Method of and apparatus for the anchoring of drilling and production platforms on a structure sunk on a sea bottom
AssigneeHOCHTIEF AG fur Hoch-und Tiefbauten vorm. Gebr. Helfmann
InventorEckart Erler
Life of this patent
Estimating the term…
Loading patent…
AssigneeHOCHTIEF AG fur Hoch-und Tiefbauten vorm. Gebr. Helfmann
InventorEckart Erler
Estimating the term…
A system for anchoring drilling or production platforms upon a plurality of posts anchored in the sea bottom or on an artificial island comprises a cylinder structure formed at the top of each of the posts and a plunger depending from a semi-submersible platform adapted to be received with clearance within each of the cylinders. The platform is provided with sand bunkers adjacent the respective plungers and with releasable closures which open upon positioning of the platform above the posts to cause granular material to flow into the cylinder around the respective plungers, thereby cushioning the engagement of the platform by the posts.
A system for the securing of a semi-submersible platform to a plurality of upright posts disposed in the sea and anchored therein, said system comprising:
A method of supporting a platform upon a plurality of posts extending in an upright manner in the sea, said method comprising the steps of:
Dependencies are inferred from the claim text.
Drawings are temporarily unavailable. Open the PDF at USPTO
No related US applications are recorded in the indexed filing history.
With relative movement between supporting construction and platform: shock absorbing means for the supporting construction
Hydraulic engineering
Term ended 24 Jan 1995 (estimated)
USPTO file history isn’t available for this patent, so only indexed dates are shown.
The present invention relates to the anchoring of a drilling or production platform (hereinafter referred to in short as a "platform") upon the columns of a support structure previously affixed in the sea bottom or an artificial island, and, more particularly, to an arrangement for fixing the platform to such a structure whereby the kinetic energy of the platform, resulting from sea movements, is cushioned during the anchoring operation.
Drilling and production platforms, e.g. for the recovery of fossil-fuel material, for example, petroleum and natural gas, are frequently anchored to a support structure previously affixed in the sea bottom. Such platforms may be formed as semi-submersible sea-going vessels which can carry the drilling rig or production equipment and are adapted to be partially submerged in the sea and securely affixed to the substructure or support.
The support generally comprises a plurality (usually three) columns or posts which have previously been anchored in the sea bed and which are adapted to be affixed to the platform at their upper end.
The above and other objects, features and advantages of the present invention will become more readily apparent from the following description, reference being made to the accompanying drawing in which:
FIG. 1 is a vertical cross-sectional view through an assembly, in accordance with the invention, shown in diagrammatic form and comprising a column previously anchored in the sea floor or on a portion of an off-shore drilling island adapted to support a platform;
FIG. 2 is a view of the assembly in another position, i.e. after positioning of the platform;
Referring first to FIG. 3, it can be seen that a platform 1 of the semi-submersible type can be anchored to a plurality of posts or columns 2 in the sea 21, the posts having previously been anchored on the sea bottom 19 or an off-shore island formed on the sea bottom. The platform 1 can carry a drilling derekly and various housing structures 15 and 16 for pumps or the like for drilling or production of a fossil-fuel substance such as crude oil or natural gas. Winches 14 can be carried by the platform 1 and can have hawsers 13 which can be attached to eyes 12 on the columns 2 to align the plungers 7 with the sockets formed in the upper ends of the columns 2. The platform may have a hole 18 through which the drilling string can pass between the columns 2.
In FIGS. 1 and 2, more specifically, I have shown the drilling and production platform 1 as a semi-submersible vessel which can be floated into position with the plungers 7 above the respective sockets formed at the upper ends of the posts.
The deck load of the platform may range up to 40,000 Mp (Mp = 1,000 Kp where Kp = Kg-f, i.e. kilograms-force). To carry this load it is preferred to provide the posts 2 as part of an off-shore drilling island.