A method of progressively constructing a wall of cementitious material, including the steps of supporting a formwork support structure on a lower foundation, or completed wall section, by means of hydraulic jacks each including a hydraulic ram assembly carrying the formwork support structure and adapted to climb up a vertically extending jack tube, raising said formwork support structure by said jacks to a higher pouring position, supporting said formwork support structure on the lower foundation, or wall section, by auxiliary support means, raising the jack tubes for each jack through its associated ram assembly, moving a formwork section on the outside of the wall toward a formwork section on the inside of said wall to provide a cavity for the receipt of cementitious material, pouring a quantity of said material into said space between said formwork sections, the lower foundation, or completed wall section, and the lower ends of the jack tubes, allowing said cementitious material to solidify, and moving the outer formwork section away from the wall and disengaging the inner formwork section, with said formwork support structure being supported on said jacks.
A method for prograssively constructing a plurality of substantially vertical walls of hardened cementitious material in successive, vertically incremental castings, said method comprising:
A method of progressively constructing at least one substantially vertical wall of hardened cememtitious material in successive, vertically incremental castings, including the steps of supporting a formwork support structure means on a completed incremental casting by jack means with said formwork support structure extending over said at least one wall and forming a common, rigid supporting assembly for a plurality of pairs of formwork sections, at least one pair of formwork sections associated with each wall to be built, each pair of formwork sections comprising a first formwork section and a facing second formwork section, said first formwork section being suspended from said formwork support structure means in a substantially vertical position, and said second formwork section being suspended from said formwork support structure means in a substantially vertical position, raising said formwork support structure means by said jack means to lift all of said formwork sections simultaneously substantially vertically upward from a first casting position to a second casting position, engaging retractable support means with at least one completed wall section of hardened cememtitious material to support said formwork support structure therefrom, and disengaging said jack means from said completed incremental casting and moving said jack means to a vertically upper position while supporting said formwork support structure on said retractable support means, moving at least one formwork section of a pair into a position relative to the other section of the pair to provide a cavity thereinbetween for receiving cementitious material, the top of the previous incremental casting defining the bottom of said cavity, introducing a quantity of cementitious material into said cavity, allowing the cementitious material in said cavity to solidify to form a subsequent incremental casting, and disengaging said second formwork section from the hardened cementitious material in said cavity, and moving each entire said first formwork section laterally and horizontally away from the second formwork section at least a distance to permit a person to pass between the first and second formwork sections, associating the jack means and the retractable support means so that there are alternate periods wherin said formwork support structure means and formwork sections are exclusively supported by said retractable support means and other periods wherein same are exclusively supported by said jack meaans;
Dependencies are inferred from the claim text.