# US 2026/0185344 A1 · Lateral force resisting system for high-rise building

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0185344 A1
- Document ID: US20260185344A1
- Status: Published application
- Kind: A1
- Application number: 19/296,961
- Filed: 2025-08-12
- Published: 2026-07-02
- Earliest claimed: 2024-12-30
- Assignees: Dl E&C Co., Ltd
- Applicants: Dl E&C Co., Ltd
- Inventors: YOUNG LAK CHOI; JEONG MO KOO; SEUNG IL KIM; DAI YOUNG YUNE; GA LAM KIM; GEON UNG YOON; SEUNG JUN LEE
- Web page: https://patentgrep.com/patent/US20260185344A1

## CPC

- E04B 1/043: {Connections specially adapted therefor}
- E04B 1/165: {with elongated load-supporting parts, cast in situ (E04B1/161, E04B1/163 and E04B1/164 take precedence)}
- E04B 2103/02: of ceramics, concrete or other stone-like material
- E04B: GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS (border constructions of opening in walls, floors or ceilings E06B1/00; {electromagnetic shielding H05K9/0001})

## Abstract

The present disclosure relates to a lateral force resisting system for a high-rise building that includes: a plurality of outer walls spaced apart from one another in a transverse direction on the external face of the building; a link beam located at a level of a slab to connect the neighboring outer walls; and a prefabricated rebar assembly disposed in the link beam and comprising upper rebars each having both ends anchored on both side outer walls thereof, lower rebars located under the upper rebars and each having both ends anchored on both side outer walls thereof, and shear reinforcing bars for connecting the upper rebars and the lower rebars.

## Claims

### Claim 1

A lateral force resisting system for a high-rise building, comprising:
a plurality of outer walls (5) spaced apart from one another in a transverse direction on the external face of the building;
a link beam (6) located at a level of a slab (4) to connect the neighboring outer walls (5); and
a prefabricated rebar assembly (62) disposed inside the link beam (6) and comprising upper rebars (621) each having both ends anchored on both side outer walls (5) thereof, lower rebars (622) located under the upper rebars (621) and each having both ends anchored on both side outer walls (5) thereof, and shear reinforcing bars (623) for connecting the upper rebars (621) and the lower rebars (622).

### Claim 2 (depends on 1)

The lateral force resisting system according to claim 1, wherein the prefabricated rebar assembly (62) has at least two or more upper rebars (621) and at least two or more lower rebars (622), and the shear reinforcing bars (623) are stirrups for surroundingly holding the upper rebars (621) and the lower rebars (622).

### Claim 3 (depends on 2)

The lateral force resisting system according to claim 2, wherein the lower rebars (622) of the prefabricated rebar assembly (62) are located above a plurality of main bolts (63) located horizontally inside the link beam (6) on the location of the slab (4) to fix an outer wall form (7a) thereto.

### Claim 4 (depends on 3)

The lateral force resisting system according to claim 3, wherein the lower portion of the link beam (6) extends downward to form a reveal (6′) protrudingly formed below the slab (4) and the shear reinforcing bars (623) extend up to the interior of the reveal (6′).

### Claim 5 (depends on 4)

The lateral force resisting system according to claim 4, wherein on the bottom of the reveal (6′) are arranged lower horizontal rebars (65) in a lengthwise direction of the reveal (6′) on the construction site, and the shear reinforcing bars (623) of the prefabricated rebar assembly (62) are located on tops of the lower horizontal rebars (65).

### Claim 6 (depends on 4)

The lateral force resisting system according to claim 4, wherein the prefabricated rebar assembly (62) further comprises U bars (624) having the shapes of inverted U open on the lower portions thereof in such a way as to be located on tops of the upper rebars (621) between the neighboring shear reinforcing bars (623).

### Claim 7 (depends on 4)

The lateral force resisting system according to claim 4, wherein the prefabricated rebar assembly (62) further comprises auxiliary shear reinforcing bars (625) located among the neighboring shear reinforcing bars (623) to surround the outer peripheral surfaces of the upper rebars (621) and the lower rebars (622), while not extending toward the reveal (6′).

### Claim 8 (depends on 7)

The lateral force resisting system according to claim 7, wherein the prefabricated rebar assembly (62) further comprises a lattice bar (626) continuously bent to connect the upper rebars (621) and the lower rebars (622).

### Claim 9 (depends on 1)

The lateral force resisting system according to claim 1, wherein the prefabricated rebar assembly (62) is constituted of at least two or more unit assemblies (620) spaced apart from one another in a transverse direction thereof, each unit assembly (620) having one upper rebar (621), one lower rebar (622), and one shear reinforcing bar (623), and the neighboring unit assemblies (620) are connected to each other by means of connection bars (627) for connecting the upper rebars (621) of the unit assemblies (620) to each other and connecting the lower rebars (622) of the unit assemblies (620) to each other.

### Claim 10 (depends on 1)

The lateral force resisting system according to claim 1, further comprising:
a main core part (2) located on the central portion or one side of the building (1) and having a plurality of shear walls (20); and
sub core parts (3) located on positions spaced apart from the main core part (2) and each having at least two or more unit walls (30) located between a lower floor slab (4a) and an upper floor slab (4b).

### Claim 11 (depends on 10)

The lateral force resisting system according to claim 10, wherein the sub core parts (3) are located on the outermost positions of the building (1) on the plane.

### Claim 12 (depends on 11)

The lateral force resisting system according to claim 11, wherein the unit wall (30) of each sub core part (3) is a precast concrete (PC) wall located between the lower floor slab (4a) and the upper floor slab (4b).

### Claim 13 (depends on 12)

The lateral force resisting system according to claim 12, wherein the lower floor slab (4a) or the upper floor slab (4b) on the corresponding position to the unit wall (30) has a plurality of anchor bars (31) protruding therefrom toward the unit wall (30), and the unit wall (30) has vertical hollow holes (301) formed thereon to insert the anchor bars (31) thereinto.

### Claim 14 (depends on 12)

The lateral force resisting system according to claim 12, wherein the unit wall (30) is fixed between the lower floor slab and the upper floor slab by means of L-shaped fixing brackets (32) each having a vertical portion (321) fixed to the side surface of the unit wall (30) and a horizontal portion (322) fixed to the surface of the slab (4a or 4b).

### Claim 15 (depends on 12)

The lateral force resisting system according to claim 12, wherein the unit wall (30) has a stress isolation pad (33) located on top or underside thereof to prevent vertical loads from being transferred thereto.

### Claim 16 (depends on 12)

The lateral force resisting system according to claim 12, wherein the unit wall (30) is configured to allow one end portion thereof to be fixed to an edge wall (10) as any one of an outer wall and inner wall disposed perpendicularly thereto and to allow top and underside thereof to be separable structurally from the lower floor slab (4a) and the upper floor slab (4b).

### Claim 17 (depends on 16)

The lateral force resisting system according to claim 16, wherein the unit wall (30) is spaced apart from the edge wall (10), the edge wall (10) and the unit wall (30) having closed-loop type wall ties (11 and 34) protruding from the front surface of the edge wall (10) and one end of the unit wall (30) on the corresponding positions between the edge wall (10) and the unit wall (30) in such a way as to be overlaid on top of each other, and the unit wall (30) has a rebar (35) passing through the portions where the wall ties (11 and 34) are overlaid on top of each other and bonding concrete (36) cast in a space between one end of the unit wall (30) and the edge wall (10).

### Claim 18 (depends on 16)

The lateral force resisting system according to claim 16, wherein the edge wall (10) has a plurality of bonding bolts (12) protruding from the front surface thereof on the positions corresponding to the unit wall (30), and the unit wall (30) has coupling pockets (37) formed on one end thereof in such a way as to allow the bonding bolts (12) to pass therethrough and to be thus received therein, whereby fixing nuts (13) are fastened to the bonding bolts (12) inside the coupling pockets (37).

### Claim 19 (depends on 10)

The lateral force resisting system according to claim 10, wherein the unit wall (30) has anchor hooks (38) protruding from the end portion thereof in such a way as to allow the front ends thereof to be buriedly anchored on the edge wall (10) as any one of the outer wall and inner wall disposed perpendicularly to the unit wall (30) and a stress isolation pad (33) located on any one of top and underside thereof to prevent the vertical loads from being transferred thereto.

### Claim 20 (depends on 12)

The lateral force resisting system according to claim 12, wherein the unit wall (30) of the sub core part (3) has a plurality of tendons (39) provided vertically therein to apply prestress thereto through post-tensioning.