Control system for hydroelectric power station system
AssigneeHitachi, Ltd.
InventorsMasuo Goto, Akira Isono, Tunehiko Takakusagi, Masanobu Araki, Haruo Ishikawa, Yukio Yamaguchi
Life of this patent
Estimating the term…
Loading patent…
AssigneeHitachi, Ltd.
InventorsMasuo Goto, Akira Isono, Tunehiko Takakusagi, Masanobu Araki, Haruo Ishikawa, Yukio Yamaguchi
Estimating the term…
In a control system for a hydroelectric power station system including upper and lower water reservoirs connected through a water channel, an intermediate water reservoir having a smaller storage capacity than those of the upper and lower reservoirs and provided on the water channel in cascade with the upper and lower reservoirs, and two power stations disposed between the upper and intermediate reservoirs and between the intermediate and lower reservoirs, respectively, the control system is arranged such that the water level of the intermediate reservoir is detected continuously and the detected value of the water level is used to correct the load instructions which are applied to the power stations for controlling outputs of the power stations whereby the water level of the intermediate reservoir is maintained substantially constant, while the power generation of the power stations is controlled so as to satisfactorily meet with the load instruction applied to the power system.
A control system for hydroelectric power station system including three water reservoir means having different water levels and connected in cascade through water channels therebetween and power stations in the respective water channels, in which load instructions applied to said respective power stations are corrected according to the water level of said intermediate reservoir and the operating condition of said respective power stations.
A control system for controlling a hydroelectric power station system including first and second water reservoirs of different water levels, a third water reservoir provided in cascade with and between said first and second reservoirs and having a water storage capacity smaller than those of said first and second reservoirs, and power stations provided between said first and third reservoirs and between said third and second reservoirs, respectively, in which load instructions applied to said respective power stations are produced by distributing an overall load instruction in accordance with the water level of said third reservoir.
A control system for controlling a hydroelectric power station system including first and second water reservoirs of different water levels, a third water reservoir provided in cascade between said first and second reservoirs and having a water storage capacity smaller than those of said first and second reservoirs and power stations between said first and third reservoirs and between said third and second reservoirs, respectively, in which load instructions applied to said respective power stations are produced by distributing an overall load instruction with a ratio determined in accordance with the rated outputs of said respective power stations and the load instructions are corrected according to the deviation of the water level of said third reservoir.
A control system for a hydroelectric power station system including first and second water reservoirs of different water levels, a third water reservoir provided between said first and second reservoirs in cascade and having a water storage capacity smaller than those of said first and second reservoirs, and power stations provided between said first and third reservoirs and between said third and second reservoirs, respectively, in which the load instructions applied to said respective power stations are produced by distributing an overall load instruction in accordance with the water levels of said first, second and third reservoirs.
A control system for controlling a hydroelectric power station system including first and second water reservoirs located upstream and downstream, respectively, in a water system, a third water reservoir located between said first and second reservoirs and having a smaller water storage capacity than that of any one of said first and second reservoirs, and first and second power stations provided between said first and third reservoirs and between said third and second reservoirs, respectively, said control system comprising first means for dividing a total load instruction representative of a required total power generation of said power station system into first and second individual load instructions and controlling said first and second power stations according to said first and second individual load instruction, respectively, and second means for selectively controlling at least one of said first and second power stations according to variation of the water level of said third water reservoir in place of the individual load instruction for the respective power stations depending on the water level of said third reservoir and the operating conditions of said power stations.
A control system for controlling a hydroelectric power station system including first and second water reservoirs located upstream and downstream, respectively, in a water system, a third water reservoir located between said first and second reservoirs and having a smaller water storage capacity than that of any one of said first and second reservoirs, and first and second power stations provided between said first and third reservoirs and between said third and second reservoirs, respectively, said control system comprising first means for dividing a total load instruction representative of a required total power generation of said power station system into first and second individual load instructions and for controlling said first and second power stations according to said first and second individual load instructions, respectively, and second means for selectively controlling at least one of said first and second power stations according to variation of the water level of said third reservoir in place of said individual load instruction for the respective power stations when the variation of the water level of said third reservoir exceeds at least one predetermined range.
A control system for controlling a hydroelectric power station system including first and second water reservoirs located upstream and downstream, respectively, in a water system, a third water reservoir located between said first and second reservoirs and having a smaller water storage capacity than that of any one of said first and second reservoirs, and first and second power stations provided between said first and third reservoirs and between said third and second reservoirs, respectively, said control system comprising first means for controlling the output of one of said first and second power stations according to a total load instruction representative of a required total power generation of the power station system, and second means for controlling the output of the other of said first and second power stations so as to maintain the water level of said third water reservoir substantially constant.
Dependencies are inferred from the claim text.