# US 2026/0302783 A1 · Methods of operating an energy storage system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0302783 A1
- Document ID: US20260302783A1
- Status: Published application
- Kind: A1
- Application number: 18/996,322
- Filed: 2023-06-23
- Published: 2026-10-01
- Earliest claimed: 2022-07-18
- Assignees: Kraken Technologies Limited
- Applicants: Kraken Technologies Limited
- Inventors: Steve WATTAM; Mike LOWE
- Web page: https://patentgrep.com/patent/US20260302783A1

## CPC

- H02J 3/28: Arrangements for balancing of the load in networks by storage of energy
- H02J 3/00142: {Oscillations concerning frequency}
- H02J 3/003: {Load forecast, e.g. methods or systems for forecasting future load demand}
- H02J 7/82: Control of state of charge [SOC]
- H02J 7/933: {the cycle being controlled or terminated in response to electric parameters}
- H02J 2103/30: Simulating, planning, modelling, reliability check or computer assisted design [CAD] of electric power networks
- H02J 2103/40: Circuit arrangements adaptive to forecasted demand
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY

## Abstract

A method of operating an energy storage system arranged to supply power to a power grid at a time tb over a predetermined operation time window(POTW) includes determining a current state of charge, SoC, at a time t0; estimating a total energy usage between t0 and tb; determining a forecast SoC at tb based on the current SoC and the estimated total energy usage; inputting the forecast SoC, an operation constraint, and a system parameter specific to the energy storage system into an optimization algorithm. The operation constraint is an operation condition met by the system during the POTW. The method further includes determining power values, each decomposed into an integer component and a float component, corresponding to a time step during the POTW using the optimization algorithm, and selecting a power value with a zero float component to form an operation baseline for the POTW.

## Claims

### Claim 1

A method of operating an energy storage system, the energy storage system being arranged to supply power to a power grid at a time tb over a predetermined operation time window, the method comprising:
determining a current state of charge, SoC, of the energy storage system at a time t0;
estimating a total energy usage by the energy storage system between the time t0 and the time tb;
determining a forecast SoC of the energy storage system at the time tb based on the current SoC and the estimated total energy usage;
inputting the forecast SoC, at least one operation constraint and one or more system parameters to an optimisation algorithm, the at least one operation constraint being an operation condition to be met by the energy storage system during the predetermined operation time window, and the one or more system parameters being parameters specific to the energy storage system;
determining a plurality of power values each corresponding to a time step during the predetermined operation time window using the optimisation algorithm, wherein each power value is decomposed into an integer component and a float component; and
selecting one or more power values from the plurality of power values with a zero float component to form an operation baseline at which the energy storage system is to be operated during the predetermined operation time window.

### Claim 2 (depends on 1)

The method of claim 1, further comprising determining an average energy usage by the energy storage system at the time t0.

### Claim 3 (depends on 2)

The method of claim 2, wherein the total energy usage by the energy storage system between the time t0 and the time tb is estimated based on the average energy usage.

### Claim 4 (depends on 1)

The method of claim 1, further comprising measuring an amount of energy usage during a time period preceding the time t0.

### Claim 5 (depends on 4)

The method of claim 4, wherein the total energy usage by the energy storage system between the time t0 and the time tb is estimated based on the amount of energy usage during the time period preceding the time t0.

### Claim 6 (depends on 4)

The method of claim 4, wherein the time period preceding the time t0 is a time period immediately preceding the time t0 or any time period preceding the time t0, and wherein the time period preceding the time t0 is one hour or multiples of one hour.

### Claim 7 (depends on 1)

The method of claim 1, wherein the one or more system parameters comprise one or more of: a storage capacity of the energy storage system, a minimum SoC, a maximum SoC, a minimum power, a maximum power, a relationship between the energy storage system SoC and power.

### Claim 8 (depends on 7)

The method of claim 7, wherein the minimum SoC is 5% and wherein the maximum SoC is 95%.

### Claim 9 (depends on 1)

The method of claim 1, wherein the at least one operation constraint comprises one or more of: a target power at a predetermined time within the predetermined operation time window, a minimum power at the time tb, a maximum power at the time tb, a minimum power at an end time of the predetermined operation time window, a maximum power at an end time of the predetermined operation time window.

### Claim 10 (depends on 1)

The method of claim 1, wherein the one or more power values are selected from the plurality of power values based on the energy storage system operating under one or more criteria.

### Claim 11 (depends on 10)

The method of claim 10, wherein the one or more criteria comprise:
meeting a target amount of energy supplied over the predetermined operation time window, meeting a target amount of energy received over the predetermined operation time window, operating below a maximum rate of change of power, a power at which the energy storage system operate does not change from negative to positive or positive to negative within a single time step.

### Claim 12 (depends on 1)

The method of claim 1, further comprising operating the energy storage system according to the operation baseline during the predetermined operation time window.

### Claim 13 (depends on 1)

The method of claim 1, further comprising operating the energy storage system according to the operation baseline in addition to providing a frequency response service during the predetermined operation time window.

### Claim 14 (depends on 1)

The method of claim 1, wherein the predetermined operation time window comprises a plurality of time steps, each time step corresponding to one minute, two minutes, three minutes, four minutes, five minutes, or multiples of one minute.

### Claim 15 (depends on 1)

The method of claim 1, wherein the optimisation algorithm is a mixed integer linear programming algorithm.

### Claim 16

An apparatus for controlling operation of an energy storage system, the energy storage system being arranged to supply power to a power grid at a time tb over a predetermined operation time window, the apparatus comprising:
communication circuitry
at least one processor; and
a non-transitory computer-readable medium having stored thereon software instructions that, when executed by the at least one processor, cause the apparatus to:
determine a current state of charge, SoC, of the energy storage system at a time t0;
estimate a total energy usage by the energy storage system between the time t0 and the time tb;
determine a forecast SoC of the energy storage system at the time tb based on the current SoC and the estimated total energy usage;
input the forecast SoC, at least one operation constraint and one or more system parameters to an optimisation algorithm, the at least one operation constraint being an operation condition to be met by the energy storage system during the predetermined operation time window, and the one or more system parameters being parameters specific to the energy storage system;
determine a plurality of power values each corresponding to a time step during the predetermined operation time window using the optimisation algorithm, wherein each power value is decomposed into an integer component and a float component; and
select one or more power values from the plurality of power values with a zero float component to form an operation baseline at which the energy storage system is to be operated during the predetermined operation time window.

### Claim 17 (depends on 16)

The apparatus of claim 16, wherein the instructions further cause the apparatus to determine an average energy usage by the energy storage system at the time t0, wherein the total energy usage by the energy storage system between the time t0 and the time tb is estimated based on the average energy usage.

### Claim 18 (depends on 16)

The apparatus of claim 16, wherein the instructions further cause the apparatus to measure an amount of energy usage during a time period preceding the time t0, wherein the total energy usage by the energy storage system between the time to and the time tb is estimated based on the amount of energy usage during the time period preceding the time t0.

### Claim 19 (depends on 16)

The apparatus of claim 16, wherein the one or more system parameters comprise one or more of: a storage capacity of the energy storage system, a minimum SoC, a maximum SoC, a minimum power, a maximum power, a relationship between the energy storage system SoC and power.

### Claim 20 (depends on 16)

The apparatus of claim 16, wherein the at least one operation constraint comprises one or more of: a target power at a predetermined time within the predetermined operation time window, a minimum power at the time tb, a maximum power at the time tb, a minimum power at an end time of the predetermined operation time window, a maximum power at an end time of the predetermined operation time window.