# US 2025/0319953 A1 · Symmetric or pseudosymmetric shared mooring-anchor system

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2025/0319953 A1
- Document ID: US20250319953A1
- Status: Published application
- Kind: A1
- Application number: 19/093,835
- Filed: 2025-03-28
- Published: 2025-10-16
- Earliest claimed: 2024-04-10
- Assignees: Arup IP Management, Ltd.
- Applicants: Arup IP Management, Ltd.
- Inventors: Adam Jaffe
- Web page: https://patentgrep.com/patent/US20250319953A1

## CPC

- B63B 77/00: Transporting or installing offshore structures on site using buoyancy forces, e.g. using semi-submersible barges, ballasting the structure or transporting of oil-and-gas platforms
- B63B 21/50: Anchoring arrangements {or methods} for special vessels, e.g. for floating drilling platforms or dredgers
- B63B 21/502: {by means of tension legs}
- B63B 2021/505: {Methods for installation or mooring of floating offshore platforms on site}
- B63B 2035/446: {for converting wind energy into electric energy}
- B63B: SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING (arrangements of vessel ventilation, heating, cooling, or air-conditioning B63J2/00; floating substructures as supports of dredgers or soil-shifting machines E02F9/06)

## Abstract

A shared mooring-anchor system may have one or more variable resource foundations, the one or more variable resource foundations supporting a variable resource. A shared mooring-anchor system may have at least one near-surface buoy and at least one seabed anchor. A shared mooring-anchor system may orient the variable resource near, at, or above a waterline of a source of water. A shared mooring-anchor system may connect the one or more variable resource foundations to the at least one near-surface buoy, the at least one near-surface buoy is connected to the at least one seabed anchor, the at least one seabed anchor is not vertically in alignment underneath the at least one near-surface buoy, an angle between the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is not a right angle.

## Claims

### Claim 1

A method of organizing a system of one or more offshore variable resource structures, the method comprising the steps of:
providing one or more variable resource foundations, the one or more variable resource foundations supporting a variable resource;
providing at least one near-surface buoy;
providing at least one seabed anchor;
orienting the variable resource near, at, or above a waterline of a body of water; and
connecting the one or more variable resource foundations to the at least one near-surface buoy, the at least one near-surface buoy is connected to the at least one seabed anchor, the at least one seabed anchor is not vertically in alignment underneath the at least one near-surface buoy, an angle between the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is not a right angle.

### Claim 2 (depends on 1)

The method of claim 1, further comprising introducing a degree of compliance to reduce a load on the at least one seabed anchor.

### Claim 3

A shared mooring anchor system, comprising:
one or more variable resource foundations, the one or more variable resource foundations supporting a variable resource, the variable resource is oriented near, at, or above a waterline of a body of water;
at least one near-surface buoy;
at least one seabed anchor;
wherein the one or more variable resource foundations is connected to the at least one near-surface buoy, the at least one near-surface buoy is connected to the at least one seabed anchor in an arrangement;
wherein the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is positioned based on rules of symmetry, and
the at least one seabed anchor is not vertically in alignment underneath the at least one near-surface buoy.

### Claim 4 (depends on 3)

The system of claim 3, wherein the variable resource is positioned within a hexagonal lattice.

### Claim 5 (depends on 3)

The system of claim 3, wherein the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is positioned based on the rules of symmetry, whereby, the variable resource is positioned at an internal symmetry of a unit cell being tetragonal.

### Claim 6 (depends on 3)

The system of claim 3, wherein the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is positioned based on the rules of symmetry, whereby, the variable resource is positioned at an internal symmetry of a unit cell being orthorhombic.

### Claim 7 (depends on 3)

The system of claim 3, wherein the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is positioned based on the rules of symmetry, whereby, the variable resource is positioned at an internal symmetry of a unit cell being monoclinic.

### Claim 8 (depends on 3)

The system of claim 3, wherein the at least one near-surface buoy is placed at a face center, the at least one near-surface buoy is placed at one or more positions per a unit cell to triangulate the variable resource.

### Claim 9 (depends on 3)

The system of claim 3, wherein the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is positioned based on the rules of symmetry, whereby, the variable resource is positioned at vertices of a lattice of a unit cell being a rhombus.

### Claim 10 (depends on 3)

The system of claim 3, wherein the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor is positioned based on the rules of symmetry, whereby, the variable resource is positioned at vertices of a lattice of a unit cell being a parallelogram.

### Claim 11 (depends on 3)

The system of claim 3, wherein the one or more variable resource foundations, the at least one near-surface buoy, and the at least one seabed anchor are densely positioned based on a weather forecast.

### Claim 12 (depends on 3)

The system of claim 3, wherein the variable resource is connected to the at least one near-surface buoy by one or more lengths of mooring line.

### Claim 13 (depends on 3)

The system of claim 3, wherein the variable resource is connected to the at least one near-surface buoy by one or more lengths of mooring line which have been pretensioned.

### Claim 14 (depends on 3)

The system of claim 3, wherein a plurality of near-surface buoys are connected in series.

### Claim 15 (depends on 3)

The system of claim 3, wherein the at least one near-surface buoy is connected to the at least one seabed anchor by one or more lengths of mooring line.

### Claim 16 (depends on 3)

The system of claim 3, wherein the variable resource is connected to the at least one near-surface buoy by one or more lengths of mooring line which have been subdivided to provide rotational restraint to the variable resource.

### Claim 17 (depends on 3)

The system of claim 3, wherein the variable resource is connected to the at least one near-surface buoy by one or more lengths of mooring line which have been spliced.

### Claim 18 (depends on 3)

The system of claim 3, wherein the at least one near-surface buoy is connected to the at least one seabed anchor by one or more lengths of mooring line.

### Claim 19 (depends on 3)

The system of claim 3, wherein the at least one near-surface buoy is connected to the at least one seabed anchor by one or more lengths of mooring line which have been spliced.

### Claim 20 (depends on 3)

The system of claim 3, further comprising:
divers and an unmanned underwater vehicle to implement an installation of the system.

### Claim 21 (depends on 3)

The system of claim 3, further comprising an intermediate system to mitigate a transfer of loads to the at least one seabed anchor.

### Claim 22 (depends on 21)

The system of claim 21, wherein the intermediate system selected from the group consisting of a spring, an elastomer, a load collector, and a dashpot.

### Claim 23

An offshore mooring system, comprising:
an anchor positioned on a seabed;
a buoy positioned between the anchor and a floating foundation;
a first mooring line of a first axial stiffness value, connecting the anchor to the buoy; and
a second mooring line of a second axial stiffness value being less than the first axial stiffness value and connecting the buoy to the floating foundation;
wherein the second mooring line is configured to absorb dynamic forces from the floating foundation.

### Claim 24 (depends on 23)

The offshore mooring system of claim 23, wherein the buoy is sized to generate a buoyant force to induce static restraining forces in the first mooring line and the second mooring line.

### Claim 25

An offshore mooring system, comprising:
an anchor positioned on a seabed;
a buoy positioned between the anchor and a floating foundation;
a first mooring line of a first axial stiffness value, connecting the anchor to the buoy; and
a second mooring line of a second axial stiffness value being at least substantially similar to or equal to the first axial stiffness value and connecting the buoy to the floating foundation;
wherein the buoy is configured to convert one or more dynamic forces from the floating foundation into buoyant potential energy.

### Claim 26 (depends on 25)

The offshore mooring system of claim 25, wherein the buoy is sized to generate a buoyant force to induce small static restraining forces in the first mooring line and the second mooring line such that the buoy is not unduly restrained from motion in a lateral direction or a vertical direction.

### Claim 27 (depends on 25)

The offshore mooring system of claim 25, wherein the buoy is designed to generate hydrodynamic drag forces to dissipate energy associated with the one or more dynamic forces.