# US 2026/0062104 A1 · Maintenance management method for a ship

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0062104 A1
- Document ID: US20260062104A1
- Status: Published application
- Kind: A1
- Application number: 19/379,880
- Filed: 2025-11-05
- Published: 2026-03-05
- Earliest claimed: 2018-11-15
- Assignees: Gaztransport Et Technigaz
- Applicants: Gaztransport Et Technigaz
- Inventors: Nicolas Dupont; Florent Ouvrard
- Web page: https://patentgrep.com/patent/US20260062104A1

## CPC

- B63B 79/40: for controlling the operation of vessels, e.g. monitoring their speed, routing or maintenance schedules
- B63B 25/16: heat-insulated (insulating panelling B63B3/68; heating or cooling B63J)
- B63B 57/00: Tank {or cargo hold} cleaning specially adapted for vessels (tank cleaning in general B08B9/08)
- B63B 71/00: Designing vessels; Predicting their performance
- B63B 79/00: Monitoring properties or operating parameters of vessels in operation
- B63B 79/20: using models or simulation, e.g. statistical models or stochastic models
- B63B 79/30: for diagnosing, testing or predicting the integrity or performance of vessels
- F17C 1/002: {Storage in barges or on ships}
- G01F 23/00: Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm
- G05B 23/0283: {Predictive maintenance, e.g. involving the monitoring of a system and, based on the monitoring results, taking decisions on the maintenance schedule of the monitored system; Estimating remaining useful life [RUL] (preventive maintenance, i.e. planning maintenance according to the available resources without monitoring the system G06Q10/06)}
- F17C 2260/015: Facilitating maintenance
- F17C 2260/016: Preventing slosh
- B63B: SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING (arrangements of vessel ventilation, heating, cooling, or air-conditioning B63J2/00; floating substructures as supports of dredgers or soil-shifting machines E02F9/06)
- F17C: VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES (storing fluids in natural or artificial cavities or chambers in the earth B65G5/00; construction or assembling of bulk storage containers employing civil-engineering techniques E04H7/00; variable-capacity gas-holders F17B; liquefaction or refrigeration machines, plants, or systems F25)
- G01F: MEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)

## Abstract

The invention relates to a method for managing maintenance for a ship comprising a sealed and thermally insulating tank for transporting liquefied gas. The method comprises the steps consisting in determining 310 a current filling level of the tank, determining 320 a current state of movement of the ship, determining 330 a current sloshing index IBi from the current filling level of the tank and the current state of movement of the ship, taking into account the position and the geometry of the tank, integrating 340 the determined current sloshing index IBi into a wear index IUi that takes into account a history of the sloshing indices. The wear index is then compared to a threshold in order to indicate if the tank needs to be inspected, depending on the result of the comparison.

## Claims

### Claim 1

A method for managing maintenance for a ship including at least one sealed and thermally insulating tank for transporting liquefied gas, the tank having a geometry and a position on the ship. The method comprises the steps consisting in:
determining a current filling level of the tank,
determining a current state of movement of the ship,
determining a current sloshing index IBi from the current filling level of the tank and the current state of movement of the ship, taking into account the position and the geometry of the tank,
integrating the determined current sloshing index IBi into a wear index IUi that takes into account a history of the sloshing indices,
comparing the wear index to a first threshold in order to indicate if the tank needs to be inspected, depending on the result of the comparison.

### Claim 2 (depends on 1)

The method as claimed in claim 1, in which the ship includes a plurality of tanks, in which a wear index (IUi) is determined for each tank and in which the first threshold corresponds to a wear index (IUi) of another tank in order to indicate that an inspection of the tank that has the highest wear index (Max (IUi)) must be carried out.

### Claim 3 (depends on 1)

The method as claimed in claim 1, in which an inspection of the indicated tank is carried out.

### Claim 4 (depends on 2)

The method as claimed in claim 2, in which, after inspection of the tank corresponding to the highest wear index (Max (IUi)), and if that inspected tank is damaged then there is determined the next tank that must be inspected as being the tank having the highest wear index of the remaining tanks.

### Claim 5 (depends on 2)

The method as claimed in claim 2, in which, after inspection of a tank, and if that tank is not damaged, then the inspection of the tanks is halted.

### Claim 6 (depends on 1)

The method as claimed in claim 1, in which the comparison of the wear index (IUi) to a threshold is carried out during a maintenance operation on the ship.

### Claim 7 (depends on 1)

The method as claimed in claim 1, in which determining a current state of movement of the ship includes determining at least one of the following parameters:
height of the waves,
period of the waves,
angle of attack of the waves relative to the orientation of the ship,
speed of the ship,
vibrations of the ship,
measured movements of the ship.

### Claim 8 (depends on 1)

The method as claimed in claim 1, in which determining a current sloshing index (IBi) takes into account at least one of the following additional structure state parameters:
number of thermal cycles to which the tank has been subjected,
elongation of the ship,
level of stiffness of the hull,
nature of the liquefied gas,
level of filling of the ballast tanks.

### Claim 9 (depends on 1)

The method as claimed in claim 1, in which determining the current sloshing index (IBi) consists in determining a probability of deterioration of the tank when it is subjected to the current state of movement of the ship.

### Claim 10 (depends on 1)

The method as claimed in claim 1, in which the current sloshing index (IBi) is obtained by reading a value in a multiple entry correspondence table, an entry corresponding to the filling of the tank, at least one entry corresponding to the current state of movement of the ship and the read value representing a probability of deterioration of the tank.

### Claim 11 (depends on 1)

The method as claimed in claim 1, in which integrating the current sloshing index (IBi) corresponds to a summation of current sloshing indices, the current sloshing indices being calculated successively during successive measurement periods.

### Claim 12

A system for managing maintenance for a ship including at least one sealed and thermally insulating tank for transporting liquefied gas, the system including:
at least one tank filling level sensor for measuring a current level of filling of the at least one tank,
a device for evaluating movements of the ship able to determine a current state of movement of the ship,
a processing means configured:
to determine a current sloshing index (IBi) from the current level of filling of the tank and the current state of movement of the ship, taking into account the position and the geometry of the tank,
integrating the current sloshing index (IBi) determined into a wear index (IUi) that takes into account a history of the sloshing indices,
comparing the wear index to a first threshold,
a warning device indicating if an inspection of the at least one tank must be carried out as a function of the result of the comparison.

### Claim 13 (depends on 12)

The system as claimed in claim 12, in which the device for evaluating movements of the ship includes a weather station that measures the height, the frequency and the direction of the waves in the environment of the ship.

### Claim 14 (depends on 12)

The system as claimed in claim 12, in which the processing means is in part located in a monitoring station on land and communicated by radio to the ship to receive information relating to the current level of filling of the at least one tank and the current state of movement of the ship.

### Claim 15 (depends on 12)

A ship for transporting liquefied gas including a plurality of sealed and thermally insulating tanks, the ship including a management system as claimed in claim 12 for each of its tanks.