# US 2026/0101200 A1 · Communication network reconfiguration for electrical power events

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0101200 A1
- Document ID: US20260101200A1
- Status: Published application
- Kind: A1
- Application number: 18/907,014
- Filed: 2024-10-04
- Published: 2026-04-09
- Earliest claimed: 2024-10-04
- Assignees: AT&T Intellectual Property I, L.P.
- Applicants: AT&T Intellectual Property I, L.P.
- Inventors: Rohit Abhishek; Farooq Bari
- Web page: https://patentgrep.com/patent/US20260101200A1

## CPC

- H04W 24/02: Arrangements for optimising operational condition
- H04L 41/0896: Bandwidth or capacity management, i.e. automatically increasing or decreasing capacities (flow or congestion control using dynamic resource allocation, e.g. in-call renegotiation, H04L47/76)
- H04W: WIRELESS COMMUNICATION NETWORKS (broadcast communication H04H; communication systems using wireless links for non-selective communication, e.g. wireless extensions H04M1/72)
- H04L: TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION (arrangements common to telegraphic and telephonic communication H04M)

## Abstract

A processing system including at least one processor of a communication network may detect an electrical power event of an alternating current electrical power distribution network. The processing system may next select one or more remedial actions in the communication network in response to a severity level of the electrical power event, where the processing system is configured to apply different sets of one or more remedial actions for different severity levels of electrical power events. The processing system may then implement the one or more remedial actions to reconfigure the communication network in response to the severity level of the electrical power event.

## Claims

### Claim 1

A method comprising:
detecting, by a processing system including at least one processor of a communication network, an electrical power event of an alternating current electrical power distribution network;
selecting, by the processing system, one or more remedial actions in the communication network in response to a severity level of the electrical power event, wherein the processing system is configured to apply different sets of one or more remedial actions for different severity levels of electrical power events; and
implementing, by the processing system, the one or more remedial actions to reconfigure the communication network in response to the severity level of the electrical power event.

### Claim 2 (depends on 1)

The method of claim 1, wherein the communication network comprises a wireless network.

### Claim 3 (depends on 1)

The method of claim 1, wherein the different severity levels of electrical power events comprise defined severity levels according to one or more factors.

### Claim 4 (depends on 1)

The method of claim 1, wherein the electrical power event is detected in accordance with electrical power data from one or more network elements of the communication network.

### Claim 5 (depends on 4)

The method of claim 4, wherein the electrical power data includes at least one of:
a voltage measure;
a frequency;
a current measure; or
a uniformity measure.

### Claim 6 (depends on 1)

The method of claim 1, wherein the electrical power event is detected in accordance with electrical power data from the alternating current electrical power distribution network.

### Claim 7 (depends on 6)

The method of claim 6, wherein the electrical power data is modulated onto an alternating current electrical power signal from the alternating current electrical power distribution network.

### Claim 8 (depends on 7)

The method of claim 7, wherein the electrical power data comprises an indicator of the severity level from among the different severity levels.

### Claim 9 (depends on 1)

The method of claim 1, wherein the electrical power event comprises a forecast electrical power event.

### Claim 10 (depends on 9)

The method of claim 9, wherein the electrical power event is detected via at least one machine learning model implemented by the processing system.

### Claim 11 (depends on 10)

The method of claim 10, wherein inputs to the at least one machine learning model include electrical power data from at least one of:
one or more network elements; or
the alternating current electrical power distribution network, and wherein an output of the machine learning model comprises the severity level.

### Claim 12 (depends on 11)

The method of claim 11, wherein the at least one machine learning model is trained in accordance with a training data set comprising historical sets of electrical power data of the one or more network elements, wherein the historical sets of electrical power data are associated with respective labels indicating respective severity levels of electrical power events.

### Claim 13 (depends on 1)

The method of claim 1, wherein the electrical power event comprises at least one of:
a loss of electrical power event; or
an excess demand electrical power event.

### Claim 14 (depends on 1)

The method of claim 1, wherein when the severity level comprises a first severity level, the one or more remedial actions include at least one of:
reducing data processing tasks that are designated as non-critical task at one or more network elements of the communication network; or
reducing processor speed at the one or more of the network elements.

### Claim 15 (depends on 14)

The method of claim 14, wherein when the severity level comprises a second severity level that is more severe than the first severity level, the one or more remedial actions include at least one of:
reducing a network capacity of the communication network for non-essential data traffic; or
imposing endpoint device connection limits for one or more access points of the communication network.

### Claim 16 (depends on 15)

The method of claim 15, wherein when the severity level comprises a third severity level that is more severe than the second severity level, the one or more remedial actions include at least one of:
shutting down one or more network elements that are designated as non-critical network elements;
blocking data traffic for non-emergency services;
configuring one or more of the network elements to maintain a low-power hibernation mode; or
configuring an operations, administration, and management system of the communication network to operate in a standby mode.

### Claim 17 (depends on 1)

The method of claim 1, wherein the one or more remedial actions include:
transmitting instructions to one or more endpoint devices to reduce data traffic for the one or more endpoint devices across the communication network.

### Claim 18 (depends on 17)

The method of claim 17, wherein the one or more endpoint devices comprise endpoint devices that are not associated with subscriptions for continuity of network service during electrical power events.

### Claim 19

A non-transitory computer-readable medium storing instructions which, when executed by a processing system including at least one processor deployed in a communication network, cause the processing system to perform operations, the operations comprising:
detecting an electrical power event of an alternating current electrical power distribution network;
selecting one or more remedial actions in the communication network in response to a severity level of the electrical power event, wherein the processing system is configured to apply different sets of one or more remedial actions for different severity levels of electrical power events; and
implementing the one or more remedial actions to reconfigure the communication network in response to the severity level of the electrical power event.

### Claim 20

An apparatus comprising:
a processing system including at least one processor; and
a non-transitory computer-readable medium storing instructions which, when executed by the processing system when deployed in a communication network, cause the processing system to perform operations, the operations comprising:
detecting an electrical power event of an alternating current electrical power distribution network;
selecting one or more remedial actions in the communication network in response to a severity level of the electrical power event, wherein the processing system is configured to apply different sets of one or more remedial actions for different severity levels of electrical power events; and
implementing the one or more remedial actions to reconfigure the communication network in response to the severity level of the electrical power event.