Pipeline retard, support and protection method
OwnerErnest I. Wilsoninventor
Life of this patent
Estimating the term…
Abstract
A pipeline retard, support and protection method wherein a fast-setting expandable foam is placed in a trench at spaced locations below and around a pipeline to create spaced retards and support pads in situ. Each retard and/or support pad is created in the absence of forms or other foam molding means for the expanding foam. The retards may be keyed to the trench walls and base for securement. The system is also adaptable to encapsulating a portion of the pipeline which transverses a roadbed.
Claims4
A method of inhibiting soil erosion along a pipeline in a trench, the steps of:
- selecting a pipeline segment which is characterized by a space between each side of the pipeline and the banks of the trench;
- directing the nozzle of a spray apparatus toward one of the spaces and delivering a foam reaction mixture through the spray nozzle to the bottom of the trench immediately adjacent one side of the pipeline segment and filling at least a portion of the space along the selected pipeline segment by creating an accretion of foam between one side of the pipeline segment and one bank of the trench;
- removing the spray nozzle to the other side of the pipeline segment essentially diametrally opposite the one side and repeating the directing and delivering steps and filling at least a portion of the space along the pipeline segment by creating an accretion of foam between the other side of the pipeline segment and the other bank of the trench, the accretion of foam on both sides of the pipeline segment forming a retard;
- and
- backfilling the trench around the accretion of foam forming the retard.
A method of inhibiting soil erosion along a pipeline situated in a trench, the steps of:
- selecting a segment of pipeline upon which a retard is to be formed, said segment having its sides spaced from both banks of the trench;
- suspending the pipeline segment such that a space exists between the bottom of the trench and the pipeline segment;
- inserting a spray nozzle into the trench and directing the spray nozzle toward the space between the trench bottom and the underside of the pipeline segment;
- spraying a foam reaction mixture into the space and substantially filling at least a portion of the space thereby forming a support pad;
- removing the spray nozzle to the space between one side of the pipeline segment and the trench bank and delivering foam reaction mixture into the space between the pipeline segment and the trench bank so as to be contiguous with the support pad, creating thereby an accretion of foam united with the support pad and filling at least a portion of the space only along the one side of the selected segment of pipeline;
- repeating the removing and delivering steps in the space between the other side of the pipeline segment and the trench bank contiguous with the support pad, creating thereby an accretion of foam united with the support pad and filling at least a portion of the space only along the other side of the selected pipeline segment;
- and
- terminating the accretion of foam before the foam reaches the upper edge of the trench banks thereby forming a retard in situ which is united with the support pad, substantially fills the spaces between the trench banks and the sides of the pipeline only along the pipeline segment and is recessed into the trench below the upper edge of the trench banks.
Dependencies are inferred from the claim text.