# US 2026/0098446 A1 · Methods and systems for converting office buildings into residential use

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0098446 A1
- Document ID: US20260098446A1
- Status: Published application
- Kind: A1
- Application number: 19/328,299
- Filed: 2025-09-15
- Published: 2026-04-09
- Earliest claimed: 2024-10-09
- Inventors: Gal EHRLICH
- Web page: https://patentgrep.com/patent/US20260098446A1

## CPC

- E06B 9/68: Operating devices or mechanisms, e.g. with electric drive
- E06B 9/28: with horizontal lamellae, e.g. non-liftable (louvre windows or gratings E06B7/08)
- E06B 9/36: with vertical lamellae {; Supporting rails therefor}
- E06B 2009/2423: {Combinations of at least two screens}
- E06B 2009/2464: {featuring transparency control by applying voltage, e.g. LCD, electrochromic panels}
- E06B 2009/2476: {Solar cells}
- E06B 2009/6827: {sensing light}
- E06B: FIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES (shades or blinds for greenhouses A01G9/22; curtains A47H; lids for car boots or bonnets B62D25/10; skylights E04B7/18; sunshades, awnings E04F10/00)

## Abstract

A method and system for converting an office building into residential use by enhancing water supply and wastewater management capabilities. Vertical water supply lines and vertical wastewater pipes are installed within a pre-existing elevator shaft to increase supply and disposal capacities. Floor-level water distribution systems supply water to residential units from the vertical water supply lines, while floor-level wastewater collectors receive wastewater, which is then pumped to the vertical wastewater pipes.

## Claims

### Claim 1

A method for converting a multi-story office building into a multi-story residential building, said office building having a vertical and continuous internal core, at least a part of or the entire said internal core is load-bearing of the building, said internal core housing:
(i) a plurality of elevators, each in a pre-existing elevator shaft;
(ii) a pre-existing vertical fresh water pipe; and
(iii) a pre-existing vertical waste water pipe;
the method comprising:
(a) repurposing at least one said pre-existing elevator shafts in the internal core, by removing at least one said elevators from within said at least one said pre-existing elevator shafts, so as to generate at least one elevator-free elevator shafts, and vertically installing, within said at least one elevator-free elevator shafts at least one augmenting fresh water pipe and/or augmenting waste water pipe, so as to increase a residential capacity of the multi-story office building, wherein the multi-story residential building comprises at least one additional pre-existing elevator shafts in the internal core which houses at least one operational elevator, wherein a majority of floors of the office building are converted into a plurality of residential units.

### Claim 2 (depends on 1)

The method of claim 1, further comprising vertically installing, within an additional pre-existing shaft of said internal core at least one additional augmenting fresh water pipe and/or additional augmenting waste water pipe.

### Claim 3 (depends on 1)

The method of claim 1, wherein said internal core further houses a pre-existing installation selected from the group consisting of air ventilation pipes and systems, air conditioning pipes, air tunnels and systems, electricity lines and panels, data lines and waste water ventilation pipes.

### Claim 4 (depends on 3)

The method of claim 3, further comprising installing within said at least one elevator-free elevator shaft and/or said additional pre-existing shaft at least one augmenting said installation.

### Claim 5 (depends on 1)

The method of claim 1, further comprising installing a plurality of floor-level wastewater collectors; each said plurality of floor-level wastewater collectors configured for gravitationally collecting wastewater from said residential units of any of said floor levels and transferring said wastewater from the floor-level wastewater collectors to said vertical wastewater pipes by a plurality of pumps.

### Claim 6 (depends on 5)

The method of claim 5, wherein said pumps are located in the pre-existing elevator-free elevator shaft.

### Claim 7 (depends on 1)

The method of claim 1, further comprising configuring at least one said residential unit on each floor such that water is supplied to the residential unit from a floor-level water distribution system connected to the vertical fresh water pipe in said at least one elevator-free elevator shaft.

### Claim 8 (depends on 1)

The method of claim 1, wherein leakage control systems are implemented to detect and contain any leakage from the augmenting wastewater pipes or the augmenting fresh water pipes.

### Claim 9 (depends on 1)

The method of claim 1, further comprising structurally reinforcing said elevator-free elevator shaft to support the additional systems installed.

### Claim 10 (depends on 1)

The method of claim 1, wherein the residential building comprises at least two additional centrally located pre-existing elevator shafts, each housing an operational elevator, which are equipped with improved scheduling software to reduce wait times due to decrease elevator availability and the converting of the office building.

### Claim 11 (depends on 1)

The method of claim 1, wherein at least 80 % of the outer façade of the building is fabricated from glass.

### Claim 12 (depends on 1)

The method of claim 1, wherein the multi-story building is at least five stories high.

### Claim 13 (depends on 1)

The method of claim 1, wherein a floor area of the building is greater than 300 square meters.

### Claim 14 (depends on 1)

The method of claim 1, wherein a floor area of the building is greater than 1,000 square meters.

### Claim 15 (depends on 1)

The method of claim 1, further comprising installing sun-shielding elements on the facade of the building, wherein the sun-shielding elements are controllable by occupants of each said residential unit to selectively allow or block sunlight entering their respective units.

### Claim 16 (depends on 15)

The method of claim 15, wherein the sun-shielding elements comprise darkening glass panels that adjust transparency in response to control signals from residents of the building.

### Claim 17 (depends on 15)

The method of claim 15, wherein the sun-shielding elements comprise blinds installed on the facade, operable to adjust the amount of sunlight entering the residential units.

### Claim 18 (depends on 15)

The method of claim 15, further comprising installing individual control interfaces within each said at least one residential unit to operate the sun-shielding elements.

### Claim 19 (depends on 15)

The method of claim 15, wherein the sun-shielding elements are installed over pre-existing windows of the building facade.

### Claim 20 (depends on 1)

A residential building converted from an office building according to claim 1.