Apparatus and method for schedule monitoring and control
OwnerWilliam L. Kelleyinventor
Life of this patent
Estimating the term…
Abstract
For the scheduling of activities, particularly construction activities by the Critical Path Method, an apparatus is provided with a mechanical simulation of the network associated with the method, and is adapted to support a network chart of activities and events. It has a progress bar for monitoring such activities and events, which is power driven at a constant rate for indicating the scheduled progress of the entire project at any given time, whereby the scheduler can determine at a glance at the board what adjustments, if any, need be made in the timing and progress of the various activities of the project.
Claims11
Schedule control and monitoring apparatus for use in network type scheduling of a project having a plurality of interrelated activities with events at the start and termination thereof and wherein a succession of activities of the longest time path for the project are critical, said apparatus comprising a support frame, means for mounting on said frame a prepared chart on which a network schedule of such activities and events is written chronologically with the distance of consecutive critical activities drawn to scale representing scheduled times based on estimates of the durations to complete the respective activities, a plurality of magnets movably disposed on said frame behind said chart whereby the positions thereof can be changed, a plurality of markers of magnetic material adapted for disposition on the front face of said chart at said event points and supported by said magnets, an indicator bar mounted on said frame over said chart, and means for moving said indicator bar at a constant rate past said markers from a position indicating the commencement of the project to provide a comparison between the actual progress of any given activity and the scheduled progress thereof.
Schedule control and monitoring apparatus for a critical path method project which has a succession of activities some of which are critical whereby they must be completed on time if the project is not to be delayed and also comprising events which are times at which activities start or terminate, said apparatus comprising a support frame including a transparent panel, means mounting on the front face of said panel a prepared chart on which a network schedule of such activities and events is written chronologically with the distance between consecutive critical activities drawn to scale representing scheduled times based on estimates of the durations to complete the respective activities, magnets slidably mounted at the rear face of said panel for respectively supporting a plurality of markers of magnetic material on the front face of said chart at event points, means interconnecting a plurality of said magnets for simultaneously shifting said magnets along said chart when the schedule is to be changed, an indicator bar mounted on said frame over said chart, and means for moving said indicator bar at a constant rate past said markers from a position indicating the commencement of the project to provide a comparison between the actual progress of any given activity and the scheduled progress thereof.
A schedule control and monitoring method for use in network type scheduling wherein a plurality of interdependent activities culminating in events of a project are to be scheduled and monitored during progress of the project comprising the steps of:
- providing a chart on which a network schedule of activities and events of the project are presented chronologically with the distance between consecutive events drawn to a time scale representing scheduled times for performance of activities based on estimates of the durations thereof,
- mounting said networks chart upon a front face of a panel,
- forming a mechanical counterpart of the network of said chart on the back face of said panel by placing magnets at the locations of said events on the chart and mechanically linking the magnets between the events as related on the chart,
- placing a magnetically responsive marker on said chart at each event and supporting said markers by said magnets,
- drawing lines indicating the actual progress of said activities on the chart to the scale thereof, and
- moving an indicator bar at a constant rate related to the scale of the chart across the front face of said panel over said chart to provide a visual comparison of actual progress of the project to estimated times of completion of activities thereof.