Control system and method for a renewable power plant
AssigneeSiemens Gamesa Renewable Energy A/S
InventorsAbhishek Chaudhary, Aris Gkountaras, Mikkel Serup
Life of this patent
Estimating the term…
Loading patent…
AssigneeSiemens Gamesa Renewable Energy A/S
InventorsAbhishek Chaudhary, Aris Gkountaras, Mikkel Serup
Estimating the term…
A control system for a power plant supplying electrical energy to a utility grid is provided. The power plant includes a wind farm with at least one wind turbine and a load system with at least one load. Each load is configured to consume and transform energy provided from the wind farm or the utility grid at each point of time. The control system includes a frequency response system for obtaining at least one electrical property data of the utility grid as input, the frequency response system being further configured for a comparison of the obtained electrical property data with respective reference values and generating a control signal in dependence of the comparison. Further, the control system is configured to reduce its power consumption during a recovery period of the utility grid, the recovery period immediately following the inertial response.
1-12. (canceled)
A control system for a power plant supplying electrical energy to a utility grid, the power plant comprising a wind farm with at least one wind turbine and a load system with at least one load, each load being configured to consume and transform energy provided from the wind farm or the utility grid at each point of time, the control system comprising:
The control system according to claim 12, wherein the frequency response system is configured to provide the control signal with at least one setpoint to reduce the power consumption of the load system, in order to achieve an amount of energy supply to the utility grid which contains a buffer period during the recovery period.
The control system according to claim 12, wherein the frequency response system is configured to provide the control signal with at least one setpoint to reduce the power consumption of the load system, in order to achieve an amount of energy supply to the utility grid which contains a given rate of recovery during the recovery period.
The control system according to claim 12, wherein the frequency response system is configured to provide the control signal with at least one setpoint to reduce the power consumption of the load system, in order to achieve an amount of energy supply to the utility grid which contains a given maximum power drop during the recovery period.
The control system according to claim 12, wherein the frequency response system monitors the consumption level of at least one load during nominal operation and/or transient operation of the utility grid.
The control system according to claim 12, wherein the at least one load comprises at least one electrolyzer and/or at least one general load which can reduce its consumption in a controlled manner.
A control method for a power plant system supplying electrical energy to a utility grid, the power plant comprising a wind farm with at least one wind turbine and a load system with at least one load, each load being configured to consume and transform energy provided from the wind farm or the utility grid at each point of time, wherein
A computer program product comprising a computer readable hardware storage device having computer readable program code stored therein, said program code executable by a processor of a computer system to implement the method according to claim 10.
Dependencies are inferred from the claim text.