# US 2025/0155953 A1 · Methods and systems for distributed power control of flexible datacenters

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2025/0155953 A1
- Document ID: US20250155953A1
- Status: Published application
- Kind: A1
- Application number: 19/024,994
- Filed: 2025-01-16
- Published: 2025-05-15
- Earliest claimed: 2018-09-14
- Assignees: Lancium LLC
- Applicants: Lancium LLC
- Inventors: Michael T. MCNAMARA; David J. HENSON; Raymond E. CLINE, Jr.
- Web page: https://patentgrep.com/patent/US20250155953A1

## CPC

- G06F 1/20: Cooling means
- G06F 1/3234: Power saving characterised by the action undertaken
- G06F 1/26: Power supply means, e.g. regulation thereof (for memories G11C)
- G06F 1/3203: Power management, i.e. event-based initiation of a power-saving mode
- G06F 1/324: by lowering clock frequency
- G06F 1/3287: by switching off individual functional units in the computer system
- G06F 1/329: by task scheduling
- G06F 1/3296: by lowering the supply or operating voltage
- H02J 7/35: with light sensitive cells
- H02J 9/06: with automatic change-over {, e.g. UPS systems}
- Y02B 10/70: Hybrid systems, e.g. uninterruptible or back-up power supplies integrating renewable energies
- Y02D 10/00: Energy efficient computing, e.g. low power processors, power management or thermal management
- Y02E 10/50: Photovoltaic [PV] energy
- Y02P 90/50: Energy storage in industry with an added climate change mitigation effect
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- H02J: ELECTRIC POWER NETWORKS; CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- Y02B: CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02D: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

In an example embodiment, a distributed power control system can include a datacenter and a remote master control system. The datacenter can include (i) computing systems, (ii) a behind-the-meter power input system configured to receive power from a behind-the-meter power source and deliver power to the computing systems, and (iii) a datacenter control system configured to control the computing systems and the behind-the-meter power input system. The remote master control system can be configured to issue instructions to the datacenter that affect an amount of behind-the-meter power consumed by the datacenter. The datacenter control system can receive, from a local station control system configured to at least partially control the behind-the-meter power source, a directive for the datacenter to ramp-down power consumption, and in response to receiving the directive, cause the computing systems to perform a set of predetermined operations correlated with the directive.

## Claims

### Claim 1

A distributed power control system comprising:
a flexible datacenter comprising:
(i) a plurality of computing systems powered by a behind-the-meter power input system,
(ii) the behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid and deliver the power to the plurality of computing systems, and
(iii) a datacenter control system configured to control the plurality of computing systems and the behind-the-meter power input system;
a remote master control system configured to issue instructions to the flexible datacenter that affect an amount of behind-the-meter power consumed by the flexible datacenter;
one or more processors; and
data storage comprising a first set of instructions that, when executed by the one or more processors, cause the datacenter control system to perform operations comprising:
receiving a first operational directive, wherein the first operational directive is an operational directive for the flexible datacenter to ramp-down power consumption, and
in response to receiving the first operational directive, causing the plurality of computing systems of the flexible datacenter to perform a first set of predetermined operations correlated with the first operational directive,
wherein the first operational directive is associated with a reduced power generation condition of the power generation system, wherein the reduced power generation condition is associated with an expected reduction in available behind-the-meter power below a predetermined availability level.

### Claim 2 (depends on 1)

The distributed power control system of claim 1, wherein causing the plurality of computing systems of the flexible datacenter to perform the first set of predetermined operations results in reduced consumption of the behind-the-meter power by the plurality of computing systems.

### Claim 3 (depends on 1)

The distributed power control system of claim 1, wherein the first set of predetermined operations comprise reducing a computational speed of one or more computing systems of the plurality of computing systems.

### Claim 4 (depends on 1)

The distributed power control system of claim 1, wherein the first set of predetermined operations comprise turning off one or more computing systems of the plurality of computing systems.

### Claim 5 (depends on 1)

The distributed power control system of claim 1, wherein before the datacenter control system receives the first operational directive, the plurality of computing systems are currently performing or scheduled to perform a computational task, and
wherein the first set of predetermined computational operations comprise
(i) completing a portion of the computational task,
(ii) communicating, to the datacenter control system, a result of the completed portion of the computational task, and
(iii) ramping down power consumption and entering a reduced-power operational state.

### Claim 6 (depends on 1)

The distributed power control system of claim 1, wherein the first set of predetermined operations comprise reducing a load factor of one or more computing systems of the plurality of computing systems.

### Claim 7 (depends on 1)

The distributed power control system of claim 1, wherein the data storage further comprises a second set of instructions that, when executed by the one or more processors, cause the datacenter control system to perform operations comprising:
in response to receiving the first operational directive, causing the behind-the-meter power input system to reduce the power delivered to the plurality of computing systems.

### Claim 8 (depends on 1)

The distributed power control system of claim 1, wherein the data storage further comprises a second set of instructions that, when executed by the one or more processors, cause the datacenter control system to perform operations comprising:
receiving a second operational directive from the remote master control system;
in response to receiving the second operational directive, determining whether a ramp-up condition exists; and
in response to determining that the ramp-up condition exists, causing the plurality of computing systems of the flexible datacenter to perform a second set of predetermined operations correlated with the second operational directive.

### Claim 9 (depends on 8)

The distributed power control system of claim 8, wherein the second operational directive is associated with a non-reduced power generation condition of the power generation system, and
wherein the non-reduced power generation condition is associated with a current or expected increase in available behind-the-meter power above a predetermined availability level.

### Claim 10 (depends on 8)

The distributed power control system of claim 8, wherein the second operational directive is an operational directive that the flexible datacenter is permitted to ramp-up power consumption.

### Claim 11 (depends on 8)

The distributed power control system of claim 8, wherein causing the plurality of computing systems of the flexible datacenter to perform the second set of predetermined operations results in increased consumption of the behind-the-meter power by the plurality of computing systems.

### Claim 12 (depends on 8)

The distributed power control system of claim 8, wherein the second set of predetermined operations comprise increasing the computational speed of one or more computing systems of the plurality of computing systems.

### Claim 13 (depends on 8)

The distributed power control system of claim 8, wherein the second set of predetermined operations comprise turning on one or more computing systems of the plurality of computing systems.

### Claim 14 (depends on 8)

The distributed power control system of claim 8, wherein the data storage further comprises a third set of instructions that, when executed by the one or more processors, cause the datacenter control system to perform operations that comprise:
in response to determining that the ramp-up condition exists, causing the behind-the-meter power input system to increase the power delivered to the plurality of computing systems.

### Claim 15

A method performed by a datacenter control system of a flexible datacenter, wherein the flexible datacenter further comprises
(i) a plurality of computing systems powered by a behind-the-meter power input system and
(ii) the behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid and deliver the power to the plurality of computing systems,
wherein the datacenter control system is configured to control the plurality of computing systems and the behind-the-meter power input system, and
wherein a remote master control system is configured to issue instructions to the flexible datacenter that affect an amount of behind-the-meter power consumed by the flexible datacenter, the method comprising:
receiving a first operational directive, wherein the first operational directive is an operational directive for the flexible datacenter to ramp-down power consumption; and
in response to receiving the first operational directive, causing the plurality of computing systems of the flexible datacenter to perform a first set of predetermined operations correlated with the first operational directive,
wherein the first operational directive is associated with a reduced power generation condition of the power generation system, wherein the reduced power generation condition is associated with an expected reduction in available behind-the-meter power below a predetermined availability level.

### Claim 16 (depends on 15)

The method of claim 15, further comprising:
receiving a second operational directive, wherein the second operational directive is associated with a non-reduced power generation condition of the power generation system;
in response to receiving the second operational directive, determining whether a ramp-up condition exists; and
in response to determining that the ramp-up condition exists, causing the plurality of computing systems of the flexible datacenter to perform a second set of predetermined operations correlated with the second operational directive.

### Claim 17

A non-transitory computer readable medium having stored thereon instructions, that when executed by one or more processors of a datacenter control system of a flexible datacenter, cause the datacenter control system to perform operations comprising:
receiving a first operational directive from a remote master control system,
wherein the remote master control system is configured to issue instructions to the flexible datacenter that affect an amount of behind-the-meter power consumed by the flexible datacenter,
wherein the first operational directive is an operational directive for the flexible datacenter to ramp-down power consumption,
wherein the flexible datacenter further comprises (i) a plurality of computing systems powered by a behind-the-meter power input system and (ii) the behind-the-meter power input system configured to receive power from a power generation system prior to the power undergoing step-up transformation for transmission to the grid and deliver power to the plurality of computing systems, and
wherein the datacenter control system is configured to control the plurality of computing systems and the behind-the-meter power input system; and
in response to receiving the first operational directive, causing the plurality of computing systems of the flexible datacenter to perform a first set of predetermined operations correlated with the first operational directive,
wherein the first operational directive is associated with a reduced power generation condition of the power generation system, wherein the reduced power generation condition is associated with an expected reduction in available behind-the-meter power below a predetermined availability level.

### Claim 18 (depends on 17)

The non-transitory computer readable medium of claim 17, the operations further comprising:
receiving a second operational directive from the remote master control system, wherein the second operational directive is associated with a non-reduced power generation condition of the power generation system;
in response to receiving the second operational directive, determining whether a ramp-up condition exists; and
in response to determining that the ramp-up condition exists, causing the plurality of computing systems of the flexible datacenter to perform a second set of predetermined operations correlated with the second operational directive.