# US 2026/0163072 A1 · Method and apparatus for manufacturing secondary battery

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0163072 A1
- Document ID: US20260163072A1
- Status: Published application
- Kind: A1
- Application number: 19/177,847
- Filed: 2025-04-14
- Published: 2026-06-11
- Earliest claimed: 2024-07-19
- Assignees: Samsung SDI Co., Ltd.
- Applicants: Samsung SDI Co., Ltd.
- Inventors: EUNJOO KO; DUCKHYUN KIM; JINMUN KIM; SUHYEON KANG; BYEONGGWAN LEE; CHANHYUNG LEE; HUIJU CHOI
- Web page: https://patentgrep.com/patent/US20260163072A1

## CPC

- H01M 10/049: {Processes for forming or storing electrodes in the battery container}
- H01M 10/4214: {Arrangements for moving electrodes or electrolyte}
- H01M 10/052: Li-accumulators
- H01M 10/058: Construction or manufacture
- H01M 10/446: {Initial charging measures}
- H01M 10/52: Removing gases inside the secondary cell, e.g. by absorption (vent plugs or other mechanical arrangements for facilitating escape of gases H01M50/30)
- H01M 50/609: Arrangements or processes for filling with liquid, e.g. electrolytes
- H01M 50/70: Arrangements for stirring or circulating the electrolyte
- Y02E 60/10: Energy storage using batteries
- Y02P 70/50: Manufacturing or production processes characterised by the final manufactured product
- H01M: PROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

A method of manufacturing a secondary battery is provided wherein efficiency of a secondary battery manufacturing process is improved and the secondary battery is more structurally stable. The method of manufacturing a secondary battery includes providing a secondary battery, injecting an electrolyte into the secondary battery, activating the secondary battery into which the electrolyte is injected, and applying ultrasonic waves to the electrolyte in the secondary battery.

## Claims

### Claim 1

A method of manufacturing a secondary battery, the method comprising:
providing a secondary battery;
injecting an electrolyte into the secondary battery;
activating the secondary battery into which the electrolyte is injected; and
applying ultrasonic waves to the electrolyte in the secondary battery.

### Claim 2 (depends on 1)

The method of claim 1, wherein the activating of the secondary battery and the applying of the ultrasonic waves to the electrolyte are performed simultaneously.

### Claim 3 (depends on 2)

The method of claim 2, wherein the applying of the ultrasonic waves to the electrolyte is performed while a state of charge of the secondary battery increases.

### Claim 4 (depends on 2)

The method of claim 2, wherein the activating of the secondary battery comprises initially charging the secondary battery and aging the secondary battery that is initially charged, and
wherein the applying of the ultrasonic waves to the electrolyte is performed while the initial charging of the secondary battery is performed.

### Claim 5 (depends on 1)

The method of claim 1, wherein, in the applying of the ultrasonic waves to the electrolyte, a frequency of the ultrasonic waves is variable.

### Claim 6 (depends on 5)

The method of claim 5, wherein the frequency of the ultrasonic waves applied to the electrolyte is adjusted according to a state of charge of the secondary battery.

### Claim 7 (depends on 6)

The method of claim 6, wherein, when the state of charge of the secondary battery is less than a preset value, the frequency of the ultrasonic waves applied to the electrolyte is adjusted to be higher than the frequency of the ultrasonic waves applied to the electrolyte when the state of charge of the secondary battery is greater than the preset value.

### Claim 8 (depends on 5)

The method of claim 5, wherein the frequency of the ultrasonic waves applied to the electrolyte is adjusted according to an activation time of the secondary battery.

### Claim 9 (depends on 8)

The method of claim 8, wherein, when the activation time of the secondary battery is shorter than a preset time, the frequency of the ultrasonic waves applied to the electrolyte is adjusted to be higher than the frequency of the ultrasonic waves applied to the electrolyte when the activation time of the secondary battery is longer than the preset time.

### Claim 10 (depends on 2)

The method of claim 2, wherein the applying of the ultrasonic waves to the electrolyte comprises:
applying ultrasonic waves having a first frequency to the electrolyte for a first time; and
applying ultrasonic waves having a second frequency lower than the first frequency to the electrolyte for a second time that is shorter than the first time.

### Claim 11 (depends on 10)

The method of claim 10, wherein the applying of the ultrasonic waves having the first frequency and the applying of the ultrasonic waves having the second frequency are performed repeatedly.

### Claim 12 (depends on 11)

The method of claim 11, wherein a ratio of the first time to the second time is 3 to 5.

### Claim 13 (depends on 1)

The method of claim 1, wherein, in the applying of the ultrasonic waves to the electrolyte, a frequency of the ultrasonic waves applied to the electrolyte is 20 kHz to 20 MHz.

### Claim 14

An apparatus for manufacturing a secondary battery, the apparatus comprising:
a charging unit electrically connected to a secondary battery and configured to charge the secondary battery, wherein an electrolyte is provided in the secondary battery;
an ultrasonic generator configured to apply ultrasonic waves to a side of the secondary battery; and
a controller configured to control driving of the ultrasonic generator while the secondary battery is charged.

### Claim 15 (depends on 14)

The apparatus of claim 14, wherein the controller is configured to control the driving of the ultrasonic generator to adjust a frequency of the ultrasonic waves applied to the secondary battery.

### Claim 16 (depends on 15)

The apparatus of claim 15, wherein the controller is capable of measuring a state of charge of the secondary battery and adjusting the frequency of the ultrasonic waves applied to the secondary battery according to the state of charge of the secondary battery.

### Claim 17 (depends on 16)

The apparatus of claim 16, wherein, when the state of charge of the secondary battery is less than a preset value, the controller adjusts the frequency of the ultrasonic waves applied to the secondary battery to be higher than the frequency of the ultrasonic waves applied to the secondary battery when the state of charge of the secondary battery is greater than the preset value.

### Claim 18 (depends on 15)

The apparatus of claim 15, wherein the controller adjusts the frequency of the ultrasonic waves applied to the secondary battery according to a charging time of the secondary battery.

### Claim 19 (depends on 18)

The apparatus of claim 18, wherein, when the charging time of the secondary battery is shorter than a preset time, the controller adjusts the frequency of the ultrasonic waves applied to the secondary battery to be higher than the frequency of the ultrasonic waves applied to the secondary battery when the charging time of the secondary battery is longer than the preset time.

### Claim 20 (depends on 14)

The apparatus of claim 14, wherein a frequency of the ultrasonic waves applied to the secondary battery by the ultrasonic generator is 20 kHz to 20 MHz.