# US 2026/0228661 A1 · Plan creation system, plan creation method, program, and training device

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0228661 A1
- Document ID: US20260228661A1
- Status: Published application
- Kind: A1
- Application number: 19/151,699
- Filed: 2023-12-12
- Published: 2026-08-06
- Earliest claimed: 2023-02-09
- Assignees: NEC Corporation
- Applicants: NEC Corporation
- Inventors: Satoshi ODA; Takeshi AKAGAWA; Hideki KOMORI
- Web page: https://patentgrep.com/patent/US20260228661A1

## CPC

- G06Q 10/06313: {Resource planning in a project environment}
- G06Q 10/06: Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q 10/0631: Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR

## Abstract

This plan creation system comprises: an information reception unit that receives plan creation information including a classification and at least one of a goal, a delivery deadline, and a budget of a new project to be created; a plan creation unit that creates a plan about the received plan creation information by using a trained model which has been trained to output a plan for a project including one or more tasks for realizing the new project, by using, as inputs, actual result data including the classification, and at least one of the goal, the delivery deadline, and the budget, of a past project and the classification of one or more actual result tasks in which at least one of the goal, the delivery deadline, and the budget have been achieved; and an output unit that outputs the created plan.

## Claims

### Claim 1

A plan creation system comprising:
at least one memory storing instructions, and
at least one processor configured to execute the instructions to;
receive plan creation information including a classification of a new project to be created and at least one of a goal, a delivery deadline, or a budget of the new project;
create a plan based on the received plan creation information by using a trained model trained to output a plan for a project including one or more tasks for implementing the new project using, as inputs, actual result data including a classification of a past project, at least one of a goal, a delivery deadline, or a budget of the past project, and the classification of one or more actual result tasks in which at least one of the goal, the delivery deadline, or the budget of the past project have been achieved; and
output the created plan.

### Claim 2 (depends on 1)

The plan creation system according to claim 1, wherein the at least one processor is configured to execute the instructions to create a plan including a plurality of tasks having different granularities according to the classification of the new project to be created.

### Claim 3 (depends on 1)

The plan creation system according to claim 1, wherein
a plurality of the actual result tasks that have achieved the goal of the past project includes a relationship among the plurality of actual result tasks, and
the at least one processor is configured to execute the instructions to create a plan including an order relationship between two or more tasks or a parallel relationship between two or more tasks.

### Claim 4 (depends on 3)

The plan creation system according to claim 3, wherein the relationship among the plurality of actual result tasks that have achieved the goal of the past project includes at least one of presence or absence of a causal relationship among the plurality of actual result tasks, a temporal order among the plurality of actual result tasks, or a relationship of a superordinate concept or a subordinate concept.

### Claim 5 (depends on 1)

The plan creation system according to claim 1, wherein the information regarding the actual result task includes a level of proficiency of a worker including a simple work level.

### Claim 6 (depends on 5)

The plan creation system according to claim 5, wherein the information regarding the actual result task includes a workload per unit period of one worker according to the level of the proficiency.

### Claim 7 (depends on 1)

The plan creation system according to claim 1, wherein
the plan creation information includes information regarding a progress state, a worker change, a delivery deadline change, and a specification change for each task indicating whether some of the tasks after the project progresses are completed, and
the at least one processor is configured to execute the instructions to reconstruct a plan in consideration of the progress state, the worker change, the delivery deadline change, and the specification change for each task.

### Claim 8 (depends on 1)

The plan creation system according to claim 1, wherein the plan includes task assignment information for assigning a task to a person or a machine.

### Claim 9 (depends on 1)

The plan creation system according to claim 1, wherein the classification of the actual result task includes a major item and a minor item included in the major item.

### Claim 10 (depends on 1)

The plan creation system according to claim 1, wherein the at least one processor is configured to execute the instructions to create a plurality of plans, and each of the created plans includes information regarding whether each of the received delivery deadline and budget is satisfied.

### Claim 11

A plan creation method comprising:
receiving plan creation information including a classification of a new project to be created and at least one of a goal, a delivery deadline, or a budget of the new project;
creating a plan based on the received plan creation information by using a trained model trained to output a plan for a project including one or more tasks for implementing the new project using, as inputs, actual result data including a classification of a past project, at least one of a goal, a delivery deadline, or a budget of the past project, and the classification of one or more actual result tasks in which at least one of the goal, the delivery deadline, or the budget of the past project have been achieved; and
outputting the created plan.

### Claim 12 (depends on 11)

The plan creation method according to claim 11, further comprising outputting a plan including a plurality of tasks having different granularities according to the classification of the new project to be created.

### Claim 13 (depends on 11)

The plan creation method according to claim 11, wherein
a plurality of the actual result tasks that have achieved the goal of the past project includes a relationship among the plurality of actual result tasks, and
the plan creation method further comprises creating a plan including an order relationship between two or more tasks or a parallel relationship between two or more tasks.

### Claim 14 (depends on 13)

The plan creation method according to claim 13, wherein the relationship among the plurality of actual result tasks that have achieved the goal of the past project includes at least one of presence or absence of a causal relationship among the plurality of actual result tasks, a temporal order among the plurality of actual result tasks, or a relationship of a superordinate concept or a subordinate concept.

### Claim 15 (depends on 11)

The plan creation method according to claim 11, wherein information regarding the actual result task includes a level of proficiency of a worker including a simple work level.

### Claim 16 (depends on 11)

A non-transitory computer readable medium storing a program causing a computer to execute processing of the method according to claim 11.

### Claim 17 (depends on 16)

The non-transitory computer readable medium according to claim 16, further causing the computer to execute processing of outputting a plan including a plurality of tasks having different granularities according to the classification of the new project to be created.

### Claim 18 (depends on 16)

The non-transitory computer readable medium according to claim 16, wherein
a plurality of the actual result tasks that have achieved the goal of the past project includes a relationship among the plurality of actual result tasks, and
the program further causes the computer to execute processing of creating a plan including an order relationship between two or more tasks or a parallel relationship between two or more tasks.

### Claim 19 (depends on 18)

The non-transitory computer readable medium according to claim 18, wherein the relationship among the plurality of actual result tasks that have achieved the goal of the past project includes at least one of presence or absence of a causal relationship among the plurality of actual result tasks, a temporal order among the plurality of actual result tasks, or a relationship of a superordinate concept or a subordinate concept.

### Claim 20

A training device comprising:
at least one memory storing instructions, and
at least one processor configured to execute the instructions to;
acquire training data that is actual result data including a classification of a past project, at least one of a goal, a delivery deadline, or a budget of the past project, and the classification of one or more actual result tasks in which at least one of the goal, the delivery deadline, or the budget of the past project have been achieved; and
trained model trained to output a plan for a project including one or more tasks for implementing a new project using the training data as an input.