# US 2024/0199327 A1 · Shuttle system and method for handling a load carrier

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2024/0199327 A1
- Document ID: US20240199327A1
- Status: Published application
- Kind: A1
- Application number: 18/373,522
- Filed: 2023-09-27
- Published: 2024-06-20
- Earliest claimed: 2022-09-27
- Assignees: Gebhardt Fordertechnik GmbH
- Applicants: Gebhardt Fördertechnik GmbH
- Inventors: Marco Gebhardt; Thomas Klopfenstein
- Web page: https://patentgrep.com/patent/US20240199327A1

## CPC

- B65G 1/0485: {Check-in, check-out devices}
- B65G 1/0492: {with cars adapted to travel in storage aisles}
- B65G 1/00: Storing articles, individually or in orderly arrangement, in warehouses or magazines (conveyor combinations in warehouses, magazines or workshops B65G37/00; stacking of articles B65G57/00; removing articles from stacks B65G59/00; loading machines B65G65/02)
- B65G 1/065: {with self propelled cars}
- B65G 1/1376: {the orders being assembled on a commissioning conveyor}
- B65G 2201/0267: Pallets
- B65G: TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS (packaging B65B; handling thin or filamentary materials, e.g. paper sheets or thread, B65H; cranes B66C; portable mobile or lifting or hauling appliances, e.g. hoists, B66D; devices for lifting or lowering goods for loading or unloading purposes, e.g. fork-lift trucks, B66F9/00; emptying bottles, jars, casks, barrels or similar containers, not otherwise provided for, B67C9/00; delivering or transferring liquids B67D; filling or discharging vessels for liquefied, solidified or compressed gases F17C; pipe-line systems for fluids F17D)

## Abstract

A method is disclosed for handling a load carrier that can be stored or removed from a rack structure. In an embodiment the method includes temporary storage of the load carrier in a buffer area, which may also serve as a transfer area to a vertical conveyor, or passing through the buffer area to transport the load carrier in a storage and retrieval area level to be moved in or out.

## Claims

### Claim 1

A shuttle system, comprising:
a rack structure with a storage and retrieval level and at least one warehouse level for storing load carriers,
a vertical conveyor for transporting load carriers between the levels of the rack structure,
at least one shuttle arranged to travel in the levels of the rack structure,
at least one buffer location, which is situated in the storage and retrieval level directly next to the vertical conveyor, the at least one buffer location is set up to temporarily receive a load carrier, and the at least one buffer location comprises a transfer section on a storage side, on a pre-zone side, and on a vertical conveyor side for receiving and delivering the load carrier,
wherein the at least one shuttle is further set up to transfer a load carrier to be retrieved to the buffer location and to take over a load carrier to be stored from the buffer location, wherein this takeover and handover is performed via the transfer section on the storage side,
wherein the buffer location is further set up to take over or hand over a load carrier also from or to a conveyor acting as an interface between the storage and retrieval level and a zone located outside the rack levels, wherein the takeover and handover is performed via the transfer section on the pre-zone side,
wherein the vertical conveyor is operable to transfer the load carrier from the buffer location to the vertical conveyor or take the load carrier over from the vertical conveyor, wherein the takeover and transfer is performed via the transfer section on the vertical conveyor side,
wherein a direction along which the buffer location transfers the load carrier to or takes the load carrier over from the conveyor acting as an interface runs parallel to a direction along which the at least one shuttle transfers the load carrier to or takes the load carrier over from the buffer location, and
wherein a direction along which the vertical conveyor transfers the load carrier to or takes the load carrier over from the buffer location runs orthogonally to the direction along which the conveyor acting as an interface transfers the load carrier to or takes the load carrier over from the buffer location.

### Claim 2 (depends on 1)

The shuttle system according to claim 1, wherein at least one further buffer location between the pre-zone-side transfer section and the conveyor acting as the interface.

### Claim 3 (depends on 1)

The shuttle system according to claim 1, wherein the vertical conveyor includes a fork operable to actively transport the load carrier from the buffer location to the vertical conveyor and back.

### Claim 4 (depends on 1)

The shuttle system according to claim 1, wherein two directly adjacent buffer locations are assigned to the vertical conveyor.

### Claim 5 (depends on 1)

The shuttle system according to claim 1, wherein at least one further buffer location adjoins the transfer section on the storage side.

### Claim 6 (depends on 1)

The shuttle system according to claim 1, wherein the buffer locations are formed by a continuous conveyor.

### Claim 7 (depends on 1)

The shuttle system according to claim 1, wherein at least one centering means is arranged to center a load carrier after it has been delivered by the conveyor acting as an interface and before it has been taken over by the at least one shuttle or by the vertical conveyor.

### Claim 8 (depends on 1)

The shuttle system according to claim 1, wherein at least one transfer section is arranged to temporarily take over a load carrier, and the transfer section further comprises at least one centering means, which is arranged to center a load carrier when the load carrier is set down on the transfer section by the at least one shuttle or the vertical conveyor.

### Claim 9 (depends on 8)

The shuttle system according to claim 8, wherein the transfer section comprises two parking rails for parking the load carrier, wherein a centering means is situated on each of the two parking rails, and wherein a clear width between the centering means corresponds at least to the clear width between the two parking rails.

### Claim 10

A method for handling a load carrier, wherein a storing or retrieving of the load carrier is performed in or from a rack structure, the method comprising:
temporarily storing the load carrier on a buffer location, which at the same time serves as a transfer section to a vertical conveyor, or passing this buffer location to store the load carrier in a storage and retrieval level or retrieve the load carrier from the storage and retrieval level.

### Claim 11 (depends on 10)

The method according to claim 10, wherein a storing of the load carrier is performed in the rack structure, wherein:
a conveyor conveys the load carrier to the storage and retrieval level, where the load carrier is conveyed to the buffer location,
if the load carrier is supposed to be stored in the storage and retrieval level, the load carrier passes the buffer location and is taken over by a shuttle running in the storage and retrieval level, and
if the load carrier is supposed to be stored in a warehouse level, the load carrier is taken over at the buffer location by the vertical conveyor and transported to the warehouse level.

### Claim 12 (depends on 10)

The method according to claim 10, wherein a retrieval of the load carrier from the rack structure is performed, wherein:
the shuttle or the vertical conveyor conveys the load carrier to the buffer location, and
a conveyor takes over the load carrier.

### Claim 13 (depends on 10)

The method according to claim 10, wherein the load carrier is temporarily stored on a further buffer location before being temporarily stored on the buffer location or passing the buffer location if the buffer location is occupied by another load carrier.

### Claim 14 (depends on 10)

The method according to claim 10, wherein the load carrier is temporarily stored on a further buffer location before being temporarily stored on the buffer location or passing the buffer location if the buffer location is occupied by another load carrier.

### Claim 15 (depends on 1, 10)

The method according to claim 10, which is performed with a shuttle system according to claim 1.

### Claim 16 (depends on 3)

The shuttle system according to claim 3, wherein the fork comprises two tines.

### Claim 17 (depends on 16)

The shuttle system according to claim 16, wherein the fork comprises a telescopic fork.

### Claim 18 (depends on 17)

The shuttle system according to claim 17, wherein the telescopic fork comprises two tines.