# US 2024/0302827 A1 · Production planning device, production planning method, and non-transitory computer readable medium

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2024/0302827 A1
- Document ID: US20240302827A1
- Status: Published application
- Kind: A1
- Application number: 18/665,107
- Filed: 2024-05-15
- Published: 2024-09-12
- Earliest claimed: 2022-02-01
- Assignees: Mitsubishi Electric Corporation
- Applicants: Mitsubishi Electric Corporation
- Inventors: Maki KITAMURA
- Web page: https://patentgrep.com/patent/US20240302827A1

## CPC

- G05B 19/41865: {characterised by job scheduling, process planning, material flow}
- G05B 19/418: Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B 19/41885: {characterised by modeling, simulation of the manufacturing system}
- G06Q 50/04: Manufacturing
- G05B 2219/31449: Monitor workflow, to optimize business, industrial processes
- G05B 2219/32365: For resource planning
- Y02P 90/30: Computing systems specially adapted for manufacturing
- G05B: CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS (systems for controlling or regulating non-electric variables G05D; systems for regulating electric or magnetic variables G05F; control devices or systems insofar as characterised by mechanical features only G05G)
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- Y02P: CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS

## Abstract

A production planning device (100) includes a simulation unit (106). A simulation unit (106) performs a discrete simulation based on a fixed plan model indicating a work related to a fixed plan product, which is a product, and a fixed plan period, which is a period in which the work related to the fixed plan product is performed, a semi-fixed plan model indicating a preparation period for performing the work related to the fixed plan product, and a fluid plan model indicating a work related to a fluid plan product, which is a product, so as to calculate a candidate period, which is a period not overlapping with the fixed plan period, as a candidate for a fluid plan period, which is a period in which the work indicated by the fluid plan model is performed, and when at least part of the candidate period overlaps with at least part of the preparation period and in a case where preparation for performing the work related to the fixed plan product is ready at a start time of the fixed plan period, determines the candidate period as the fluid plan period.

## Claims

### Claim 1

A production planning device comprising
processing circuitry to perform a discrete simulation based on a fixed plan model, a semi-fixed plan model, and a fluid plan model, the fixed plan model being a model indicating a work related to a fixed plan product, which is a product, and a fixed plan period, which is a period in which the work related to the fixed plan product is performed, the semi-fixed plan model being a model indicating a preparation period for performing the work related to the fixed plan product, the fluid plan model being a model indicating a work related to a fluid plan product, which is a product, so as calculate a candidate period as a candidate for a fluid plan period, the candidate period being a period not overlapping with the fixed plan period, the fluid plan period being a period in which the work indicated by the fluid plan model is performed, and
when at least part of the candidate period overlaps with at least part of the preparation period and in a case where preparation for performing the work related to the fixed plan product is ready at a start time of the fixed plan period, determine the candidate period as the fluid plan period.

### Claim 2 (depends on 1)

The production planning device according to claim 1,
wherein the processing circuitry creates the semi-fixed plan model based on the fixed plan model.

### Claim 3 (depends on 1)

The production planning device according to claim 1,
wherein the processing circuitry calculates the candidate period so as to result in a short total length of a length of a preparation period for performing the work related to the fixed plan product and a length of a preparation period for performing the work related to the fluid plan product.

### Claim 4 (depends on 1)

The production planning device according to claim 1,
wherein the processing circuitry calculates the candidate period based on a state of each resource to be used in a work related to a product.

### Claim 5 (depends on 1)

The production planning device according to claim 1,
wherein the work related to the fixed plan product is one of production of the fixed plan product and a test on the fixed plan product, and
wherein the work related to the fluid plan product is one of production of the fluid plan product and a test on the fluid plan product.

### Claim 6 (depends on 1)

The production planning device according to claim 1,
wherein a length of the preparation period indicated by the semi-fixed plan model is a length of a time period required for a setup change for performing the work related to the fixed plan product.

### Claim 7

A production planning device method comprising:
performing a discrete simulation based on a fixed plan model, a semi-fixed plan model, and a fluid plan model, the fixed plan model being a model indicating a work related to a fixed plan product, which is a product, and a fixed plan period, which is a period in which the work related to the fixed plan product is performed, the semi-fixed plan model being a model indicating a preparation period for performing the work related to the fixed plan product, the fluid plan model being a model indicating a work related to a fluid plan product, which is a product, so as calculate a candidate period as a candidate for a fluid plan period, the candidate period being a period not overlapping with the fixed plan period, the fluid plan period being a period in which the work indicated by the fluid plan model is performed, and
when at least part of the candidate period overlaps with at least part of the preparation period and in a case where preparation for performing the work related to the fixed plan product is ready at a start time of the fixed plan period, determining the candidate period as the fluid plan period, by a computer.

### Claim 8

A non-transitory computer readable medium storing a production planning program that causes a production planning device, which is a computer, to execute
a simulation process of performing a discrete simulation based on a fixed plan model, a semi-fixed plan model, and a fluid plan model, the fixed plan model being a model indicating a work related to a fixed plan product, which is a product, and a fixed plan period, which is a period in which the work related to the fixed plan product is performed, the semi-fixed plan model being a model indicating a preparation period for performing the work related to the fixed plan product, the fluid plan model being a model indicating a work related to a fluid plan product, which is a product, so as calculate a candidate period as a candidate for a fluid plan period, the candidate period being a period not overlapping with the fixed plan period, the fluid plan period being a period in which the work indicated by the fluid plan model is performed, and
when at least part of the candidate period overlaps with at least part of the preparation period and in a case where preparation for performing the work related to the fixed plan product is ready at a start time of the fixed plan period, determining the candidate period as the fluid plan period.