# US 2024/0418295 A1 · Non-disruptive underground pipe replacement process

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2024/0418295 A1
- Document ID: US20240418295A1
- Status: Published application
- Kind: A1
- Application number: 18/583,519
- Filed: 2024-02-21
- Published: 2024-12-19
- Earliest claimed: 2023-06-19
- Inventors: Ted R. Dimitroff
- Web page: https://patentgrep.com/patent/US20240418295A1

## CPC

- F16L 1/028: in the ground (F16L1/026 takes precedence)
- E03B 7/02: Public or like main pipe systems
- F16L: PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- E03B: INSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER (drilling wells, obtaining fluids in general from wells E21B; pipe-line systems in general F17D)

## Abstract

A method of installing a new underground pipe adjacent an existing underground pipe begins with drilling a series of substantially vertical boreholes downwardly from the ground surface so as to expose a portion of the existing pipe. Then, a pilot stem is directionally bored in a first direction adjacent the existing pipe and intersecting the bottoms of the vertical boreholes. Next, a reamer head is pulled in an opposite direction to enlarge the pilot hole, while pulling the new pipe through the enlarged hole behind the reamer head. The new pipe extends substantially parallel and adjacent the existing pipe. When the existing pipe is a water main, water service through the existing pipe is maintained during these drilling steps, until the new pipe is installed and connected for water service. The existing pipe is retained and can be repurposed for other uses.

## Claims

### Claim 1

A method of installing a new underground pipe adjacent an old underground pipe, comprising:
forming a series of substantially vertical bore holes downwardly from ground surface whereby each vertical bore hole exposes the old underground pipe while maintaining service through the old pipe;
directionally boring a pilot hole adjacent the old pipe; and
pulling a new pipe through the pilot hole while preserving the old pipe.

### Claim 2 (depends on 1)

The method of claim 1 wherein the pilot hole is drilled with a boring stem, and the boring stem is observed through the bore holes.

### Claim 3

(canceled)

### Claim 4 (depends on 1)

The method of claim 1 wherein water connected to customers via the old pipe is shut off only after the new pipe is laid.

### Claim 5 (depends on 1)

The method of claim 1 wherein the old pipe is re-purposed for use by other utilities.

### Claim 6 (depends on 1)

The method of claim 1 further comprising reaming the pilot hole to a diameter larger than the new pipe diameter.

### Claim 7 (depends on 6)

The method of claim 6 further comprising supplying liquid during the reaming to create a slurry which is expelled out of the bore holes.

### Claim 8 (depends on 1)

The method of claim 1 wherein the old and new pipes are at substantially same elevations.

### Claim 9 (depends on 1)

The method of claim 1 wherein the new pipe resides within a few inches of the old pipe.

### Claim 10 (depends on 1)

The method of claim 1 further comprising maintaining service to customers connected to the old pipe until the new pipe is installed.

### Claim 11 (depends on 1)

The method of claim 1 wherein the new pipe runs parallel to the old pipe.

### Claim 12 (depends on 1)

The method of claim 1 wherein the new pipe is spaced laterally from the old pipe.

### Claim 13 (depends on 1)

The method of claim 1 wherein the new pipe is spaced above the old pipe.

### Claim 14 (depends on 1)

The method of claim 1 wherein a supply of water to the old pipe is not shut off until the new pipe is installed.

### Claim 15 (depends on 1)

The method of claim 1 wherein the old pipe remains functional until the new pipe is installed.

### Claim 16

A replacement process for an existing underground pipe, comprising;
drilling holes downwardly from a ground surface to form bottoms of the holes adjacent the existing pipe while maintaining functionality of the existing pipe;
boring a pipe hole adjacent the existing pipe to extend through the hole bottoms;
pulling a new pipe through the pipe hole; and
maintaining service of the existing pipe while the new pipe is pulled into the pipe hole.

### Claim 17 (depends on 16)

The process of claim 16 wherein the new pipe extends parallel to the existing pipe.

### Claim 18 (depends on 16)

The process of claim 16 wherein the pipe hole is formed by a pilot stem pulled in a first direction and a reaming head pulled in an opposite second direction.

### Claim 19 (depends on 16)

The process of claim 16 wherein the existing pipe is retained for re-purposed use.

### Claim 20 (depends on 16)

The process of claim 16 further comprising providing service to the new pipe before service of the existing pipe is discontinued.