# US 2024/0186940 A1 · Installation method and installation equipment for photovoltaic module in photovoltaic field area, and photovoltaic array

> Agents: this data is available as JSON from the patentgrep API and MCP server — see https://patentgrep.com/llms.txt

- Number: US 2024/0186940 A1
- Document ID: US20240186940A1
- Status: Published application
- Kind: A1
- Application number: 18/437,261
- Filed: 2024-02-09
- Published: 2024-06-06
- Earliest claimed: 2021-08-12
- Assignees: Ting CHEN; Chunhua HAN
- Inventors: Chunhua HAN
- Web page: https://patentgrep.com/patent/US20240186940A1

## CPC

- H02S 20/30: Supporting structures being movable or adjustable, e.g. for angle adjustment
- B66D 1/30: Rope, cable, or chain drums or barrels
- H02S 20/00: Supporting structures for PV modules
- H02S 20/10: Supporting structures directly fixed to the ground (H02S20/30 takes precedence)
- H10F 19/20: comprising photovoltaic cells in arrays in or on a single semiconductor substrate, the photovoltaic cells having planar junctions (having multiple thin-film photovoltaic cells deposited on the same substrate H10F19/31)
- Y02E 10/50: Photovoltaic [PV] energy
- H02S: GENERATION OF ELECTRIC POWER BY CONVERSION OF INFRARED RADIATION, VISIBLE LIGHT OR ULTRAVIOLET LIGHT, e.g. USING PHOTOVOLTAIC [PV] MODULES (obtaining electrical energy from radioactive sources G21H1/12; light sensitive inorganic semiconductor devices H10F; light sensitive organic semiconductor devices H10K30/00; thermoelectric devices H10N10/00; pyroelectric devices H10N15/00)
- B66D: CAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS (winding or unwinding ropes or cables for feeding or storage purposes B65H; rope or cable winding or unwinding mechanisms for lifts B66B)
- H10F: INORGANIC SEMICONDUCTOR DEVICES SENSITIVE TO INFRARED RADIATION, LIGHT, ELECTROMAGNETIC RADIATION OF SHORTER WAVELENGTH OR CORPUSCULAR RADIATION
- Y02E: REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION

## Abstract

Disclosed are an installation method and installation equipment for a photovoltaic module in a photovoltaic field area, and a photovoltaic array, applied in the technical field of photovoltaic installation. The installation method includes determining a photovoltaic field area and laying a traction rope; mounting a photovoltaic module on the traction rope and feeding the traction rope, until arriving at an installation area; securing two ends of the traction rope; and moving to a next installation position and repeating to carry out installation. The installation equipment includes an unwinding device, a traction rope, a winding device, a photovoltaic support, a stock bin, an unloading apparatus, a snap-fit structure and a track. The method can carry out large-scale and batch installation in a photovoltaic field area, the process is standardized, and quality of installation is ensured, thereby achieving process-oriented processing, reducing labor input, saving costs, and implementing cost-effective batch installation.

## Claims

### Claim 1

An installation method for a photovoltaic module in a photovoltaic field area, comprising the steps of:
using a transmitter, generating and transmitting a baseband transmission signal by:
S1, determining an installation area of a photovoltaic field area, and laying a traction rope traversing the installation area from a first side to an opposite second side of the installation area;
S2, feeding the traction rope from the first side of the installation area to the second side thereof, mounting photovoltaic modules on the traction rope at the first side of the installation area, moving the photovoltaic modules along with the traction rope, feeding until a row of photovoltaic modules is moved to the installation area, and then stopping; and
S3, securing two ends of the traction rope at the first side and the second side of the installation area, respectively, to complete the installation of the row of photovoltaic modules.

### Claim 2 (depends on 1)

The installation method for the photovoltaic module in the photovoltaic field area according to claim 1, wherein the installation of a next row or more rows of photovoltaic modules further comprises the steps of:
S4, moving to an installation position parallel to a previous row of photovoltaic modules, re-arranging the traction rope, completing the installation of a next row of photovoltaic modules according to Steps S2-S3, and repeating this step until all the photovoltaic modules in the installation area are installed.

### Claim 3 (depends on 1)

The installation method for the photovoltaic module in the photovoltaic field area according to claim 1, wherein in Steps S2-S3, the traction rope is kept under tension throughout the feeding process until the installation is completed.

### Claim 4 (depends on 3)

The installation method for the photovoltaic module in the photovoltaic field area according to claim 3, wherein in Step S2, when the photovoltaic modules are installed on the traction rope, a plurality of photovoltaic modules are installed in sequence as a group; at least one photovoltaic module is installed at a time; and photovoltaic modules of adjacent groups are installed at intervals.

### Claim 5 (depends on 4)

The installation method for the photovoltaic module in the photovoltaic field area according to claim 4, wherein that in Step S1, at least two traction ropes are laid; the distance between adjacent traction ropes is less than the length or width of one photovoltaic module; and the distance between adjacent traction ropes is kept constant.

### Claim 6 (depends on 3)

The installation method for the photovoltaic module in the photovoltaic field area according to claim 3, wherein in Step S2, an unwinding device is arranged on a first side of the installation area; a winding device is arranged on a second side of the installation area; two ends of the traction rope are respectively connected to the unwinding device and the winding device; the traction rope is fed by the unwinding device, and the winding device synchronously receives the traction rope to complete the feeding of the traction rope from the first side to the second side; and in Step S3, the traction rope is firstly disconnected from the unwinding device and the winding device, and then both ends of the traction rope are fixed.

### Claim 7 (depends on 6)

The installation method for the photovoltaic module in the photovoltaic field area according to claim 6, wherein in Step S2, a track is provided on a first side and a second side of the installation area, respectively, and the unwinding device and the winding device are installed on the track; and the unwinding device and the winding device are movable relative to the installation area in a sliding manner.

### Claim 8 (depends on 3)

The installation method for the photovoltaic module in the photovoltaic field area according to claim 3, wherein in Step S1, before the traction rope are laid, the installation area is laid with a plurality of photovoltaic supports; the traction ropes rest on the photovoltaic supports; and the feeding direction of the traction ropes coincides with the arrangement direction of the plurality of photovoltaic supports.

### Claim 9 (depends on 1)

An installation equipment for a photovoltaic module in a photovoltaic field area, capable of using the installation method according to any one of claim 1, comprising an unwinding device, a traction rope, a winding device, a photovoltaic support, a stock bin, an unloading apparatus, a snap-fit structure and a track; wherein the plurality of photovoltaic supports are provided at intervals in an installation area of the photovoltaic field area; at least two traction ropes together traverse the plurality of photovoltaic supports; the unwinding device and the winding device are respectively provided at two ends outside the photovoltaic field area; the bottoms of the unwinding device and the winding device are respectively provided with a track along the edge direction of the installation area; the two ends of the traction rope are respectively connected to the unwinding device and the winding device, wherein the unwinding device is used for feeding the traction rope, and the winding device is used for receiving the traction rope; the stock bin and the unloading apparatus are mounted beside the unwinding device; a plurality of photovoltaic modules are placed in the stock bin; the unloading apparatus is used for transferring the photovoltaic modules from the stock bin to the traction rope; and the snap-fit structure is used for clamping and fixing the photovoltaic modules and the traction rope.

### Claim 10 (depends on 1)

A photovoltaic array for a photovoltaic module in a photovoltaic field area, obtained using the installation method according to claim 1, wherein it comprises at least two traction ropes and at least one row of photovoltaic modules in a photovoltaic field area, wherein one row of the photovoltaic modules is divided into multiple groups; each group of photovoltaic modules is arranged along the direction of the traction ropes, and adjacent groups of photovoltaic modules have a spacing there between; and all the photovoltaic modules are arranged in an array on the traction ropes.