# US 2025/0304409 A1 · Systems and methods for adjusting elevator load settings

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2025/0304409 A1
- Document ID: US20250304409A1
- Status: Published application
- Kind: A1
- Application number: 19/234,612
- Filed: 2025-06-11
- Published: 2025-10-02
- Earliest claimed: 2020-08-26
- Assignees: Appana Industries LLC
- Applicants: Appana Industries LLC
- Inventors: Amarnauth APPANA, JR.
- Web page: https://patentgrep.com/patent/US20250304409A1

## CPC

- B66B 1/3407: {Setting or modification of parameters of the control system}
- B66B 1/2466: {For elevator systems with multiple shafts and multiple cars per shaft}
- B66B 1/28: electrical (detecting excessive speed B66B5/04 {; control of electrical motor H02P})
- B66B 1/3476: {Load weighing or car passenger counting devices (B66B5/14 takes precedence)}
- B66B 2201/215: Transportation capacity
- B66B 2201/222: Taking into account the number of passengers present in the elevator car to be allocated
- B66B 2201/235: Taking into account predicted future events, e.g. predicted future call inputs
- B66B 2201/242: Parking control
- B66B: ELEVATORS; ESCALATORS OR MOVING WALKWAYS ({apparatus for raising or lowering persons on theatrical stages or the like A63J5/12} ; funicular railbound systems with rigid ground-supported tracks and cable traction, e.g. cliff railways, B61B9/00; arrangements of ammunition handlers in vessels B63G3/00; hoists, lifts, or conveyors for loading or unloading in general B65G; braking or detent devices controlling normal movements of winding drums or barrels B66D; ship-lifting devices E02C; garages for many vehicles with mechanical means for lifting vehicles E04H6/12; hoists for feeding ammunition or projectiles to launching apparatus or to loading mechanisms F41A9/00)

## Abstract

A method of adjusting a load setting of an elevator car that includes receiving one or more load measurements associated with the elevator car and determining a maximum load of the elevator car from the one or more load measurements. The method further includes generating a modified load setting for the elevator car based on the maximum load and replacing the load setting of the elevator car with the modified load setting.

## Claims

### Claim 1

A method of adjusting a load setting of an elevator car, comprising:
receiving one or more load measurements associated with the elevator car;
generating a modified load setting for the elevator car based on a maximum load of the elevator car from the one or more load measurements;
replacing the load setting of the elevator car with the modified load setting for a predefined period such that the modified load setting is replaced with the load setting upon completion of the predefined period.

### Claim 2 (depends on 1)

The method of claim 1, wherein prior to completion of the predefined period, the method further comprises:
receiving a new load measurement associated with the elevator car; and
comparing the new load measurement to the modified load setting.

### Claim 3 (depends on 2)

The method of claim 2, further comprising:
rendering the elevator car inoperable to receive a call in response to determining the new load measurement exceeds the modified load setting, or operable to receive the call in response to determining the new load measurement does not exceed the modified load setting.

### Claim 4 (depends on 1)

The method of claim 1, wherein the modified load setting replaces the load setting for the predefined period, and the modified load setting defines an adjusted capacity of the elevator car relative to the load setting.

### Claim 5 (depends on 1)

The method of claim 1, wherein the predefined period includes a predefined time interval throughout a duration, the predefined time interval including at least one of:
hourly intervals throughout a day;
daily intervals throughout a week;
weekly intervals throughout a month; or
monthly intervals throughout a year.

### Claim 6 (depends on 1)

The method of claim 1, further comprising:
receiving a new load measurement associated with the elevator car after completion of the predefined period;
comparing the new load measurement to the load setting; and
rendering the elevator car inoperable to receive a call in response to determining the new load measurement exceeds the load setting, or operable to receive the call in response to determining the new load measurement does not exceed the load setting.

### Claim 7 (depends on 1)

The method of claim 1, wherein the one or more load measurements are received during an occurrence of the predefined period, such that the maximum load of the elevator car is associated with the predefined period.

### Claim 8 (depends on 1)

The method of claim 1, further comprising:
receiving the one or more load measurements during a plurality of predefined periods;
determining the maximum load of the elevator car for each of the plurality of predefined periods; and
generating at least one modified load setting for each of the plurality of predefined periods based on the maximum load associated with each of the plurality of predefined periods.

### Claim 9 (depends on 1)

The method of claim 1, wherein prior to generating the modified load setting for the elevator car, the method comprises:
comparing the maximum load to the load setting;
determining a difference between the maximum load and the load setting exceeds a predetermined threshold; and
generating the modified load setting in response to the difference exceeding the predetermined threshold.

### Claim 10 (depends on 1)

The method of claim 1, wherein the load setting defines a first maximum load capacity of the elevator car, and the modified load setting defines a second maximum load capacity of the elevator car that is less than the first maximum load capacity.

### Claim 11

A method of operating a plurality of elevator cars, comprising:
measuring a plurality of load measurements of each of the plurality of elevator cars;
generating a modified load setting for each of the plurality of elevator cars based on a maximum load of each of the plurality of elevator cars from the plurality of load measurements; and
activating the modified load setting of each of the plurality of elevator cars in substitute of an original load setting during a predefined period such that the original load setting of each of the plurality of elevator cars is reactivated in substitute of the modified load setting upon completion of the predefined period.

### Claim 12 (depends on 11)

The method of claim 11, wherein prior to completion of the predefined period, the method further comprises:
receiving a call for at least one of the plurality of elevator cars during the predefined period;
measuring a new load of each of the plurality of elevator cars for comparison to the modified load setting of each of the plurality of elevator cars.

### Claim 13 (depends on 12)

The method of claim 12, further comprising:
determining a load of a first elevator car of the plurality of elevator cars does not exceed the modified load setting; and
dispatching the first elevator car to the call.

### Claim 14 (depends on 12)

The method of claim 12, further comprising:
determining a load of a first elevator car of the plurality of elevator cars exceeds the modified load setting; and
preventing dispatch of the first elevator car to the call.

### Claim 15 (depends on 11)

The method of claim 11, wherein the predefined period includes a predefined time interval throughout a duration, the predefined time interval including at least one of:
hourly intervals throughout a day;
daily intervals throughout a week;
weekly intervals throughout a month; or
monthly intervals throughout a year.

### Claim 16 (depends on 11)

The method of claim 11, further comprising:
determining an updated maximum load for each of the plurality of elevator cars in response to measuring one or more additional load measurements during the predefined period;
generating an updated modified load setting for each of the plurality of elevator cars based on the updated maximum load associated with each of the plurality of elevator cars; and
activating the updated modified load setting in substitute of the original load setting during an occurrence of the predefined period.

### Claim 17

A system for adjusting a load setting of an elevator car, comprising:
a processor; and
a memory storing instructions that, when executed by the processor, causes the processor to perform operations including:
receiving one or more load measurements associated with the elevator car;
generating a modified load setting for the elevator car based on a maximum load of the elevator from the one or more load measurements;
substituting the load setting of the elevator car with the modified load setting for a predefined period such that the modified load setting is substituted with the load setting upon completion of the predefined period.

### Claim 18 (depends on 17)

The system of claim 17, wherein the modified load setting defines a reduced occupant capacity of the elevator car relative to the load setting.

### Claim 19 (depends on 18)

The system of claim 18, wherein the one or more load measurements are received during the predefined period, such that the maximum load of the elevator car is associated with the predefined period.

### Claim 20 (depends on 18)

The system of claim 18, the operations further including:
receiving one or more load measurements during a plurality of predefined periods;
determining the maximum load of the elevator car for each of the plurality of predefined periods based on the one or more load measurements; and
generating at least one modified load setting of the elevator car for each of the plurality of predefined periods based on the maximum load associated with each of the plurality of predefined periods.