# US 2025/0155880 A1 · Method of Scheduling Resources in an Industrial Process, Computer-Implemented Scheduling System, and Computer Program Product

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2025/0155880 A1
- Document ID: US20250155880A1
- Status: Published application
- Kind: A1
- Application number: 19/026,994
- Filed: 2025-01-17
- Published: 2025-05-15
- Earliest claimed: 2022-07-19
- Assignees: ABB Schweiz AG
- Applicants: ABB Schweiz AG
- Inventors: Shrikant Bhat; Ulaganathan Nallasivam
- Web page: https://patentgrep.com/patent/US20250155880A1

## CPC

- G05B 19/41865: {characterised by job scheduling, process planning, material flow}
- G05B 19/41885: {characterised by modeling, simulation of the manufacturing system}
- G05B 2219/32301: Simulate production, process stages, determine optimum scheduling rules
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)

## Abstract

A method for scheduling resources in an industrial process includes generating a model of the industrial process, and simulating the industrial process in the model. Simulating the industrial process in the model includes operations a) through e): a) determining an initial state as the current state of the industrial process model; b) selecting an allowable action from a group of possible actions for a resource; c) determining an updated state based on the selected action, and setting the current state as the updated state; d) repeating operations b) through c) until a final state is reached; and e) evaluating the updated states and/or the final state according to a predefined evaluation function.

## Claims

### Claim 1

A method of scheduling resources in an industrial process, the industrial process comprising resources comprising primary resources, wherein the primary resources are associated with a production cycle of the industrial process, the method comprising:
generating a model of the industrial process, and
simulating the industrial process in the model;
a) determining an initial state as the current state of the industrial process model;
b) selecting an allowable action from a group of possible actions for a resource;
c) determining an updated state based on the selected action, and setting the current state as the updated state;
d) repeating operations b) through c) until a final state is reached;
e) evaluating the updated states and/or the final state according to a predefined evaluation function.

### Claim 2 (depends on 1)

The method according to claim 1, wherein the allowable action is selected randomly from the group of possible actions.

### Claim 3 (depends on 1)

The method according to claim 1, the industrial process comprising resources comprising secondary resources, wherein the secondary resources comprise at least one state associated with a production cycle of the industrial process, and at least one state not associated with the production cycle.

### Claim 4 (depends on 1)

The method according to claim 1, wherein the group of possible actions of a resource is determined from a state and action matrix associated with the resource.

### Claim 5 (depends on 1)

The method according to claim 1, wherein the group of allowable actions is determined from a feasibility matrix, the feasibility matrix defining forbidden actions of a first resource depending on a state of a second resource.

### Claim 6 (depends on 1)

The method according to claim 1, wherein an iteration comprising operations b) through c) corresponds to a time period.

### Claim 7 (depends on 1)

The method according to claim 1, wherein determining the state of the industrial process model comprises evaluating parameters, the parameters comprising at least one of a resource capacity, a process time, a resource material balance and/or a resource energy balance.

### Claim 8 (depends on 7)

The method according to claim 7, wherein the parameters are stored in a parameter matrix.

### Claim 9 (depends on 1)

The method according to claim 1, further comprising:
repeatedly simulating the industrial process for a number of repeats, each repeat comprising after performing a predefined number of iterations, generating a result schedule, wherein the result schedule comprises records of the randomly selected allowable actions;
evaluating the state corresponding to the result schedule; and
selecting an optimized result schedule based on a result of the evaluation function.

### Claim 10 (depends on 1)

The method according to claim 1, wherein the evaluation function comprises evaluating the state according to one or more of:
energy consumption;
material consumption;
processed material output; and/or
time required to achieve a predefined result.

### Claim 11 (depends on 1)

The method according to claim 1, further comprising an optimization procedure comprising:
identifying trends in data generated from one or more states of the industrial process model, wherein identifying the trends includes presenting the data to an operator;
generating rules based on the identified trends; and
redefining allowable actions based on the rules.

### Claim 12 (depends on 11)

The method according to claim 11, wherein the optimization procedure includes a reinforcement learning operation.

### Claim 13 (depends on 11)

The method according to claim 11, wherein redefining allowable actions includes modifying at least one of: the state and action matrix, the feasibility matrix and/or the parameter matrix.

### Claim 14 (depends on 11)

The method according to claim 11, wherein identifying trends includes processing the data with a pattern recognition function.

### Claim 15 (depends on 14)

The method according to claim 14, wherein the pattern recognition function includes a machine learning algorithm and/or an artificial intelligence algorithm.

### Claim 16 (depends on 14)

The method according to claim 14, wherein an output of the pattern recognition function includes a fuzzy logic ruleset, particularly a set of fuzzy focal elements.

### Claim 17 (depends on 11)

The method according to claim 11, wherein the optimization procedure is executed following a trigger, the trigger comprising an operator input; and/or a change in a configuration of the industrial process model.

### Claim 18

A computer-implemented scheduling system for scheduling a process cycle of an industrial process, comprising a user interface and a software that, when executed on the scheduling system, causes the scheduling system to perform a method of scheduling resources in the industrial process, the industrial process comprising resources comprising primary resources, wherein the primary resources are associated with a production cycle of the industrial process, the method comprising:
generating a model of the industrial process, and
simulating the industrial process in the model;
a) determining an initial state as the current state of the industrial process model;
b) selecting an allowable action from a group of possible actions for a resource;
c) determining an updated state based on the selected action, and setting the current state as the updated state;
d) repeating operations b) through c) until a final state is reached;
e) evaluating the updated states and/or the final state according to a predefined evaluation function.

### Claim 19 (depends on 18)

The scheduling system according to claim 18, further comprising a network interface for connecting the device to a data network, wherein the scheduling system is operatively connected to the network interface for at least one of carrying out a command received from the data network and sending device status information to the data network.

### Claim 20

A computer program product comprising instructions stored in tangible media which, when the program is executed by a computer, cause the computer to carry out a method of scheduling resources in an industrial process, the industrial process comprising resources comprising primary resources, wherein the primary resources are associated with a production cycle of the industrial process, the method comprising:
generating a model of the industrial process, and
simulating the industrial process in the model;
a) determining an initial state as the current state of the industrial process model;
b) selecting an allowable action from a group of possible actions for a resource;
c) determining an updated state based on the selected action, and setting the current state as the updated state;
d) repeating operations b) through c) until a final state is reached;
e) evaluating the updated states and/or the final state according to a predefined evaluation function.