# US 2024/0202380 A1 · A method of determining a layout of a wind energy plant

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2024/0202380 A1
- Document ID: US20240202380A1
- Status: Published application
- Kind: A1
- Application number: 18/554,689
- Filed: 2022-03-11
- Published: 2024-06-20
- Earliest claimed: 2021-04-10
- Assignees: Vestas Wind Systems A/S
- Applicants: Vestas Wind Systems A/S
- Inventors: Michael PERKINS; Buddhika ABEYRAMA; Aaron LEASE
- Web page: https://patentgrep.com/patent/US20240202380A1

## CPC

- F03D 9/257: {the wind motor being part of a wind farm}
- G06F 30/13: Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
- F03D 13/30: Commissioning, e.g. inspection, testing or final adjustment before releasing for production
- F03D 80/002: {Micro-siting, i.e. process through which the specific location or arrangement of wind turbine is determined}
- G06F 30/20: Design optimisation, verification or simulation (optimisation, verification or simulation of circuit designs G06F30/30)
- G06Q 50/06: Energy or water supply
- F05B 2260/82: Forecasts
- F05B 2260/84: Modelling or simulation
- G06F 2119/06: Power analysis or power optimisation
- F03D: WIND MOTORS
- G06F: ELECTRIC DIGITAL DATA PROCESSING (computer systems based on specific computational models G06N)
- G06Q: INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- F05B: INDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G

## Abstract

Techniques for determining a layout of a wind energy plant comprising a plurality of wind turbines at a site, where the wind turbines are configured for connection to a power grid having a power demand. Techniques include: providing an initial layout of wind turbines at initial positions within the site; obtaining site condition data for the initial layout; estimating an expected power output of the wind energy plant for a predetermined time period; forecasting the power demand within the power grid for the predetermined time period; performing an optimising process on the initial layout based on the estimated expected power output and on the forecasted power demand in order to match the expected power output to the forecasted power demand to obtain an optimised layout of the wind energy plant; and erecting the wind turbines in accordance with the optimised layout.

## Claims

### Claim 1

A method of determining a layout of a wind energy plant comprising a plurality of wind turbines at a site, the wind turbines being configured for connection to a power grid having a power demand, the method comprising:
providing an initial layout by arranging the plurality of wind turbines at initial positions within the site;
obtaining site condition data for the initial positions of the plurality of wind turbines, wherein the site condition data comprises expected wind speed data;
estimating an expected power output of the wind energy plant based on the initial layout and on the site condition data for a predetermined time period;
forecasting the power demand within the power grid for the predetermined time period;
performing an optimising process on the initial layout based on the estimated expected power output and on the forecasted power demand in order to match the expected power output to the forecasted power demand to obtain an optimised layout of the wind energy plant; and
erecting the wind turbines in accordance with the optimised layout.

### Claim 2 (depends on 1)

The method of claim 1, wherein the performing the optimising process comprises a step of changing the position of at least one of the wind turbines.

### Claim 3 (depends on 2)

The method of claim 2, wherein the performing the optimising process further comprises a step of obtaining site condition data for the changed position of the at least one wind turbine.

### Claim 4 (depends on 1)

The method of claim 1, wherein the site condition data further comprises estimated wind direction data.

### Claim 5 (depends on 1)

The method of claim 1, wherein the site condition data is based at least partly on meteorological data obtained at the site during a measurement period.

### Claim 6 (depends on 5)

The method of claim 5, wherein the measurement period is at least one year.

### Claim 7 (depends on 1)

The method of claim 1, wherein the site condition data represents variations as a function of time of year.

### Claim 8 (depends on 1)

The method of claim 1, wherein the site condition data represents variations as a function of time of day.

### Claim 9 (depends on 1)

The method of claim 1, wherein the providing an initial layout is based on at least one of historical meteorological data and terrain data.

### Claim 10 (depends on 1)

The method of claim 1, wherein the estimating the expected power output of the wind energy plant comprises a step of estimating an expected power output of each of the wind turbines individually.

### Claim 11

A method of determining a layout of a wind energy plant comprising a plurality of wind turbines at a site, the wind turbines being configured for connection to a power grid having a power demand, the method comprising:
estimating an expected power output of the wind energy plant based on at least two inputs for a predetermined time period; the at least two inputs comprising:
an initial layout of the plurality of wind turbines arranged at initial positions within the site; and
site condition data for the initial positions of the plurality of wind turbines, wherein the site condition data comprises expected wind speed data;
forecasting the power demand within the power grid for the predetermined time period; and
generating an optimised layout of the wind energy plant by performing an optimising process on the initial layout based on the estimated expected power output and on the forecasted power demand in order to match the expected power output to the forecasted power demand.