Work management device, work management method, and computer readable medium
AssigneeMitsubishi Electric Corporation
InventorsGosuke MINAMI, Kazuki WATANABE
Life of this patent
Estimating the term…
Abstract
A progress acceptance unit (214) accepts delay information that indicates a delay task, which is a task in which a delay may occur. An impact identification unit (23) refers to allocation relation information that indicates resources respectively allocated to a plurality of tasks so as to identify a task that is allocated the same resource as a resource allocated to the delay task indicated by the delay information accepted by the progress acceptance unit (214) as an affected task that may be affected by a delay in the delay task. A notification unit (24) notifies a person in charge of the affected task identified by the impact identification unit (23).
Claims4
A work management device comprising
- processing circuitry to:
- accept delay information that indicates a delay task, the delay task being a task in which a delay may occur;
- refer to allocation relation information that indicates resources respectively allocated to a plurality of tasks so as to identify a task that is allocated a same resource as a resource allocated to the delay task indicated by the accepted delay information as an affected task that may be affected by a delay in the delay task, and refer to dependence relation information that indicates a dependence relation between tasks so as to identify, as the affected task, a task whose requirement for execution is completion of the delay task;
- and
- notify a person in charge of the affected task by displaying information about the affected task and also information about the delay task.
A work management method comprising:
- accepting delay information that indicates a delay task, the delay task being a task in which a delay may occur;
- referring to allocation relation information that indicates resources respectively allocated to a plurality of tasks so as to identify a task that is allocated a same resource as a resource allocated to the delay task indicated by the delay information as an affected task that may be affected by a delay in the delay task, and referring to dependence relation information that indicates a dependence relation between tasks so as to identify, as the affected task, a task whose requirement for execution is completion of the delay task;
- and
- notifying a person in charge of the affected task by displaying information about the affected task and also information about the delay task.
A non-transitory computer readable medium storing a work management program that causes a computer to function as a work management device to perform:
- a progress acceptance process of accepting delay information that indicates a delay task, the delay task being a task in which a delay may occur;
- an impact identification process of referring to allocation relation information that indicates resources respectively allocated to a plurality of tasks so as to identify a task that is allocated a same resource as a resource allocated to the delay task indicated by the delay information accepted by the progress acceptance process as an affected task that may be affected by a delay in the delay task, and referring to dependence relation information that indicates a dependence relation between tasks so as to identify, as the affected task, a task whose requirement for execution is completion of the delay task;
- and
- a notification process of notifying a person in charge of the affected task by displaying information about the affected task identified by the impact identification process and also information about the delay task.
Dependencies are inferred from the claim text.