# US 2026/0015812 A1 · Method for forming a foundation pile in the ground

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2026/0015812 A1
- Document ID: US20260015812A1
- Status: Published application
- Kind: A1
- Application number: 18/992,068
- Filed: 2023-07-13
- Published: 2026-01-15
- Earliest claimed: 2022-09-16
- Assignees: BAUER Offshore Technologies GmbH
- Applicants: BAUER Offshore Technologies GmbH
- Inventors: Paul SCHELLER
- Web page: https://patentgrep.com/patent/US20260015812A1

## CPC

- E02D 5/38: making by use of mould-pipes or other moulds
- E02D 5/40: in open water
- E02D 5/46: making in situ by forcing bonding agents into gravel fillings or the soil (consolidating soil in general E02D3/12)
- E02D 5/665: {for making piles}
- E02D 15/06: Placing concrete under water {(for surfacing the bottom of bodies of water E02B3/121)}
- E02D 15/08: Sinking workpieces into water or soil {inasmuch as not provided for elsewhere}
- E02D 7/28: Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes {(E02D13/08 takes precedence)}
- E02D 13/00: Accessories for placing or removing piles or bulkheads {, e.g. noise attenuating chambers}
- E02D: FOUNDATIONS; EXCAVATIONS; EMBANKMENTS (specially adapted for hydraulic engineering E02B); UNDERGROUND OR UNDERWATER STRUCTURES {(tunnels, tunnelling, mining E21)}

## Abstract

The invention relates to a method for forming a foundation pile in the ground, in which a drilled hole is created in the ground, a pile tube is gripped by means of a handling device and inserted into the drilled hole, and a curable medium is introduced into an annular space between a wall of the drilled hole and an outer circumference of the pile tube, which medium cures to form the foundation pile. According to the invention, it is provided that the curable medium is introduced into the drilled hole via the handling device.

## Claims

### Claim 1

A method for forming a foundation pile in the ground, in which
a drilled hole is created in the ground,
a pile tube is gripped by means of a handling device and inserted into the drilled hole, and
a curable medium is introduced into an annular space between a wall of the drilled hole and an outer circumference of the pile tube, which medium cures to form the foundation pile, wherein
the curable medium is introduced into the drilled hole via the handling device.

### Claim 2 (depends on 1)

The method according to claim 1, wherein
the curable medium is introduced into the drilled hole, while the pile tube is held by the handling device.

### Claim 3 (depends on 1)

The method according to claim 1, wherein
the curable medium is conducted by means of at least one conveying line through the handling device up to at least one feed opening on the pile tube,
wherein the curable medium is conducted via at least one line through the tube wall of the pile tube and emerges into the annular space via at least one outlet opening on the outer circumference of the pile tube.

### Claim 4 (depends on 3)

The method according to claim 3, wherein
two conveying lines and/or lines are provided, which are switched by at least one valve means in such a way that they are connected in parallel for forming a dual feed line, or are connected in series for rinsing operation.

### Claim 5 (depends on 3)

The method according to claim 3, wherein
at least one outlet opening is located in a lower region of the pile tube and the curable medium fills the annular space from the bottom to the top.

### Claim 6 (depends on 1)

The method according to claim 1, wherein
an excess pressure is generated at least in the pile tube, in a lower portion, which excess pressure counteracts an entry of curable medium from the annular space into the interior of the pile tube.

### Claim 7 (depends on 6)

The method according to claim 6, wherein
in order to form an excess pressure in the lower portion of the pile tube a bulkhead plate is arranged therein, which bulkhead plate seals off the lower portion from an upper portion located there above.

### Claim 8 (depends on 7)

The method according to claim 7, wherein
for inserting the pile tube into a drilled hole filled with liquid, at least one through-opening on the bulkhead plate is opened.

### Claim 9 (depends on 7)

The method according to claim 7, wherein
the at least one through-opening is closed after the pile tube has been placed on a drilled hole bottom and before the curable medium is introduced.

### Claim 10 (depends on 1)

The method according to claim 1, wherein
for inserting the pile tube into the drilled hole the handling device is coupled to a lifting equipment, and
after the introduction of the curable medium the lifting equipment is released from the handling device and the handling device remains on the pile tube as an extra load, at least until the medium is cured.

### Claim 11 (depends on 10)

The method according to claim 10, wherein
after the curing of the medium the handling device is released from the pile tube and is salvaged.

### Claim 12 (depends on 1)

The method according to claim 1, wherein
the foundation pile is created under water in a bottom of a body of water as the ground.

### Claim 13 (depends on 1)

The method according to any one of claim 1, wherein
the handling device is actuated based upon a watercraft.

### Claim 14 (depends on 1)

The method according to claim 1, wherein
the handling device is connected via a releasable connecting device to at least one supply line.