled between the tube and the excavation such that concrete poured between the walls engages the elevated tube as well as the gravel filled thereunder;
- and
- a cross over pipe providing fluid communication between the interior and exterior walls and at least one hook coupled with the cross over pipe such that a reinforcing bar coupled with said at least one hook is elevated above the excavation bottom.
A method of constructing a concrete form for retaining concrete poured about one side thereof, the method including the steps of:
- excavating a concrete receiving area;
- elevating a tube above the excavation bottom;
- and
- filling gravel between at least a portion of said excavation bottom and said elevated tube such that the tube and the gravel are both in position to engage said poured concrete;
- wherein the step of elevating a tube above the excavation bottom includes the steps of elevating the tube to grade and supporting the tube thereat.
Dependencies are inferred from the claim text.