# US 2026/0280292 A1 · Loading calculation

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0280292 A1
- Document ID: US20260280292A1
- Status: Published application
- Kind: A1
- Application number: 19/681,151
- Filed: 2026-05-19
- Published: 2026-09-17
- Earliest claimed: 2021-02-25
- Assignees: S&C Electric Company
- Applicants: S&C Electric Company
- Inventors: Qing Guo; Michael Quinlan; Yoav Sharon; Boris Marendic
- Web page: https://patentgrep.com/patent/US20260280292A1

## CPC

- H02J 3/06: Controlling the transfer of power between connected networks; Controlling load sharing between connected networks
- H04L 43/08: Monitoring or testing based on specific metrics, e.g. QoS, energy consumption or environmental parameters
- G01R 19/2513: {Arrangements for monitoring electric power systems, e.g. power lines or loads; Logging}
- G01R 31/086: {in power transmission or distribution networks, i.e. with interconnected conductors}
- G05B 19/042: using digital processors (G05B19/05 takes precedence)
- H02J 3/001: Arrangements for handling faults or abnormalities, e.g. emergencies or contingencies
- H02J 3/0073: by providing alternative feeding paths when the main path fails
- H02J 3/08: Synchronisation of networks
- H02J 3/17: Demand-responsive operation of AC power transmission or distribution networks
- H02J 13/36: specially adapted for protection systems
- H04L 41/12: Discovery or management of network topologies
- H04L 43/022: by sampling
- H04L 43/028: by filtering
- H04L 67/12: specially adapted for proprietary or special-purpose networking environments, e.g. medical networks, sensor networks, networks in vehicles or remote metering networks
- G05B 2219/2639: Energy management, use maximum of cheap power, keep peak load low
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H04L: TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION (arrangements common to telegraphic and telephonic communication H04M)
- G01R: MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES (indicating correct tuning of resonant circuits H03J3/12)
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)

## Abstract

A system and method for determining loads throughout a power distribution network having a plurality of switching devices provided along a feeder. The method includes measuring the current and/or voltage on one or both sides of the switching devices and calculating a power flowing through each of the switching devices and a load in each section using the current and/or voltage measurements at predetermined sample times. The method further includes storing a plurality of recorded current/voltage measurements or calculated powers flowing through each device for consecutive sample times. The method then determines a median load from the measurements and power flows and calculates a load in each of network sections.

## Claims

### Claim 1

A computer-implemented method of controlling an electrical power distribution network that includes at least one power source, a primary feeder partitioned into sections by switching devices, and at least one alternate source selectively connectable to one or more of the sections, the method comprising:
(a) obtaining, from switching devices positioned along the feeder, time-stamped current and/or voltage measurements for respective device sides and computing, at predetermined sample times, power flowing through each device, and for each section, a section load defined as the sum of power flowing into that section from all devices that bound the section;
(b) for each device side, storing a fixed-size history of the computed powers or underlying measurements across consecutive sample times and, for each section, determining a robust load estimate by applying a median filter over a predetermined number of the most recent section-load computations, whereby transient measurement outliers are rejected;
(c) maintaining, in the switching devices or a control center, an automatically updated topological model of the division of the feeder that specifies devices and the sections (teams) on each side of each device and disseminating device data between neighbor devices so that, at the end of each dissemination period, the control has up-to-date section information for restoration decisions;
(d) responsive to a known topology change that may directly alter section loading, clearing at least a portion of the stored measurement history such that subsequent median-filtered section-load estimates reflect post-change conditions more rapidly;
(e) for any section electrically adjacent to a constant-voltage source for which source-side measurements are unavailable, determining an available additional capacity for that source using a conservative computation based on the source maximum capability, a maximum allowed section load, and the latest robust section-load estimate measured from the section boundary;
(f) treating any distributed generation within a section as a negative load such that section load represents the algebraic combination of local consumption and distributed generation output;
(g) selecting and issuing switching commands to open and close switching devices to restore one or more de-energized sections, subject to constraints that each energized source and each alternate source is able to accommodate the aggregate of the robust section-load estimates on the corresponding restored segments connected thereto, including the available additional capacity determined in step (e); and
(h) after execution of the switching commands, repeating steps (a)-(g) in successive dissemination periods to update section-load estimates and to verify continuing compliance with source-capacity constraints during ongoing restoration or reconfiguration.

### Claim 2 (depends on 1)

The method of claim 1, wherein the current and/or voltage measurements comprise synchrophasor values, and calculating the power flowing through each switching device includes computing a complex power value using a measured or estimated voltage phasor and a complex conjugate of a measured current phasor.

### Claim 3 (depends on 1)

The method of claim 1, wherein determining the median load comprises applying a median filter to two-dimensional sample points, including real and imaginary components of complex power, and selecting as the median the sample closest to a reference point derived from medians of the real and imaginary parts.

### Claim 4 (depends on 1)

The method of claim 1, further comprising discarding the latest measurements in a dissemination period if any switching device reports a loss of voltage, and rejecting subsequent measurements from remaining devices during the same dissemination period so that the median filter uses only previously stored measurements.

### Claim 5 (depends on 1)

The method of claim 1, wherein the control clears the stored measurement history upon detecting a topology change that may directly alter section loads, and begins storing new measurements thereafter.

### Claim 6 (depends on 1)

The method of claim 1, wherein a distributed-generation source within a section is treated as a negative load, and the section load is computed as a sum of customer load and distributed-generation output.

### Claim 7 (depends on 1)

The method of claim 1, further comprising calculating a ratio of the load magnitudes of sections on both sides of a switching device upon detecting loss of communications with that device and, using the ratio, distributing a subsequently.

### Claim 8

A system for controlling an electrical power distribution network that includes at least one power source, a primary feeder partitioned into sections by switching devices, and at least one alternate source selectively connectable to one or more of the sections, the system comprising:
a plurality of switching devices positioned along the feeder, each switching device including:
(i) sensors configured to obtain time-stamped current measurements and, in some devices, voltage measurements on one or both sides of the device; and
(ii) local processing circuitry configured to compute, at predetermined sample times, power flowing through the device using the obtained measurements;
a communications interface coupled to the switching devices and configured to disseminate device information, including computed powers and device status, between neighbor devices and to a control device so that, at the end of each dissemination period, the control device possesses up-to-date information for the devices and sections of a division of the feeder;
a control device implemented in one or more of the switching devices or in a control center and comprising:
(a) a topology model storing a graph representation that identifies, for each switching device, the section on each device side and the devices on each section, thereby enabling automatic recovery and update of division topology from disseminated device and section (team) data;
(b) a memory configured to store, for each device side, a fixed-size history of computed powers or underlying measurements from consecutive sample times; and
(c) a median-filter module configured to determine, for each section, a robust section-load estimate as a median over a predetermined number of the most recent section-load computations, where each section load is defined as the sum of power flowing into that section from all devices bounding the section;
(d) a restoration logic module configured to:
(1) upon detection of a known topology change that may directly alter section loading, clear at least a portion of the stored history so that subsequent median-filtered section-load estimates reflect post-change conditions more rapidly;
(2) for any section that is electrically adjacent to a constant-voltage source and lacks source-side measurements, compute an available additional capacity for that source from a maximum source capability, a maximum allowed section load, and a latest robust section-load estimate measured at the section boundary;
(3) model any distributed generation within a section as negative load such that the section-load estimate represents an algebraic combination of consumption and distributed generation output; and
(4) select and issue switching commands to open and close the switching devices to restore one or more de-energized sections subject to constraints that each energized source and each alternate source can accommodate an aggregate of the robust section-load estimates on the corresponding restored segments, including the computed available additional capacity; wherein the control device is further configured to repeat acquisition, estimation, and constraint checking in successive dissemination periods to verify continued compliance with source-capacity constraints during ongoing restoration or reconfiguration.

### Claim 9 (depends on 8)

The system of claim 8, wherein the sensors are configured to obtain synchrophasor voltage and current measurements, and the local processing circuitry computes complex power as the product of a voltage phasor and complex conjugate of a current phasor.

### Claim 10 (depends on 8)

The system of claim 8, wherein the median-filter module is configured to apply a two-dimensional median filter using real and imaginary components of complex power and to select as the median the complex sample closest to a reference formed from medians of the real and imaginary parts.

### Claim 11 (depends on 8)

The system of claim 8, wherein the control device includes logic to discard the latest measurements whenever any device reports a loss of voltage and to reject measurements from other devices during that dissemination period to preserve valid historical data for median filtering.

### Claim 12 (depends on 8)

The system of claim 8, wherein the control device is further configured to clear its stored measurement history in response to a topology change that may directly alter section load values and to begin repopulating the measurement history thereafter.

### Claim 13 (depends on 8)

The system of claim 8, wherein the restoration logic module models a distributed-generation source located within a section as a negative load such that section load reflects both customer demand and distributed-generation output.

### Claim 14 (depends on 8)

The system of claim 8, wherein the restoration logic module is configured, upon detecting a loss of communications from a switching device, to store a ratio of the load magnitudes of the two sections adjacent to the device, compute a combined section load from available measurements, and distribute the combined load across the two sections according to the stored ratio.