# US 2025/0167690 A1 · Full-bridge power converter

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2025/0167690 A1
- Document ID: US20250167690A1
- Status: Published application
- Kind: A1
- Application number: 18/764,193
- Filed: 2024-07-04
- Published: 2025-05-22
- Earliest claimed: 2023-11-21
- Assignees: APh ePower Co., Ltd.
- Applicants: APh ePower Co., Ltd.
- Inventors: Jian-Min Wang; Wei-En Hu; Kai-Lun Yi; Hsiu-Hsien Su; Shang-Zeng Huang
- Web page: https://patentgrep.com/patent/US20250167690A1

## CPC

- H02M 1/32: Means for protecting converters other than automatic disconnection
- H02M 3/33573: {Full-bridge at primary side of an isolation transformer}
- H02M 1/0058: {by employing soft switching techniques, i.e. commutation of transistors when applied voltage is zero or when current flow is zero (using an auxiliary actively switched resonant commutation circuit connected to an intermediate DC voltage or between two push-pull branches of an inverter bridge H02M7/4811; in resonant inverters H02M7/4815; in inverters operating from a resonant DC source H02M7/4826)}
- H02M 1/36: Means for starting or stopping converters
- H02M 3/01: {Resonant DC/DC converters}
- H02M 3/33584: {Bidirectional converters}
- H02M 3/33592: {having a synchronous rectifier circuit or a synchronous freewheeling circuit at the secondary side of an isolation transformer}
- H02M: APPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF (transformers H01F; dynamo-electric converters H02K47/00; controlling transformers, reactors or choke coils, control or regulation of electric motors, generators or dynamo-electric converters H02P)

## Abstract

A full-bridge power converter is provided. The full-bridge power converter includes a transformer circuit, an input-side circuit, an output-side circuit, and a controller. The input-side circuit includes an input-side full-bridge circuit and an input inductor. The input-side full-bridge circuit includes multiple power switches. The input inductor is coupled between a positive power terminal of the battery module and the input-side full-bridge circuit. The output-side circuit includes an output-side full-bridge circuit and an output capacitor. The controller turns on the power switches during a first period, causing the transformer circuit to release an electric energy stored in the transformer circuit. The controller turns on the power switches during a second period after the first period, and controls the output-side full-bridge circuit to precharge the output-side full-bridge circuit by using an energy stored in the output capacitor.

## Claims

### Claim 1

A full-bridge power converter, comprising:
a transformer circuit;
an input-side circuit, coupled to a primary circuit of the transformer circuit, comprising:
an input-side full-bridge circuit, comprising a first power switch, a second power switch, a third power switch, and a fourth power switch; and
an input inductor, coupled between a positive power terminal of a battery module and the input-side full-bridge circuit;
an output-side circuit, comprising:
an output-side full-bridge circuit, coupled to a first terminal of a load, a second terminal of the load, and a secondary circuit of the transformer circuit; and
an output capacitor, coupled between the first terminal of the load and the second terminal of the load; and
a controller, coupled to the input-side circuit and the output-side circuit, configured to:
turning on the first power switch, the second power switch, the third power switch, and the fourth power switch during a first period, causing the transformer circuit to release an electric energy stored in the transformer circuit, and
turning on the first power switch, the second power switch, the third power switch, and the fourth power switch during a second period after the first period, and controlling the output-side full-bridge circuit to precharge the output-side full-bridge circuit by using an energy stored in the output capacitor,
wherein a switching time point at which the first period is switched to the second period is determined by the load.

### Claim 2 (depends on 1)

The full-bridge power converter according to claim 1, wherein:
a first terminal of the first power switch is coupled to the input inductor, a second terminal of the first power switch is coupled to a first node, and a control terminal of the first power switch is coupled to the controller,
a first terminal of the second power switch is coupled to the first node, a second terminal of the second power switch is coupled to a negative power terminal of the battery module, and a control terminal of the second power switch is coupled to the controller,
a first terminal of the third power switch is coupled to the input inductor, a second terminal of the third power switch is coupled to a second node, a control terminal of the third power switch is coupled to the controller, and
a first terminal of the fourth power switch is coupled to the second node, a second terminal of the fourth power switch is coupled to the negative power terminal of the battery module, and a control terminal of the fourth power switch is coupled to the controller.

### Claim 3 (depends on 2)

The full-bridge power converter according to claim 2, wherein the primary circuit is coupled between the first node and the second node.

### Claim 4 (depends on 2)

The full-bridge power converter according to claim 2, wherein the output-side full-bridge circuit comprises:
a fifth power switch, wherein a first terminal of the fifth power switch is coupled to the first terminal of the load, a second terminal of the fifth power switch is coupled to a third node, and a control terminal of the fifth power switch is coupled to the controller;
a sixth power switch, wherein a first terminal of the sixth power switch is coupled to the third node, a second terminal of the sixth power switch is coupled to the second terminal of the load, and a control terminal of the sixth power switch is coupled to the controller;
a seventh power switch, wherein a first terminal of the seventh power switch is coupled to the first terminal of the load, a second terminal of the seventh power switch is coupled to a fourth node, and a control terminal of the seventh power switch is coupled to the controller; and
an eighth power switch, wherein a first terminal of the eighth power switch is coupled to the fourth node, a second terminal of the eighth power switch is coupled to the second terminal of the load, and a control terminal of the eighth power switch is coupled to the controller.

### Claim 5 (depends on 4)

The full-bridge power converter according to claim 4, wherein the secondary circuit is coupled between the third node and the fourth node.

### Claim 6 (depends on 4)

The full-bridge power converter according to claim 4, wherein during the first period, the controller further turns on the fifth power switch and turns off the sixth power switch, the seventh power switch, and the eighth power switch.

### Claim 7 (depends on 4)

The full-bridge power converter according to claim 4, wherein during the first period, after an electric energy stored in the transformer circuit is completely released, the output-side full-bridge circuit releases the electric energy stored in a parasitic capacitance of the seventh power switch by using the electric energy stored in the output capacitor.

### Claim 8 (depends on 4)

The full-bridge power converter according to claim 4, wherein during the second period, the controller further turns on the fifth power switch and the eighth power switch, and turns off the sixth power switch and the seventh power switch.

### Claim 9 (depends on 4)

The full-bridge power converter according to claim 4, wherein during the second period:
the output-side full-bridge circuit charges a parasitic capacitance of the seventh power switch by using the electric energy stored in the output capacitor, and
in response to a terminal voltage value of the parasitic capacitance of the seventh power switch rising to a voltage value located at the first terminal of the load, the controller turns off the first power switch, the fourth power switch, the fifth power switch, and the eighth power switch to end the second period.

### Claim 10 (depends on 4)

The full-bridge power converter according to claim 4, wherein during a third period after the second period:
the controller turns on the second power switch and the third power switch, and turns off the first power switch, the fourth power switch, the fifth power switch, the sixth power switch, the seventh power switch, and the eighth power switch, and
the input-side full-bridge circuit provides the electric energy stored in the input inductor to the transformer circuit.

### Claim 11 (depends on 10)

The full-bridge power converter according to claim 10, wherein during the third period, the output-side full-bridge circuit releases the electric energy stored in a parasitic capacitance of the sixth power switch and releases the electric energy stored in a parasitic capacitance of the seventh power switch by using the electric energy stored in the transformer circuit, and charges a parasitic capacitance of the fifth power switch and a parasitic capacitance of the eighth power switch.

### Claim 12 (depends on 11)

The full-bridge power converter according to claim 11, wherein during the third period, in response to the electric energy stored in the parasitic capacitance of the sixth power switch and the electric energy stored in the parasitic capacitance of the seventh power switch being completely released, the output-side full-bridge circuit transmits the electric energy from the transformer circuit to the load, the parasitic capacitance of the fifth power switch, and the parasitic capacitance of the eighth power switch through an intrinsic diode of the sixth power switch and an intrinsic diode of the seventh power switch.

### Claim 13 (depends on 10)

The full-bridge power converter according to claim 10, wherein during a fourth period after the third period, the controller turns on the second power switch, the third power switch, and the seventh power switch, and turns off the first power switch, the fourth power switch, the fifth power switch, the sixth power switch, and the eighth power switch.

### Claim 14 (depends on 1)

The full-bridge power converter according to claim 1, wherein the controller comprises:
a lookup table, recording a plurality of operating current values corresponding to the load and a plurality of time points of the plurality of operating current values of the load,
wherein the controller selects the switching time point from the plurality of time points based on a current operating current value of the load and a current operating voltage value of the load.

### Claim 15 (depends on 1)

The full-bridge power converter according to claim 1, wherein the battery module is implemented by one of an aluminum-ion battery and a fuel cell.