Energy recovery snubber
AssigneeSundstrand Corporation
InventorEric A. Henderson
Life of this patent
Estimating the term…
Abstract
A snubber circuit for protecting power switches which modulate the flow of power through an inductive element in a power converter, such as a main primary winding of a transformer, includes a snubbing capacitor and a first switch which is operable to connect the snubbing capacitor to a power switch. A second switch is operable to connect the snubbing capacitor to an auxiliary primary winding of the transformer. The first and second switches are operated so that immediately prior to turn-off of the power switch, the capacitor is connected thereto to store the turn-off reactive power caused by turn-off of the power switch. The first switch is then opened and the second switch closed to couple the reactive power to the auxiliary primary winding to improve the efficiency of the converter.
Claims16
A snubber circuit for a power converter having at least one power switch which is turned on and off to modulate the flow of power through an inductive element, comprising:
- a capacitor;
- a first switch operable to connect the capacitor to the power switch;
- a load;
- a second switch operable to couple the capacitor to the load;
- and
- a switch control coupled to the first and second switches including means for operating the first switch while the power switch is on to transfer transient energy from the inductive element to the capacitor and means for operating the second switch after the power switch is turned off to transfer the transient energy to the load.
A snubber circuit for a power converter having at least one power switch which is switched between on and off states by drive logic to modulate the flow of power from a power source to a load, the switch being connected to a transformer having a primary winding, comprising:
- a snubber capacitor;
- a first switch operable to connect the snubber capacitor to the power switch and to the primary winding;
- an auxiliary primary winding on the transformer;
- a second switch operable to connect the snubber capacitor to the auxiliary primary winding;
- and
- a switch control including means for closing the first switch before the power switch is switched to the off state, means for opening the first switch a first predetermined time after the power switch is switched to the off state and means for closing the second switch after the first switch is opened to transfer to the auxiliary primary winding the transient energy following turn-off of the power switch.
A snubber circuit for a power switch which is periodically operated between on and off states by a switch control to modulate the flow of power through a main primary winding of a transformer, the snubber circuit comprising:
- a capacitor;
- a first switch operable to connect the capacitor across the power switch;
- an auxiliary primary winding inductively linked to the main primary winding;
- a second switch operable to connect the capacitor to the auxiliary primary winding;
- and
- the switch control including means for operating the first switch before turn-off of the power switch and means for operating the second switch following turnoff of the power switch to transfer the transient energy to the auxiliary primary winding.
A snubber circuit for a power converter having two power switches which are periodically operated in alternate fashion between on and off states to modulate the flow of power through a main primary winding coupled to a load, the snubber circuit comprising:
- a capacitor;
- a first switch operable to connect the capacitor across one of the power switches;
- a second switch coupled to the capacitor;
- a third switch operable to connect the capacitor across the other of the power switches;
- and
- a switch control coupled to the first, second and third switches including means for operating the first switch when the one power switch is on, means for operating the second switch after the one power switch is turned off to transfer the transient energy resulting from turn-off of the one power switch to the load, means for subsequently operating the third switch when the other power switch is on and means for operating the second switch after the other power switch is turned off to transfer the transient energy resulting from turn-off of the other power switch to the load.
In a DC-to-AC power converter having two power switches which are periodically operated alternately between on and off states by a switch control to modulate the flow of power through a main primary winding of a transformer, the power switches being operated so that a period of dead time is interposed between switch operations during which neither switch is on, a snubber circuit for one of the power switches comprising:
- a capacitor;
- a first switch operable to connect the capacitor across the one power switch;
- an auxiliary primary winding inductively linked to the main primary winding;
- a second switch operable to connect the capacitor to the auxiliary primary winding;
- and
- a switch control including means for operating the first switch before turn-off of said one power switch to transfer energy upon turn-off of the one power switch from the transformer to said capacitor, and means for operating the second switch during the dead time following turn-off of the one power switch to transfer the energy from the capacitor to the auxiliary primary winding.
A snubber circuit for a power converter having two power switches which are periodically operated in alternate fashion between on and off states to modulate the flow of power through a main primary winding of an inductive load, the snubber circuit comprising:
- a capacitor;
- a first switch operable to connect the capacitor across one of the power switches;
- a second switch coupled to the capacitor;
- and
- a switch control coupled to the switches including means coupled to the second switch for developing switch control signals to the power switches, means for operating the first switch when the one power switch is on and means for operating the second switch after the one power switch is turned off to connect the capacitor to the developing means and transfer the transient energy resulting from turn-off of the one power switch to the other power switch to thereby operate same.