Planning system, planning method, and planning program
AssigneesKabushiki Kaisha Toshiba, Toshiba Electronic Devices & Storage Corporation
InventorKatsumi Narimatsu
Life of this patent
Estimating the term…
Abstract
According to one embodiment, a planning system includes an allocating unit configured to perform an allocation process of allocating, for each of production operations of producing products planned to be conducted on multiple planned production dates, at least one of multiple allocation materials which comprise one or more parts and one or more work-in-progress items, wherein, in the allocation process, the allocating unit calculates, for each of the production operations of producing the products for which the one or more parts are allocated, an expected consumption date representing a schedule to consume the allocated one or more parts.
Claims11
A planning system comprising
- an allocating unit configured to perform an allocation process of allocating, for each of production operations of producing products planned to be conducted on multiple planned production dates, at least one of multiple allocation materials which comprise one or more parts and one or more work-in-progress items,
- wherein, in the allocation process, the allocating unit calculates, for each of the production operations of producing the products for which the one or more parts are allocated, an expected consumption date representing a schedule to consume the allocated one or more parts.
A planning method comprising:
- allocating, for each of production operations of producing products planned to be conducted on multiple planned production dates, at least one of multiple allocation materials which comprise one or more parts and one or more work-in-progress items;
- and
- calculating, for each of the production operations of producing the products for which the one or more parts are allocated, an expected consumption date representing a schedule to consume the allocated one or more parts.
A planning program for causing a computer to:
- allocate, for each of production operations of producing products planned to be conducted on multiple planned production dates, at least one of multiple allocation materials which comprise one or more parts and one or more work-in-progress items;
- and
- calculate, for each of the production operations of producing the products for which the one or more parts are allocated, an expected consumption date representing a schedule to consume the allocated one or more parts.
Dependencies are inferred from the claim text.