A method for constructing a data center using an existing building includes identifying locations of beams in a first level of the existing building in which a server is placed; specifying layout options that include a server placement region that is surrounded by the beams and a floor removal region in a second level immediately above the first level, the floor removal region being directly above the server placement region; and determining, in the layout options, a layout of the data center in accordance with a weight of a server placed in the server placement region and a weight of a floor in the floor removal region.
A method for constructing a data center using an existing building, the method comprising:
A data center construction system comprising a circuitry configured to determine a layout for installing a server of a data center in an existing building, wherein the circuitry is configured to execute:
A data center provided in an existing building, comprising: