# US 2025/0156293 A1 · Data center infrastructure optimization method based on causal learning

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2025/0156293 A1
- Document ID: US20250156293A1
- Status: Published application
- Kind: A1
- Application number: 19/026,890
- Filed: 2025-01-17
- Published: 2025-05-15
- Earliest claimed: 2018-11-28
- Assignees: 3M Innovative Properties Company
- Applicants: 3M Innovative Properties Company
- Inventors: Gilles J. Benoit
- Web page: https://patentgrep.com/patent/US20250156293A1

## CPC

- G06F 11/3089: {Monitoring arrangements determined by the means or processing involved in sensing the monitored data, e.g. interfaces, connectors, sensors, probes, agents (software debugging using additional hardware using a specific debug interface G06F11/3656; performance evaluation by tracing or monitoring G06F11/3466)}
- G05B 13/021: {in which a variable is automatically adjusted to optimise the performance}
- G05B 13/024: {in which a parameter or coefficient is automatically adjusted to optimise the performance}
- G05B 13/0265: {the criterion being a learning criterion}
- G05B 15/02: electric
- G05D 23/1917: {using digital means}
- G06F 1/206: {comprising thermal management}
- G06F 11/3006: {where the computing system is distributed, e.g. networked systems, clusters, multiprocessor systems (multiprogramming arrangements G06F9/46; allocation of resources G06F9/50)}
- G06F 11/3058: {Monitoring arrangements for monitoring environmental properties or parameters of the computing system or of the computing system component, e.g. monitoring of power, currents, temperature, humidity, position, vibrations (thermal management in cooling arrangements of a computing system G06F1/206)}
- G06F 11/3409: {for performance assessment}
- G06N 7/01: Probabilistic graphical models, e.g. probabilistic networks
- G06N 20/00: Machine learning
- H05K 7/20836: {Thermal management, e.g. server temperature control}
- Y02D 10/00: Energy efficient computing, e.g. low power processors, power management or thermal management
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- G05D: SYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
- G06N: COMPUTING ARRANGEMENTS BASED ON SPECIFIC COMPUTATIONAL MODELS
- H05K: PRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
- Y02D: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE

## Abstract

Methods for active data center management by injecting randomized controlled signals in the operational controls of the cooling infrastructure of the data center and receiving response signals corresponding with the injected signals. The injected signals are used to adjust the operational controls of the cooling infrastructure, and the response signals relate to the operational conditions in the data center. Based upon the response signals along with independent and external variables, the randomized signals are continually injected into the cooling infrastructure and fine-tuned based upon the response signals. Optimum or improved parameters for controlling the cooling infrastructure of the data center are determined based upon the signal injections and corresponding responses.

## Claims

### Claim 1

A method for active data center management, comprising:
injecting randomized controlled signals into operational controls of a data center;
ensuring the signal injections occur within normal operational ranges and constraints;
monitoring performance of operational conditions in the data center in response to the controlled signals;
computing confidence intervals about the causal relationships, between the operational conditions and the controlled signals; and
monitoring the confidence intervals for changes over time as health indicators for preventive maintenance.

### Claim 2 (depends on 1)

The method of claim 1, wherein the injecting further comprises injecting the controlled signals to adjust parameters of cooling infrastructure for the data center.

### Claim 3 (depends on 1)

The method of claim 1, wherein the operational conditions comprise a temperature in the data center.

### Claim 4 (depends on 1)

The method of claim 1, wherein the injecting further comprises injecting the controlled signals into particular zones of the data center.

### Claim 5 (depends on 1)

The method of claim 1, wherein the normal operational ranges comprise a multidimensional space of possible control states generated based on control information and operational constraints.

### Claim 6 (depends on 1)

The method of claim 1, wherein the selecting further comprises selecting the optimal signals based upon external data.

### Claim 7 (depends on 1)

The method of claim 1, wherein the injecting further comprises blocking and balancing the randomized controlled signals across external variable states and minimizing carry over effects based on the measured spatial and temporal reach of effects.

### Claim 8 (depends on 1)

The method of claim 1, further comprising monitoring the performance over space and time.

### Claim 9 (depends on 1)

The method of claim 1, wherein the computing further comprises computing the confidence intervals within clusters to eliminate effect modifiers.

### Claim 10 (depends on 1)

The method of claim 1, wherein the signal injections have a spatial reach.

### Claim 11 (depends on 1)

The method of claim 1, wherein the signal injections have a temporal reach.

### Claim 12

A method for active data center management, comprising:
providing signal injections for operational controls of cooling infrastructure of a data center;
receiving response signals corresponding with the signal injections and operational conditions in the data center;
measuring a utility of the response signals;
accessing data relating to parameters for the operational controls of the cooling infrastructure of the data center; and
monitoring the utility of the response signals over time as health indicators for preventive maintenance.

### Claim 13 (depends on 12)

The method of claim 12, wherein the providing further comprises adjusting parameters of the cooling infrastructure for the data center.

### Claim 14 (depends on 12)

The method of claim 12, wherein the signal injections have a spatial reach.

### Claim 15 (depends on 12)

The method of claim 12, wherein the signal injections have a temporal reach.

### Claim 16 (depends on 12)

The method of claim 12, wherein the providing further comprises providing the signal injections into particular zones of the data center.

### Claim 17 (depends on 12)

The method of claim 12, wherein the modifying further comprises modifying the data for the operational controls based upon external data.

### Claim 18

At least one non-transitory data storage device storing instructions that, when executed, configure at least one processor to:
providing signal injections for operational controls of cooling infrastructure of a data center;
receiving response signals corresponding with the signal injections and operational conditions in the data center;
measuring a utility of the response signals;
accessing data relating to parameters for the operational controls of the cooling infrastructure of the data center; and
monitoring the utility of the response signals over time as health indicators for preventive maintenance.

### Claim 19 (depends on 18)

The at least one non-transitory data storage device of claim 18, wherein the providing further comprises providing the signal injections into particular zones of the data center.

### Claim 20 (depends on 18)

The at least one non-transitory data storage device of claim 18, wherein the signal injections are randomized.