Method and device for managing project
AssigneeSamsung Engineering Co., Ltd.
InventorsWon Sang CHUNG, Hoon Yi KEUN, Baek Hun SONG, Hyun Il LEE, Hyeon Gi BAEK, Hyo Jin KIM, Eun Hye KWON
Life of this patent
Estimating the term…
Abstract
According to a preferred embodiment of the present disclosure, a project management device includes: a division unit configured to divide a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and a display unit configured to classify the n CWPs according to construction statuses and work front statuses and display the n CWPs in a grid form.
Claims17
A project management device comprising:
- a division unit configured to divide a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information;
- and
- a display unit configured to classify the n CWPs according to construction statuses and work front statuses and display the n CWPs in a grid form,
- wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses, wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status,
- wherein in a rightward direction along the horizontal axis, a construction status of a started construction is shown, and then a construction status of a non-started construction is shown,
- wherein when the construction type is piping, the work front statuses are calculated separately based on present and future, wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, wherein the three independent sequential simulations are performed in an order of:
- a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping;
- an ISO drawing that is a drawing before preparing a detailed construction drawing;
- and 3D that is a drawing before preparing a line drawing.
(canceled)
(canceled)
A project management method comprising:
- dividing, a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information;
- and
- classifying, by a display unit, the n CWPs according to construction statuses and work front statuses and displaying the n CWPs in a grid form on the display unit,
- wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses, wherein each of grid boxes the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status,
- wherein in a rightward direction along the horizontal axis, a construction status of a started construction is shown, and then a construction status of a non-started construction is shown,
- wherein when the construction type is piping, the work front statuses are calculated separately based on present and future, wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, wherein the three independent sequential simulations are performed in an order of:
- a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping;
- an ISO drawing that is a drawing before preparing a detailed construction drawing;
- and 3D that is a drawing before preparing a line drawing.
(canceled)
(canceled)
A project management method comprising:
- dividing, a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information;
- and
- classifying, by a display unit, the n CWPs according to construction statuses and work front statuses and displaying the n CWPs in a grid form on the display unit,
- wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses, wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status,
- wherein the project management method further comprises selecting only CWPs corresponding to a grid box from the n CWPs by filtering when the information on the number of CWPs in the grid box is clicked, wherein detailed information on the selected CWPs are shown.
(canceled)
Dependencies are inferred from the claim text.