# US 4,561,458 A · Steam-metering method and apparatus

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 4,561,458 A
- Document ID: US4561458A
- Status: Granted
- Kind: A
- Application number: 06/673,022
- Filed: 1984-11-19
- Granted: 1985-12-31
- Earliest claimed: 1984-11-19
- Assignees: Spence Engineering Company
- Inventors: Rudolf H. Hoffmann
- Web page: https://patentgrep.com/patent/US4561458A

## CPC

- G01F 13/00: Apparatus for measuring by volume and delivering fluids or fluent solid materials, not provided for in the preceding groups
- Y10T 137/0324: With control of flow by a condition or characteristic of a fluid
- Y10T 137/2562: Dividing and recombining
- G01F: MEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
- Y10T: TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION

## Abstract

A steam or the like supply system has two parallel legs of supply, a first leg designed for high-demand flows and for the metering thereof, and a second leg designed for low-demand flows and for the metering thereof. Each of these legs has its own control valve, and an electronic controller responds to a sensed drop in demand to control a program of valve in the low-demand line; similarly, the controller responds to a sensed increase in demand to control a program of valve shut down in the low-demand leg while opening the control valve in the high-demand line. Protective features in the controller assure against response to transient changes in demand and against interruption of a valve-changing operation until the programmed change has been fully implemented.

## Claims

### Claim 1

In the method of metering the supply of steam over a wide range of demand involving a high-demand line and a low-demand line connected in parallel, wherein each line includes flow-metering means connected to a control valve to govern the transfer of flow to the low-demand line at the low end of the metering range of the high-demand line and to transfer flow to the high-demand line at the upper end of the range of the low-demand line,
the improvement which comprises
Step (1), delaying the control of any such transfer for a predetermined interval of sustained change in demand, whereby to avoid response to transient changes in demand;
Step (2), initiating the transfer control only after said predetermined interval has run, and
Step (3), effecting the transfer control by predetermined relatively slow progressive change in at least a valve-opening actuation of said control valves, whereby to avoid rapid change in the flow of steam in the line to which flow is being transferred.

### Claim 2 (depends on 1)

The improved method of claim 1, in which, once Step (3) has been initiated, it is irreversibly continued until completed.

### Claim 3 (depends on 1)

The improved method of claim 1, in which, for overload demand that is sensed at the upper end of the high-demand line, the control valve of the low-demand line is opened, whereby the sum of metering in both lines is the measure of total consumption under an overload condition.

### Claim 4 (depends on 1)

The improved method of claim 1, in which Step (3) is performed for one control valve concurrently with relatively rapid closure of the other control valve.

### Claim 5

In the method of metering the supply of a fluid over a wide range of demand involving a high-demand line and a low-demand line connected in parallel, wherein each line includes flow-metering means connected to a control valve to govern the transfer of flow to the low-demand line at the low end of the metering range of the high-demand line and to transfer flow to the high-demand line at the upper end of the range of the low-demand line,
the improvement which comprises
Step (1), delaying the control of any such transfer for a predetermined interval of sustained change in demand, whereby to avoid response to transient changes in demand;
Step (2), initiating only after said predetermined interval has run, and
Step (3), effecting the transfer control by predetermined relatively slow progressive change in at least a valve-opening actuation of said control valves, whereby to avoid rapid change in fluid flow in the line to which flow is being transferred.

### Claim 6 (depends on 5)

The improved method of claim 5, in which the fluid is steam.

### Claim 7

In a steam-flow measuring system comprising a high-demand line and a low-demand line connected in parallel between a supply-receiving inlet and a supply-delivering output, a motor-operated flow-control valve and a metering orifice in each of said lines, first and second differential-pressure switches connected across the respective orifices, the first of said differential-pressure switches being operative to change its state upon detection of steam flow at the upper end of the metering range of the low-demand line and the second of said differential-pressure switches being operative to change its state upon detection of steam flow at the lower end of the metering range of the high-demand line, a first resetting delay-timing switch connected for operation by said first differential-pressure switch for timing a first predetermined interval to avoid valve response to a steam-flow transient condition, first controller means responsive to completion of a timed delay by said first delay-timing switch and establishing a valve-opening motor-drive connection to the motor-operated control valve of the high-demand line, and second controller means concurrently responsive to completion of said first interval and establishing a valve-closing motor-drive connection to the motor-operated control valve of the low-demand line, a second resetting delay-timing switch connected for operation by said second differential-pressure switch for timing a second predetermined interval to avoid valve response to a steam-flow transient condition, said first controller means being responsive to completion of a second interval by said second delay-timing switch and establishing a valve-closing motor-drive connection to the motor-operated control valve of the high-demand line, and said second controller means being responsive to completion of said second interval and establishing a valve-opening motor-drive connection to the motor-operated control valve of the low-demand line.

### Claim 8 (depends on 7)

The steam-flow measuring system of claim 7, in which said first and second controllers include means whereby a given operation thereof, once started, continues to completion of said given operation for each of said controllers.

### Claim 9 (depends on 7)

The steam-flow measuring system of claim 7, in which each of said controllers is of a variety providing stepped increments of valve-positioning control at least for the valve-opening direction of control.

### Claim 10

In a steam-flow measuring system comprising a high-demand line and a low-demand line connected in parallel between a supply-receiving inlet and a supply-delivering output, a motor-operated flow-control valve and a metering orifice in each of said lines, first and second differential-pressure switches connected across the respective orifices, the first of said differential-pressure switches being operative to change its state upon detection of steam flow at the upper end of the metering range of the low-demand line and the second of said differential-pressure switches being operative to change its state upon detection of steam flow at the lower end of the metering range of the high-demand line, relay means having a first state wherein the flow-control valve motor for one of said lines is connected for a valve-opening run while the flow-control motor in the other of said lines is connected for a valve-closing run, said relay means having a second state wherein the flow-control valve motor for the other of said lines is connected for a valve-opening run while the flow-control motor in said one line is connected for a valve-closing run, and delay means interposed in the connection of one of said switches to operate said relay to said first state and in the connection of the other of said switches to operate said relay to said second state.

### Claim 11 (depends on 10)

The steam-flow measuring system of claim 10, in which hold-in means associated with both flow-control valve motors maintains the valve actuating drive of the involved motor until completion of the involved valve stroke, said hold-in means being interlocked to preclude any change of valve motor drive until both motors have completed their strokes.

### Claim 12 (depends on 7)

The steam-flow measuring system of claim 7, and including flow-responsive switch means set to change its state at the upper end of the metering range of the high-demand line, said last-mentioned switch means being connected to said first controller to establish a valve-opening motor-drive connection to the motor-operated control of the low-demand line upon a rise in demand beyond said upper end for the high-demand line, and said last-mentioned switch means being also connected to said first controller to establish a valve-closing motor-drive connection to the motor-operated control of the low-demand line upon a drop in demand below said upper end for the high-demand line.

### Claim 13

In a fluid-flow measuring system comprising a high-demand line and a low-demand line connected in parallel between a supply-receiving inlet and a supply-delivering output, a motor-operated flow-control valve and a flow-measuring device in each of said lines, the first of said flow-measuring devices being operative to produce an electrical change of state upon detection of fluid flow at the upper end of the metering range of the low-demand line and the second of said flow-measuring devices being operative to produce an electrical change of state upon detection of fluid flow at the lower end of the metering range of the high-demand line, relay means having a first state wherein the flow-control valve motor for one of said lines is connected for a valve-opening run while the flow-control motor in the other of said lines is connected for a valve-closing run, said relay means having a second state wherein the flow-control valve motor for the other of said lines is connected for a valve-opening run while the flow-control motor in said one line is connected for a valve-closing run, and delay means interposed in the connection of one of said flow-measuring devices to operate said relay to said first state and in the connection of the other of said flow-measuring devices to operate said relay to said second state.

### Claim 14

In a fluid-flow measuring system comprising a high-demand line and a low-demand line connected in parallel between a supply-receiving inlet and a supply-delivering output, a motor-operated flow-control valve and a flow-measuring device in each of said lines, the first of said flow-measuring devices being operative to produce an electrical change of state upon detection of fluid flow at the upper end of the metering range of the low-demand line and the second of said flow-measuring devices being operative to produce an electrical change of state upon detection of fluid flow at the lower end of the metering range of the high-demand line, first resetting delay-timing means connected for operation by said first flow-measuring device for timing a first predetermined interval to avoid valve response to a fluid-flow transient condition, first controller means responsive to completion of a timed delay by said first delay-timing means and establishing a valve-opening motor-drive connection to the motor-operated control valve of the high-demand line, and second controller means concurrently responsive to completion of said first interval and establishing a valve-closing motor-drive connection to the motor-operated control valve of the low-demand line, second resetting delay-timing means connected for operation by said second flow-measuring means for timing a second predetermined interval to avoid valve response to a fluid-flow transient condition, said first controller means being responsive to completion of a second interval by said second delay-timing means and establishing a valve-closing motor-drive connection to the motor-operated control valve of the high-demand line, and said second controller means being responsive to completion of said second interval and establishing a valve-opening motor-drive connection to the motor-operated control valve of the low-demand line.